Procurement and Supply Chain: School Construction Project

Verified

Added on  2023/05/30

|19
|4832
|475
Report
AI Summary
This report provides a detailed procurement plan for a school construction project funded by the Capital Spending Program. The project aims to build a new school with facilities for health science and digital technology, expected to be completed by 2020. The report outlines procurement and supply chain strategies, including the procurement process, systems, and management contract procurement. It highlights the project team and participants, defining their roles and responsibilities, and emphasizes the importance of ethical conduct and professional ethics. The report addresses property context, including the facilities, teaching and learning facilities, and the selection of experts like project managers, contractors, and architects. It also covers procurement strategies, such as understanding the organizational mission, identifying important procurement items, and defining success metrics. The procurement process, including investigation of various sectors, selection of procurement processes, and the implementation of a correct procurement framework based on time, quality, and cost is also detailed. The report emphasizes the need for effective procurement systems and the importance of aligning procurement strategies with project and organizational objectives, ensuring cost-effectiveness, quality, and timely delivery.
Document Page
Running head: Procurement and Supply Chain 1
Procurement and Supply Chain
Student’s Name
University
Course
Date
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Procurement and Supply Chain 2
Executive Summary
In this report, provides procurement report on the development of a construction project.
The project is about the construction of the school which is funded by Capital Spending Program
form the department of education. The funds released was £60m to develop this project by
coming up with the economic factor of education in health science and digital technology. The
project is expected to be completed by the year 2020, which will enhance both the students and
management to relocate and operates from the new premises.
This report provides procurement and supply chain strategies to be used in the project.
These strategies will be an encouragement towards achieving the organizational and procurement
goals and objectives. Procurement process also will be outlined by providing a clear way of how
the project requirements will be absorbed and used in this project. The client’s requirements to
run the project successfully are mentioned in details by this report. This includes the ethical and
professional code to be applied. All the required team including, the project manager, contractor,
architect and procurement team are employed completely according to the project requirements.
Document Page
Procurement and Supply Chain 3
Table of Contents
Introduction....................................................................................................................................2
Property Context...........................................................................................................................3
Procurement strategy....................................................................................................................4
Procurement process.....................................................................................................................7
Procurement systems.....................................................................................................................8
Management contract procurement............................................................................................9
Project Team and Participants...................................................................................................10
Roles and Responsibilities of Participants.................................................................................11
Ethical conduct and professional ethics.....................................................................................13
Summary and conclusion............................................................................................................14
Reference......................................................................................................................................15
Document Page
Procurement and Supply Chain 4
Introduction
This is a procurement plan for the project of school construction in the state. This project
is funded by the “Capital spending program from the education department”, this is to develop a
school program which is not under the management of the local authority. In this project, it
requires a well-planned procurement and supply plan, so as to ensure the success of the project.
Different materials, skills, knowledge and experts in the different field of specialization are
required to be involved in the project. The client needs a quality procurement report which will
convince the team to accept the proposed plan. The client has a high demand to work close with
available contractor throughout the project time. This contractor is required to offer a timely
completion of the project and the budget by proving facilities of high first class. More than one
part is required in this project to make the project successful (Mostafa and Chileshe, 2018). The
major requirements includes peoples like experts in project management, construction contractor
and other useful consultant who will make completion of the project successful. The client will
require to maintain the first architecture. This report will help in getting quality and reliable
services and product from the selected team, therefore, maximizing the value of every product to
be used in all stages. The following report will show out the strategic procurement processes that
will be used, client requirement will be captured and all responsibilities of the consultants
employed will outline out (Phillips, 2018).
The school will offer a Health and digital education in the technology sector. The project
is expected to be complete by the year 2020 and this will enhance the students and the
management to relocate and carry out their operations from the new premises.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Procurement and Supply Chain 5
Property Context
This procurement report will outline all required properties, including personnel which
will be employed in the project. The construction of the school will start from scratch since the
selected local architect has not completed everything (Herbert, 2018). The reason being that, the
developed design was not approved by the school principal. This stage involves the following
elements:
- Teaching and learning facilities.
- Accommodation.
- Staff offices.
- Laboratory facilities.
- 3D, VR, and digital universe.
- Dining and canteen facilities.
- Multi-purpose hall and indoor games arena.
- Outdoor play and learning areas.
