PPMP 20013 Project Management: Developing a Tender Request Document
VerifiedAdded on  2023/06/11
|8
|2380
|263
Report
AI Summary
This report provides a comprehensive analysis of a tender request developed for a large asset project, adhering to the guidelines of AS 4120-1994. The project involves constructing a 50-story building complex in Australia, with Laing O'Rourke responsible for the construction work. The report covers various aspects of the tender process, including principal obligations, tenderer obligations, financing justification, contractual terms (referencing AS 4000-1997), quality assurance and control requirements (referencing AS ISO 10014-2007), and safety requirements (referencing AS/NZS 4804-2001). Key elements such as project definition, documentation, selection, methodologies, and associated inquiries are discussed. The financial aspects, including sources of funds and project selection criteria, are also examined. Contractual terms related to service, subcontracting, statutory requirements, testing, progress, suspension, costs, defects, variations, payments, insolvency, termination, claims, and dispute resolution are detailed. Furthermore, the report addresses quality assurance and control, emphasizing customer quality, leadership, people involvement, methodological and systematic approaches, continuous improvement, and mutual benefits. Finally, safety requirements, including safety management, measurement, configuration, planning, and OHS policy, are covered.

PPMP 20013 PROJECT MANAGEMENT FOR OPERATORS OF LAEGE
ASSETS
TUTOR –
SUBJECT – THE TENDER, WRITTEN ASSESSMENT
PREPERED BY –
ASSETS
TUTOR –
SUBJECT – THE TENDER, WRITTEN ASSESSMENT
PREPERED BY –
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1. Reflection of AS 4120-1994
1.1 Making proper decisions
The Making proper decisions is prepared according to the AS 4120-1994 as
prescribed in the section 3 page.5
The project tender has planned to build for constructing a 50 storey building complex at Australia
1.2 Statement related to ethics
The definition is prepared according to the AS 4120-1994 as prescribed in the
section 4 page.5
1.3 Tendering methodologies, which includes:-
1.3.1 Principal Obligations: -
1.3.1.1 Project Define
The Project Define is prepared according to the AS 4120-1994 as prescribed in the section 6.1.1
page.6
A 50 storey building complex has been planned to construct at Australia. Laing O'Rourke has taken
the responsibility to carry out the construction work for the project. The project manager will
develop the project plan. Project manager prepared plan will consist of the list of activities that need
to be carried out. The stakeholders for the project will carry out the project activities and they will
have to complete the project within stipulated deadline and the budget. The construction project
will contain all the necessary activities that need to be carried out. The project plan will contain all
the activities related to the project activities and that needs to be carried out. The project will
contain the primary list of activities and they are contracts, documents and revision, bids and
contracts, detailed review of bids, grading and building permits. Other than all these activities the
project will contain the site work, foundation, rough carpentry, construction of concrete slabs. All
these activities will be conducted by the construction department and the builder. The electrician
will take up the responsibility to set up HVAC. It is the responsibility of the plumber to setup the
Plumbing Rough-in. The masons and the builders will conduct the work on roofing, exterior finishes,
insulation, drywall, and the floor finishes. The painter and the decorators will carry out the painting
works for the building. In this way the entire project will be completed as per deliverables.