Therefore, due to the above reason, the school principal and promoters were limited to carry out
the project requirements complete. The caretaker, chairperson and five members were selected
by the promoters to be included in the procurement committee. Admission manager, Principal
PA, and manager of the Business Liaison were selected also. In this selected team, no person had
technical or operational know-how of construction concept, therefore the team is responsible to
select another team of experts who will run the project until completion. The required experts
includes:
- Full-time project manager. This person should be available throughout the project time,
monitoring the progress of the project.
Document Page
Procurement and Supply Chain 6
- Construction contractor. This expert will organize various elements in the project to be
performed within the construction site.
- The architect was needed. This area was not fully decided since the original architect
might continue with the original design or the promoters employ another one, who will
start a new design or continue with the original design.
- Consultants. These are another experts who will be required to collect and deliver useful
information about the project, also, can be called assistant team.
Procurement strategy
Procurement involves the acquisition of the materials, services, supplies and other
requirements which will be used in the targeted project and make it successfully completed.
Therefore, when it becomes to the procurement strategies it means that these are already planned
methodology on how to get cost-effective purchase for the project materials from different
suppliers under consideration (Mena, Van Hoek, and Christopher, 2018). Several factors will be
considered when setting out procurement strategies like timeline, the budget, and funding project
opportunities. These procurement strategies will define the goals and objective of the project to
be achieved with time. The selected team should plan an effective procurement strategies which
will assist them in getting viable materials of the project. In this process of decision making cost
factor is important to be under considerations plus the quality of the materials to be used (Bag,
Venkatesh, Luthra and Anand, 2018).
The building of this school, the selected team should come up with the procurement
strategy which will facilitate successful completion of the project. The selected team should sit
down and exchange ideas on how to achieve the project completion successful (School). These
strategies may be on the quality of the product used and certain measure should be met by all
Document Page
Procurement and Supply Chain 7
materials to be used in this project. Another factor to be considered is time this includes duration
the project will take and timely delivery of the materials from different sources should be
considered. Also, the price of the materials and other personnel should be quoted according to
the budget of the project (Ahmadi, Pishvaee and Torabi, 2018). Therefore, the requirement to
meet should be cost-effective, therefore, encouraging to achieve procurement goals smoothly.
The following are the key steps for developing strong and effective procurement
strategies:
1. Understand the Mission of the organization. Is very important for the team to
understand the organizational mission when coming up with procurement strategies.
This will help to know the stand of the organization and what is required in the future.
If is impossible to measure the organization progress today also, will be hard to
achieve future goals. Therefore, in procurement, the team should understand the
procurement sector is currently accumulating value and understand on how to operate
effective. These includes payment terms and conditions, procurement lifecycle,
contract compliance, investment in procurement returns and others.
2. Identifying and evaluating what is important to procure for the project. Once the
mission of the procurement is clear to the team, now the opportunity is identified. The
most important items are the one to be procured first because they will motivate the
achievement of the organizational and procurement strategies effectively.
3. Define the success of the product to be procured. The procurement strategy must be
able to identify the quality of the product. Will the product assist to add a certain
percentage of progress in the project, therefore, attaining the procurement strategies
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Procurement and Supply Chain 8
in and outside the project? This will help to measure the procurement ability on the
products.
4. Develop target that defines success in a measurable way. This is done after
procurement is determined, this where the quality of product can be measurable only.
The measurable of the strategy will cooperate with different objectives in
procurement. Also, will allow prominence on quality, cost, and services. This is
important since it provides progress improvement when the goal is measurable.
5. Implement and measure of the strategy. The strategies developed now is required to
be implemented in the project system. After implementation, the team should ensure
progress is still monitored across the project activities.
The use of an effective procurement strategy in this project on the purchase of services and
materials, it will enhance effective cost, quality maintained and timely delivered (Oke,
Aigbavboa, and Tong, 2018). As procurement strategies are achieved also the organization and
project objectives will be successfully attained.
Procurement process
In every procurement report, there is a procurement process to be carried out in the project. For
example, in this project of school construction, the team should select effective procurement
processes. The selected team of experts should carry out a detailed investigation of the various
sectors which are going to be involved in the project of school construction (Ajayi and Oyedele,
2018). The following areas need the investigation before selecting procurement process:
transportation of items available for the construction, site and environment survey, structural
design investigation and the analyses of the materials to be used in construction. Also, the
Document Page
Procurement and Supply Chain 9
required methodology in the whole processes of project construction is required to be
investigated.