1.3.1.2 Documentation related to Tender
The documentation related to tender is prepared according to the AS 4120-1994 as prescribed in the
section 6.1.2
ï‚· The following information is provided by the tender document-
ï‚· The tender will cater full works details
ï‚· The specific conditions required for the tender are described and along with that the
supporting information from the tenderers are identified and diagnosed
ï‚· The validity period of tender is specified
ï‚· The lodgement date for the tenders are provided along with its methods and appropriate
openings
1.3.1.3 Selection related to tenders
The selection related to tender is prepared according to the AS 4120-1994 as prescribed in the
section 6.1.3 page.7
1.1 Making proper decisions
The Making proper decisions is prepared according to the AS 4120-1994 as
prescribed in the section 3 page.5
The project tender has planned to build for constructing a 50 storey building complex at Australia
1.2 Statement related to ethics
The definition is prepared according to the AS 4120-1994 as prescribed in the
section 4 page.5
1.3 Tendering methodologies, which includes:-
1.3.1 Principal Obligations: -
1.3.1.1 Project Define
The Project Define is prepared according to the AS 4120-1994 as prescribed in the section 6.1.1
page.6
A 50 storey building complex has been planned to construct at Australia. Laing O'Rourke has taken
the responsibility to carry out the construction work for the project. The project manager will
develop the project plan. Project manager prepared plan will consist of the list of activities that need
to be carried out. The stakeholders for the project will carry out the project activities and they will
have to complete the project within stipulated deadline and the budget. The construction project
will contain all the necessary activities that need to be carried out. The project plan will contain all
the activities related to the project activities and that needs to be carried out. The project will
contain the primary list of activities and they are contracts, documents and revision, bids and
contracts, detailed review of bids, grading and building permits. Other than all these activities the
project will contain the site work, foundation, rough carpentry, construction of concrete slabs. All
these activities will be conducted by the construction department and the builder. The electrician
will take up the responsibility to set up HVAC. It is the responsibility of the plumber to setup the
Plumbing Rough-in. The masons and the builders will conduct the work on roofing, exterior finishes,
insulation, drywall, and the floor finishes. The painter and the decorators will carry out the painting
works for the building. In this way the entire project will be completed as per deliverables.
1.3.1.2 Documentation related to Tender
The documentation related to tender is prepared according to the AS 4120-1994 as prescribed in the
section 6.1.2
ï‚· The following information is provided by the tender document-
ï‚· The tender will cater full works details
ï‚· The specific conditions required for the tender are described and along with that the
supporting information from the tenderers are identified and diagnosed
ï‚· The validity period of tender is specified
ï‚· The lodgement date for the tenders are provided along with its methods and appropriate
openings
1.3.1.3 Selection related to tenders
The selection related to tender is prepared according to the AS 4120-1994 as prescribed in the
section 6.1.3 page.7

Laing O'Rourke will carry out the construction work. They will select the best person for the business
1.3.1.4 Calling tenders
The calling tenders is prepared according to the AS 4120-1994 as prescribed in the section 6.2.2
page.7
It involves all the work description associated with the project; it will contain all the necessary details
about the tender like the closing details of the tender. The tender will contain the name , adres and
the telephone number of the customers.
1.3.1.5 Methodologies related to tendering
The methodologies related to tender is prepared according to the AS 4120-1994 as prescribed in the
section 6.2.3 page.8
1.3.1.6 Construction Project Associated Inquiries related to tenders
The Construction Project Associated inquiries related to tender is prepared according to the AS
4120-1994 as prescribed in the section 6.2.4 page.8
Construction Project Associated Inquiries details can be found on info@bacmajorprojects.com.au
1.3.1.7 Construction Project Associated Alternates made in tender documents
The Construction Project Associated alternates made in the tender is prepared according to the AS
4120-1994 as prescribed in the section 6.2.5 page.8
1.3.1.8 Construction Project Associated Tenders received
The Project Associated tenders received is prepared according to the AS 4120-1994 as prescribed in
the section 6.3 page.9
1.3.1.9 Construction Project Associated Tenders closure
The Construction Project Associated tenders closure is prepared according to the AS 4120-1994 as
prescribed in the section 6.4 page.9
1.3.1.10 Construction Project Associated Calculating Tenders
The Construction Project Associated calculating tenders is prepared according to the AS 4120-1994
as prescribed in the section 6.5 page.9
1.3.1.11 Construction Project Associated Negotiation as well as selection
The Construction Project Associated negotiation as well as selection related to tender is prepared
according to the AS 4120-1994 as prescribed in the section 6.6 page.10
1.3.2 Tenderers Obligations: -
1.3.2.1 Belief
The belief related to tender is prepared according to the AS 4120-1994 as prescribed in the section
7.1 page.10
1.3.2.2 Construction Project Associated Return of Documents
The Construction Project Associated return of documents related to tender is prepared according to
the AS 4120-1994 as prescribed in the section 7.2 page.10
1.3.2.3 Construction Project Associated Tender documentation monitoring
The Construction Project Associated tender documentation monitoring related to tender is prepared
according to the AS 4120-1994 as prescribed in the section 7.3 page.10
1.3.2.4 Formulation of tender and estimates with respect to:-
1.3.2.4.1 Project labour
The project creates opportunity for 7800 people for the people of Australia until 2020
1.3.1.4 Calling tenders
The calling tenders is prepared according to the AS 4120-1994 as prescribed in the section 6.2.2
page.7
It involves all the work description associated with the project; it will contain all the necessary details
about the tender like the closing details of the tender. The tender will contain the name , adres and
the telephone number of the customers.
1.3.1.5 Methodologies related to tendering
The methodologies related to tender is prepared according to the AS 4120-1994 as prescribed in the
section 6.2.3 page.8
1.3.1.6 Construction Project Associated Inquiries related to tenders
The Construction Project Associated inquiries related to tender is prepared according to the AS
4120-1994 as prescribed in the section 6.2.4 page.8
Construction Project Associated Inquiries details can be found on info@bacmajorprojects.com.au
1.3.1.7 Construction Project Associated Alternates made in tender documents
The Construction Project Associated alternates made in the tender is prepared according to the AS
4120-1994 as prescribed in the section 6.2.5 page.8
1.3.1.8 Construction Project Associated Tenders received
The Project Associated tenders received is prepared according to the AS 4120-1994 as prescribed in
the section 6.3 page.9
1.3.1.9 Construction Project Associated Tenders closure
The Construction Project Associated tenders closure is prepared according to the AS 4120-1994 as
prescribed in the section 6.4 page.9
1.3.1.10 Construction Project Associated Calculating Tenders
The Construction Project Associated calculating tenders is prepared according to the AS 4120-1994
as prescribed in the section 6.5 page.9
1.3.1.11 Construction Project Associated Negotiation as well as selection
The Construction Project Associated negotiation as well as selection related to tender is prepared
according to the AS 4120-1994 as prescribed in the section 6.6 page.10
1.3.2 Tenderers Obligations: -
1.3.2.1 Belief
The belief related to tender is prepared according to the AS 4120-1994 as prescribed in the section
7.1 page.10
1.3.2.2 Construction Project Associated Return of Documents
The Construction Project Associated return of documents related to tender is prepared according to
the AS 4120-1994 as prescribed in the section 7.2 page.10
1.3.2.3 Construction Project Associated Tender documentation monitoring
The Construction Project Associated tender documentation monitoring related to tender is prepared
according to the AS 4120-1994 as prescribed in the section 7.3 page.10
1.3.2.4 Formulation of tender and estimates with respect to:-
1.3.2.4.1 Project labour
The project creates opportunity for 7800 people for the people of Australia until 2020
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

1.3.2.4.2 50 storey Building Construction Site
The 50 storey Building Construction Site is located at the 5 km from the nearby rail station.
1.3.2.4.3 50 storey Building Construction Project Resources
The subcontractors use the sand, cement and other resources required for constructing the building.
1.3.2.4.4 50 storey Building Construction Project sub-contractors
Laing O'Rourke has been given the charge to construct the 5 storey building.
1.3.2.5 Construction Project Associated Tenders submit
Construction Project Associated tender submit is prepared according to the AS 4120-1994 as
prescribed in the section 7.5 page.11
1.4 Confidentiality
The confidentiality related to tender is prepared according to the AS 4120-1994 as prescribed in the
section 8 page.11
The 50 storey Building Construction Site is located at the 5 km from the nearby rail station.
1.3.2.4.3 50 storey Building Construction Project Resources
The subcontractors use the sand, cement and other resources required for constructing the building.
1.3.2.4.4 50 storey Building Construction Project sub-contractors
Laing O'Rourke has been given the charge to construct the 5 storey building.