Therefore, the team of an expertly selected for the school construction should be ready to select
the suitable procurement processes after the investigation is done on those sectors. The correct
procurement framework must be implemented in the project. This framework will be based on
the main terminologies of procurement, that is time, quality and cost. The success of the project
activities will depend on the selected procurement process to be used in the construction of this
school. Also, this will help the team to meets client and final user requirements and needs to
design the project (Ghazali, Rashid, and Sadullah, 2018). The expert team should be ready to
develop, implement and control the selected procurement processes. The school construction
team has identified several qualities which should be met by the project, therefore, satisfying the
client’s and all parties requirements involved in their needs accordingly. These qualities they
include:
- The cost of construction material. The standards cost according to the material quality
should be agreed by both parties involved.
- Time. The required time for project completion should under heavy consideration.
- Competition of the price. Is very important to analyze well the price competition on the
market before procuring anything for the project.
- Quality. The quality of the material, ideas, and expert must kindly be investigated.
- Responsibilities. As the team of experts is selected, should be assigned different roles
which each individual will participate to ensure successful completion of the project.
Document Page
Procurement and Supply Chain 10
- Complexity. The project processes should be complicated due to the use of a complicated
procurement process selected. This must be avoided at the highest rate as the project is
concern.
- Risk. The exchange of various risk within the different activities in the project, will it
possible within the project of school construction?
Using the above qualities, will enable the team to select an effective procurement processes
and implement the process according to the project requirement of the client and to the final user
of the school developement. A successful project is based on the perfect and effective selection
of the procurement process.
Procurement systems
This is the same as the procurement framework to be used in the project development.
This system of procurement will lay out several duties and responsibilities to be undertaken by
several selected experts (Awuzie, Farag and McDermott, 2018). Therefore, effective
implementations of the procurement framework will involve scheduling and planning cost saving
in all project operations and put a commitment on the procurement team. This will facilitate cost
reduction in the project activities but increase the profitability level.
Procurement system is classified into four categories, as mentioned below:
- Traditional.
- Design and construction.
- Management.
- Collaborative.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Procurement and Supply Chain 11
Most orders of this project have multiplied much in the market due to the high demand of the
material. The development of suitable procurement system will be depending on the school
project and the procurement techniques to be used in acquiring materials (Daoud, Othman,
Robinson, and Bayyati, 2018). The risk is a very important factor to be considered in the project,
as well as the involvement of the client in general. The selected system implemented in this
project should facilitate contract strategy, methodology and team selected knowledge on how to
processed and finish the project within the time limit.
Management contract procurement
Several parties, like buyers and sellers, are most important to be involved in the
procurement processes. The school team of experts, contractors, suppliers and any party involved
in this project development must work under certain contract of agreement. The existence of
those several parties should sign up the contract which will help the project to run effectively.
Also, they is existence of a general worker in the project which they need to be managed by the
experts, therefore, requiring management contract between these casual employees in the project
(De Marco, 2018). The management which is selected by promoters of the school must supervise
the project until it’s over according to the legal requirement they agreed together. They are many
contracts of agreement involved in this project like management construction contract, design
and implementation contract, employees and management contract and these all contracts will
help and encourage the technical and procurement framework to implemented and managed well
in achieving procurement and organizational objective (Kumar, Pal, and Dash, 2018). All the
management contract they have advantages towards the procurement processes. These
advantages they include:
Document Page
Procurement and Supply Chain 12
- The selected Team of experts and school team they will encourage each other to
coordinate and combine all efforts between the contractors, consulters, and designer of
the project.
- The developed plan will be implemented according to since each party will focus to work
according to the agreed contract.
- Set of responsibilities, roles and areas of specialization are well defined by the contract.
- Terms and condition governing the project and the participants are well elaborated in
case of any change. This helps to maintain the good relationship between all parties
involved in the management.
- Use of quality contract, it will enhance the use of quality and timely delivered materials.
The contact between a supplier and the contractor is very important for successful project
development.
Project Team and Participants
Project team and participants are the groups of peoples and individuals who are involved
in the development of a successful project. The team of experts like architects, contractors and
consulters are required in the project development processes (Eftekhar, Masini, Robotis and Van
Wassenhove, 2018). The project owner and his management team are also involved. The
outsiders’ participants like suppliers, local government and competitor for the tender in one way
or the other they motivates the success towards the development of the project. For the local
government, the authority has provided £60m towards the school development. This team is
ranked according to the mandate it has in the project. The following is a structure towards this
project team selected.