1.3.2.5 Construction Project Associated Tenders submit
Construction Project Associated tender submit is prepared according to the AS 4120-1994 as
prescribed in the section 7.5 page.11
1.4 Confidentiality
The confidentiality related to tender is prepared according to the AS 4120-1994 as prescribed in the
section 8 page.11
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

2. Financing justification and financial
arrangements of the project by the Principal,
including:-
2.1 Construction Project Source of funds, i.e. capital funds or
operational expenses
The total budget that is required to build the 5 storey building is close to $1.3 million
2.2 Project selection criteria:-
Cash inflow and the cash outflow are considered for the project and it assist in calculating the net
benefits that the project can earn. There are several methods by which the value of the project is
calculated like the unadjusted rate of returns and the payback period method.
3. Contractual terms, including: -
3.1 Construction Project associated Contract Type
The Construction Project contract type related to tender is prepared according to the AS 4000-1997
as prescribed in the clause 2 page.5
3.2 Construction Project associated Notices related Service
The Construction Project associated notices related service is prepared according to the AS 4000-
1997 as prescribed in the clause 7 page.9
3.3 Construction Project associated Subcontracting and
Assignment
The Construction Project associated Subcontracting and Assignment is prepared according to the AS
4000-1997 as prescribed in the clause 9 page.10
3.4 Construction Project associated Requirements related to
statutory
The Construction Project associated requirements related to statutory is prepared according to the
AS 4000-1997 as prescribed in the clause 11 page.12
3.5 Construction Project associated Assessing and Testing
The Construction Project associated assessing and testing related to tender is prepared according to
the AS 4000-1997 as prescribed in the clause 30 page.24
3.6 Construction Project associated Works Progress as well
as Construction Project associated Works Programming
The Construction Project associated Works Progress related to tender is prepared according to the
AS 4000-1997 as prescribed in the clause 34.1 page.27
The Construction Project associated Works Programming related to tender is prepared according to
the AS 4000-1997 as prescribed in the clause 32 page.25
3.7 Construction Project associated Activities Suspension
The Construction Project associated activities suspension related to tender is prepared according to
the AS 4000-1997 as prescribed in the clause 33 page.26
arrangements of the project by the Principal,
including:-
2.1 Construction Project Source of funds, i.e. capital funds or
operational expenses
The total budget that is required to build the 5 storey building is close to $1.3 million
2.2 Project selection criteria:-
Cash inflow and the cash outflow are considered for the project and it assist in calculating the net
benefits that the project can earn. There are several methods by which the value of the project is
calculated like the unadjusted rate of returns and the payback period method.
3. Contractual terms, including: -
3.1 Construction Project associated Contract Type
The Construction Project contract type related to tender is prepared according to the AS 4000-1997
as prescribed in the clause 2 page.5
3.2 Construction Project associated Notices related Service
The Construction Project associated notices related service is prepared according to the AS 4000-
1997 as prescribed in the clause 7 page.9
3.3 Construction Project associated Subcontracting and
Assignment
The Construction Project associated Subcontracting and Assignment is prepared according to the AS
4000-1997 as prescribed in the clause 9 page.10
3.4 Construction Project associated Requirements related to
statutory
The Construction Project associated requirements related to statutory is prepared according to the
AS 4000-1997 as prescribed in the clause 11 page.12
3.5 Construction Project associated Assessing and Testing
The Construction Project associated assessing and testing related to tender is prepared according to
the AS 4000-1997 as prescribed in the clause 30 page.24
3.6 Construction Project associated Works Progress as well
as Construction Project associated Works Programming
The Construction Project associated Works Progress related to tender is prepared according to the
AS 4000-1997 as prescribed in the clause 34.1 page.27
The Construction Project associated Works Programming related to tender is prepared according to
the AS 4000-1997 as prescribed in the clause 32 page.25
3.7 Construction Project associated Activities Suspension
The Construction Project associated activities suspension related to tender is prepared according to
the AS 4000-1997 as prescribed in the clause 33 page.26

3.8 Construction Project associated Costs Related to
Disruption
The Construction Project associated costs related to disruption is prepared according to the AS 4000-
1997 as prescribed in the clause 34 page.27
3.9 Construction Project associated Liability Defects
The Construction Project associated Liability Defects related to tender is prepared according to the
AS 4000-1997 as prescribed in the clause 35 page.29
3.10 Construction Project associated Variations
The Construction Project associated variations related to tender is prepared according to the AS
4000-1997 as prescribed in the clause 36 page.29
3.11 Construction Project associated Certificates as well as
Construction Project associated Payments
The Construction Project associated Certificates related to tender is prepared according to the AS
4000-1997 as prescribed in the clause 37.2 page.31
The Construction Project associated Payments related to tender is prepared according to the AS
4000-1997 as prescribed in the clause 37 page.30
3.12 Construction Project associated Insolvency
Construction Project associated Insolvency related to tender is prepared according to the AS 4000-
1997 as prescribed in the clause 39 page.33
3.13 Construction Project associated Termination
The Construction Project associated Termination related to tender is prepared according to the AS
4000-1997 as prescribed in the clause 40 page.37
3.14 Construction Project associated Claims
The Construction Project associated Claims related to tender is prepared according to the AS 4000-
1997 as prescribed in the clause 41 page.37
3.15 Construction Project associated Dispute Resolution as
well as Construction Project associated Arbitration
The Construction Project associated Dispute Resolution related to tender is prepared according to
the AS 4000-1997 as prescribed in the clause 42 page.38
The Construction Project associated Arbitration related to tender is prepared according to the AS
4000-1997 as prescribed in the 42.3 page.39
4. Quality Assurance and Control requirements,
including: -
4.1 Construction Project associated Quality Related to
customers
The Construction Project associated Quality Related to customers is prepared according to the AS
ISO 10014-2007 as prescribed in the section 5.1 page.3
Disruption
The Construction Project associated costs related to disruption is prepared according to the AS 4000-
1997 as prescribed in the clause 34 page.27
3.9 Construction Project associated Liability Defects
The Construction Project associated Liability Defects related to tender is prepared according to the
AS 4000-1997 as prescribed in the clause 35 page.29
3.10 Construction Project associated Variations
The Construction Project associated variations related to tender is prepared according to the AS
4000-1997 as prescribed in the clause 36 page.29
3.11 Construction Project associated Certificates as well as
Construction Project associated Payments
The Construction Project associated Certificates related to tender is prepared according to the AS
4000-1997 as prescribed in the clause 37.2 page.31
The Construction Project associated Payments related to tender is prepared according to the AS
4000-1997 as prescribed in the clause 37 page.30
3.12 Construction Project associated Insolvency
Construction Project associated Insolvency related to tender is prepared according to the AS 4000-
1997 as prescribed in the clause 39 page.33
3.13 Construction Project associated Termination
The Construction Project associated Termination related to tender is prepared according to the AS
4000-1997 as prescribed in the clause 40 page.37
3.14 Construction Project associated Claims
The Construction Project associated Claims related to tender is prepared according to the AS 4000-
1997 as prescribed in the clause 41 page.37
3.15 Construction Project associated Dispute Resolution as
well as Construction Project associated Arbitration
The Construction Project associated Dispute Resolution related to tender is prepared according to
the AS 4000-1997 as prescribed in the clause 42 page.38
The Construction Project associated Arbitration related to tender is prepared according to the AS
4000-1997 as prescribed in the 42.3 page.39
4. Quality Assurance and Control requirements,
including: -
4.1 Construction Project associated Quality Related to
customers
The Construction Project associated Quality Related to customers is prepared according to the AS
ISO 10014-2007 as prescribed in the section 5.1 page.3
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

4.2 Construction Project associated Leadership Quality
The Construction Project associated leadership quality is prepared according to the AS ISO 10014-
2007 as prescribed in the section 5.2 page.5
4.3 Construction Project associated Involvement of people
The Construction Project associated people involvement is prepared according to the AS ISO 10014-
2007 as prescribed in the section 5.3 page.6
4.4 Construction Project associated Methodological approach
The Construction Project associated methodological approach is prepared according to the AS ISO
10014-2007 as prescribed in the section 5.4 page.7.