Document Page
Procurement and Supply Chain 13
Roles and Responsibilities of Participants
Project Manager. This is an individual who is responsible for all achievement and failures of
the progress in the project. The project manager must be involved in every single step of the
project and understand what is going on. The project manager cannot execute all activities of the
project alone, therefore, requiring a team of experts to work alongside him. Therefore the project
manager is in charge of this team, anything undertaken by the team is the responsibility of the
manager to be aware. Eventually, single mistake inside the project, the project manager is
answerable to it, therefore he should a person who takes his responsibilities with heavy concern
and careful (Zwikael and Meredith, 2018). The following are the key roles and responsibilities of
the project manager:
- Incorporation management. This is ensuring all activities have been created and directed
in the right way according to the construction phases resulting in the success of the
activities.
The Principal
School Management
Project Manager
Architect Construction
Manager
Procurement
Team Consultants
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Procurement and Supply Chain 14
- Scope supervision. He is the overall planner and controller of the whole project in
progress. All the resources within the project are under his responsibilities.
- Management quality services in the project. This involves setting up measures which will
determine the quality measures according to the project requirement.
- All human resources in the project are managed by the project manager. The employees
are controlled by the project manager. The project manager he will ensure all tasks
assigned to the employees are completed on time and have met the required standard of
the project.
- Risk taker. All risk which might raise from the project should be addressed by the project
manager. This should be recovered without no time wastage.
- Manage all procurement processes. Procurement team is under the project manager. He
should be aware of the suppliers and material to be supplied for the project to be
complete in time. He must ensure all standards are met in the procurement process.
- He must ensure clear and frequent communication channel is implemented in the project
system. All level of management in the project should maintain all direct communication
since it will result in the quality decision making (Martinsuo and Hoverfält, 2018).
Construction manager. The construction manager will work closely with the project manager
to ensure the success is achieved in the project. Regularly, the construction manager will work
closely with several teams. For example, the designer of the project to ensure correct
implementation is done according to the original design. Also, the Architect is required to work
closely with the construction manager. The main role of the construction manager is to maintain
the planning is on progress well as it is initiated, allocation of resources, management of the staff
Document Page
Procurement and Supply Chain 15
in the site, doing the budget calculation and finally, conducting the minor tender in the site for
boosting project success (Gustavsson, 2018).
Architect. This is the individual who is responsible in designing the project from the scratch. Is
the one who originated the project form the first stage and plans the direction the will follow.
When the project starts, he should be ready to provide any clarification where is required by the
rest of the team. He must ensure all plans from the first one are safely packed and preserver since
they will used at the end to evaluate the standards of the project (Kelkar, 2018).
Procurement team. Material for the project is required in high demand when the project startes.
Therefore, the procurement team should be ready to conduct health purchase of all these
materials at a required quality and on a good time. The materials on the site is planned,
controlled and disposed of by the procurement team where possible. Conducting the procurement
process like searching quality and reliable supplier is the role the procurement team (Nguyen and
Hadikusumo, 2018).
Ethical conduct and professional ethics
Ethical conducts are the responsibilities of every party involved in the project to maintain high
standards in carrying out activities in the project and maintain good behavior towards each party.
Professional ethics are role and condition to be followed by every part of the project to ensure
professional and reliable solution has been provided (Ikeda and Mangan, 2018). The following
are some code of ethics in this project development:
- All parties should cooperate and respect each other accordingly, failure to that the action
will be undertake to the necessary part.
- Every project team they must adhere to the agreed contract.
Document Page
Procurement and Supply Chain 16
- The procurement should exercise open and clear purchase of materials. These materials
they supposed to meet required standards of the project.
- In case of failure to the specific sector, the responsible team will bear that risk as personal
or as the group level until it is recovered.
Summary and conclusion
In summary, this is the procurement report describing all the procurement strategies,
procurement processes, client requirements in the project and the personal skills which are
required to complete the construction of the school project. Finally, the procurement team should
cooperate with other teams of experts in drawing out the procurement processes and strategies.
Quality, time and cost factors are every important factors to be considered in the procurement
processes and entirely in the project.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Procurement and Supply Chain 17
Reference
Ahmadi, A., Pishvaee, M.S. and Torabi, S.A., 2018. Procurement Management in Healthcare
Systems. In Operations Research Applications in Health Care Management, pp. 569-598.
Ajayi, S.O. and Oyedele, L.O., 2018. Waste-efficient materials procurement for construction
projects: A structural equation modeling of critical success factors. Waste Management, 75,
pp.60-69.