4.5 Construction Project associated Systematic approach
The Construction Project associated systematic approach is prepared according to the AS ISO 10014-
2007 as prescribed in the section 5.5 page.8
4.6 Construction Project associated Continuous improvement
The Construction Project associated continuous improvement is prepared according to the AS ISO
10014-2007 as prescribed in the section 5.6 page.9
4.7 Construction Project associated Mutual benefit
The Construction Project associated mutual benefit is prepared according to the AS ISO 10014-2007
as prescribed in the section 5.8 page.11
5. Safety requirements, including: -
5.1 Construction Project associated Re-examination of safety
management
The Construction Project associated Re-examination of safety management is prepared according to
the AS/NZS 4804-2001 as prescribed in the section 4.5.2 page.39
5.2 Construction Project associated Safety measurement as
well as evaluation
The Construction Project associated Re-examination Safety measurement is prepared according to
the AS/NZS 4804-2001 as prescribed in the section 4.4 page.35
5.3 Construction Project associated Configuration of safety
features
The Construction Project associated Configuration of safety features is prepared according to the
AS/NZS 4804-2001 as prescribed in the section 4.3 page.15
5.4 Construction Project associated Re-examination Planning
Safety
The Construction Project associated Planning Safety is prepared according to the AS/NZS 4804-2001
as prescribed in the section 4.2 page.11
5.5 Construction Project associated OHS policy
The Construction Project associated OHS policy is prepared according to the AS/NZS 4804-2001 as
prescribed in the section 4.1.4 page.9
The Construction Project associated leadership quality is prepared according to the AS ISO 10014-
2007 as prescribed in the section 5.2 page.5
4.3 Construction Project associated Involvement of people
The Construction Project associated people involvement is prepared according to the AS ISO 10014-
2007 as prescribed in the section 5.3 page.6
4.4 Construction Project associated Methodological approach
The Construction Project associated methodological approach is prepared according to the AS ISO
10014-2007 as prescribed in the section 5.4 page.7.
4.5 Construction Project associated Systematic approach
The Construction Project associated systematic approach is prepared according to the AS ISO 10014-
2007 as prescribed in the section 5.5 page.8
4.6 Construction Project associated Continuous improvement
The Construction Project associated continuous improvement is prepared according to the AS ISO
10014-2007 as prescribed in the section 5.6 page.9
4.7 Construction Project associated Mutual benefit
The Construction Project associated mutual benefit is prepared according to the AS ISO 10014-2007
as prescribed in the section 5.8 page.11
5. Safety requirements, including: -
5.1 Construction Project associated Re-examination of safety
management
The Construction Project associated Re-examination of safety management is prepared according to
the AS/NZS 4804-2001 as prescribed in the section 4.5.2 page.39
5.2 Construction Project associated Safety measurement as
well as evaluation
The Construction Project associated Re-examination Safety measurement is prepared according to
the AS/NZS 4804-2001 as prescribed in the section 4.4 page.35
5.3 Construction Project associated Configuration of safety
features
The Construction Project associated Configuration of safety features is prepared according to the
AS/NZS 4804-2001 as prescribed in the section 4.3 page.15
5.4 Construction Project associated Re-examination Planning
Safety
The Construction Project associated Planning Safety is prepared according to the AS/NZS 4804-2001
as prescribed in the section 4.2 page.11
5.5 Construction Project associated OHS policy
The Construction Project associated OHS policy is prepared according to the AS/NZS 4804-2001 as
prescribed in the section 4.1.4 page.9
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

References
Al Qady, M. and Kandil, A., 2014. Automatic clustering of construction project documents based on
textual similarity. Automation in construction, 42, pp.36-49.
Amade, B., Ubani, E.C., Omajeh, E.O.M., Anita, U. and Njoku, P., 2015. Critical success factors for
public sector construction project delivery: A case of Owerri, Imo State. International Journal of
Research in Management, Science and Technology, 3(1), pp.11-21.
Elbarkouky, M.M., Fayek, A.R., Siraj, N.B. and Sadeghi, N., 2016. Fuzzy arithmetic risk analysis
approach to determine construction project contingency. Journal of Construction Engineering and
Management, 142(12), p.04016070.
Karimi, H., Taylor, T.R. and Goodrum, P.M., 2017. Analysis of the impact of craft labour availability on
North American construction project productivity and schedule performance. Construction
Management and Economics, 35(6), pp.368-380.
Khattri, T., Agarwal, S., Gupta, V. and Pandey, M., 2016. Critical Causes of Delay In Construction
Project In Jhansi Region. International Research Journal of Engineering and Technology (IRJET)
Volume, 3.
Nguyen, H.T. and Hadikusumo, B., 2017. Impacts of human resource development on engineering,
procurement, and construction project success. Built Environment Project and Asset
Management, 7(1), pp.73-85.
Ospina-Alvarado, A., Castro-Lacouture, D. and Roberts, J.S., 2016. Unified framework for
construction project integration. Journal of Construction Engineering and Management, 142(7),
p.04016019.
Siew, R.Y.J., 2016. Integrating sustainability into construction project portfolio management. KSCE
Journal of Civil Engineering, 20(1), pp.101-108.
Taylan, O., Bafail, A.O., Abdulaal, R.M. and Kabli, M.R., 2014. Construction projects selection and risk
assessment by fuzzy AHP and fuzzy TOPSIS methodologies. Applied Soft Computing, 17, pp.105-116.
Zima, K., 2015. The Case-Based Reasoning model of cost estimation at the preliminary stage of a
construction project. Procedia Engineering, 122, pp.57-64.
Al Qady, M. and Kandil, A., 2014. Automatic clustering of construction project documents based on
textual similarity. Automation in construction, 42, pp.36-49.
Amade, B., Ubani, E.C., Omajeh, E.O.M., Anita, U. and Njoku, P., 2015. Critical success factors for
public sector construction project delivery: A case of Owerri, Imo State. International Journal of
Research in Management, Science and Technology, 3(1), pp.11-21.
Elbarkouky, M.M., Fayek, A.R., Siraj, N.B. and Sadeghi, N., 2016. Fuzzy arithmetic risk analysis
approach to determine construction project contingency. Journal of Construction Engineering and
Management, 142(12), p.04016070.
Karimi, H., Taylor, T.R. and Goodrum, P.M., 2017. Analysis of the impact of craft labour availability on
North American construction project productivity and schedule performance. Construction
Management and Economics, 35(6), pp.368-380.
Khattri, T., Agarwal, S., Gupta, V. and Pandey, M., 2016. Critical Causes of Delay In Construction
Project In Jhansi Region. International Research Journal of Engineering and Technology (IRJET)
Volume, 3.
Nguyen, H.T. and Hadikusumo, B., 2017. Impacts of human resource development on engineering,
procurement, and construction project success. Built Environment Project and Asset
Management, 7(1), pp.73-85.
Ospina-Alvarado, A., Castro-Lacouture, D. and Roberts, J.S., 2016. Unified framework for
construction project integration. Journal of Construction Engineering and Management, 142(7),
p.04016019.
Siew, R.Y.J., 2016. Integrating sustainability into construction project portfolio management. KSCE
Journal of Civil Engineering, 20(1), pp.101-108.
Taylan, O., Bafail, A.O., Abdulaal, R.M. and Kabli, M.R., 2014. Construction projects selection and risk
assessment by fuzzy AHP and fuzzy TOPSIS methodologies. Applied Soft Computing, 17, pp.105-116.
Zima, K., 2015. The Case-Based Reasoning model of cost estimation at the preliminary stage of a
construction project. Procedia Engineering, 122, pp.57-64.
1 out of 8
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.