Awuzie, B., Farag, F. and McDermott, P., 2018. Achieving social value through construction
frameworks: the effect of client attributes. Proceedings of the Institution of Civil Engineers–
Management, Procurement and Law, 171(1), pp.25-31.
Bag, S., Venkatesh, V.G., Luthra, S. and Anand, N., 2018. Ethical Practices, Buyer-Supplier
Relationship, and Innovative Green Procurement Performance: Some Exploratory Results.
In Ethics and Decision-Making for Sustainable Business Practices, pp. 1-23.
Daoud, A.O., Othman, A.A., Robinson, H. and Bayyati, A., 2018. Exploring The Relationship
Between Materials Procurement and Waste Minimization in The Construction Industry: The
Case of Egypt. The 4th NZAAR International Event Series on Natural and Built Environment,
Cities, Sustainability and Advanced Engineering, pp.76-85.
De Marco, A., 2018. Procurement Management. In Project Management for Facility
Constructions, pp. 149-154.
Eftekhar, M., Masini, A., Robotis, A. and Van Wassenhove, L.N., 2018. Corrigendum: Vehicle
Procurement Policy for Humanitarian Development Programs. Production and Operations
Management, 27(4), pp.798-798.
Document Page
Procurement and Supply Chain 18
Ghazali, F.E.M., Rashid, S.A. and Sadullah, A.F.M., 2018. The disparity between the
Procurement Process Best Practice for Public-Private Partnership (PPP) Projects in the UK and
Malaysia. Proceedings of the Institution of Civil Engineers-Management, Procurement, and
Law, pp.1-29.
Gustavsson, T.K., 2018. Liminal roles in construction project practice: exploring change through
the roles of partnering manager, building logistic specialist and BIM coordinator. Construction
Management and Economics, pp.1-12.
Herbert, C.W., 2018. Like a good neighbor, squatters are there: Property and neighborhood
stability in the context of urban decline. City & Community, 17(1), pp.236-258.
Ikeda, K. and Mangan, J.A., 2018. Towards the Construction of a New Regionalism? The End of
East Asian Colonialism: Japanese Responses and Reactions to the Games of Asia. In Japanese
Imperialism: Politics and Sport in East Asia, pp. 337-363.
Kelkar, S., 2018. Engineering a platform: The construction of interfaces, users, organizational
roles, and the division of labor. New Media & Society, 20(7), pp.2629-2646.
Kumar, A., Pal, A. and Dash, M.K., 2018. Construction of Capital Procurement Decision
Making Models to Optimize Supplier Selection Using Fuzzy Delphi and AHP-
DEMATEL. Benchmarking: An International Journal, (just-accepted), pp.30-40.
Martinsuo, M. and Hoverfält, P., 2018. Change program management: Toward a capability for
managing value-oriented, integrated multi-project change in its context. International Journal of
Project Management, 36(1), pp.134-146.
Document Page
Procurement and Supply Chain 19
Mena, C., Van Hoek, R. and Christopher, M., 2018. Leading procurement strategy: driving
value through the supply chain, pp. 678-769.
Mostafa, S. and Chileshe, N., 2018. Application of discrete-event simulation to investigate the
effects of client order behavior on off-site manufacturing performance in Australia. Architectural
Engineering and Design Management, 14(1-2), pp.139-157.
Nguyen, H.T. and Hadikusumo, B.H., 2018. Human resource-related factors and engineering,
procurement, and construction (EPC) project success. Journal of Financial Management of
Property and Construction, 23(1), pp.24-39.
Oke, A.E., Aigbavboa, C.O. and Tong, B.A., 2018. Evaluation of Procurement Systems of Public
Sector Funded Projects. In Proceedings of the 21st International Symposium on Advancement of
Construction Management and Real Estate, pp. 709-715.
Phillips, S., 2018. The ongoing evolution of government infrastructure procurement. Civil
Engineering= Siviele Ingenieurswese, 2018(v26i1), pp.16-19.
Sarhan, S., Pasquire, C., King, A. and Manu, E., 2018. Institutional waste within the UK
construction procurement context: a conceptual framework. Engineering Project Organization
Journal, 8.
Sivakumaran, S. and Perera, B.A.K.S., 2018. Construction management as a suitable
procurement method for hotel building construction in Sri Lanka, pp. 350-423.
Zwikael, O. and Meredith, J.R., 2018. Who’s who in the project zoo? The ten core project
roles. International Journal of Operations & Production Management, 38(2), pp.474-492.