PROJ 6002 Project: Scope, Schedule, and Planning for Vehicle Facility
VerifiedAdded on 2022/09/06
|13
|2279
|17
Report
AI Summary
This report presents a comprehensive project management plan for a vehicle maintenance facility, addressing project goals, scope, schedule, and budget. It outlines the project's objectives, which include constructing a paving, runoff system, and a building with servicing and office areas. The project scope defines in-scope activities like delivering the project within budget, constructing a parking zone, and building a two-part facility. It also specifies out-of-scope items. The report includes project constraints, such as budget and quality, and assumptions related to budget and timeline. A detailed work breakdown structure (WBS) is provided, breaking down the project into phases and tasks. The project schedule is also included, showing task durations and resource allocation. A network diagram visually represents the project's workflow. The report concludes by emphasizing the importance of adhering to the schedule and scope to ensure project success.

Running head: PROJECT MANAGEMENT
PROJ 6002: Project planning and budgeting
Name of the Student
Name of the University
Author’s Note
PROJ 6002: Project planning and budgeting
Name of the Student
Name of the University
Author’s Note
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1
PROJECT MANAGEMENT
Table of Contents
Introduction................................................................................................................................2
Project goals and objectives.......................................................................................................2
Project scope..............................................................................................................................3
In scope..................................................................................................................................4
Out scope................................................................................................................................4
Constraints..............................................................................................................................5
Assumptions...........................................................................................................................5
Work breakdown structure (WBS).............................................................................................6
Project schedule.........................................................................................................................6
Network diagram........................................................................................................................8
Conclusion................................................................................................................................10
References................................................................................................................................11
PROJECT MANAGEMENT
Table of Contents
Introduction................................................................................................................................2
Project goals and objectives.......................................................................................................2
Project scope..............................................................................................................................3
In scope..................................................................................................................................4
Out scope................................................................................................................................4
Constraints..............................................................................................................................5
Assumptions...........................................................................................................................5
Work breakdown structure (WBS).............................................................................................6
Project schedule.........................................................................................................................6
Network diagram........................................................................................................................8
Conclusion................................................................................................................................10
References................................................................................................................................11

2
PROJECT MANAGEMENT
Introduction
The project management is an approach which is used for ensuring the production of
business outcomes. The overall project management is categorized in such divisions like
project goals, project scope, work break down structure, time management, cost management,
project schedule (Kerzner, 2017). This report follows the project of vehicle maintenance
facility which consists of all the features with a location sized in small commercial building.
Here to complete the project, the project manager should follow such project management
related methodology by which the project team can achieve the success for the project
(Radujković & Sjekavica, 2017). Regarding this project, the project owner has made a
contract with a normal contractor that the project has to complete within the fixed scope as
well as fixed cost. Within this project, a paving, runoff and also a building are considered as
the project deliverable (Meredith, Mantel Jr & Shafer, 2017). Within the building, there must
implement a fire alarm system for security purposes. In this report, it has to present the
project goal as well as project scope, schedule etc.
Project goals and objectives
The project goals as well as objectives are the declaration of the project outcome
which has to be realized by the project team along with the full support. The project objective
is similar to the project goal (Heagney, 2016). Every project has a high level goal and it is too
problematic for the project team to achieve their target. To complete the project goal in a
positive way, the project chief should work with proper efficiency and instructs the exact
direction to the project team so that they can able to reach towards the project goal (Seymour
& Hussein, 2014).
According to this project, as this project relates with the vehicle maintenance facility
therefore within this project, a paving as well as a runoff and also a building has to construct
PROJECT MANAGEMENT
Introduction
The project management is an approach which is used for ensuring the production of
business outcomes. The overall project management is categorized in such divisions like
project goals, project scope, work break down structure, time management, cost management,
project schedule (Kerzner, 2017). This report follows the project of vehicle maintenance
facility which consists of all the features with a location sized in small commercial building.
Here to complete the project, the project manager should follow such project management
related methodology by which the project team can achieve the success for the project
(Radujković & Sjekavica, 2017). Regarding this project, the project owner has made a
contract with a normal contractor that the project has to complete within the fixed scope as
well as fixed cost. Within this project, a paving, runoff and also a building are considered as
the project deliverable (Meredith, Mantel Jr & Shafer, 2017). Within the building, there must
implement a fire alarm system for security purposes. In this report, it has to present the
project goal as well as project scope, schedule etc.
Project goals and objectives
The project goals as well as objectives are the declaration of the project outcome
which has to be realized by the project team along with the full support. The project objective
is similar to the project goal (Heagney, 2016). Every project has a high level goal and it is too
problematic for the project team to achieve their target. To complete the project goal in a
positive way, the project chief should work with proper efficiency and instructs the exact
direction to the project team so that they can able to reach towards the project goal (Seymour
& Hussein, 2014).
According to this project, as this project relates with the vehicle maintenance facility
therefore within this project, a paving as well as a runoff and also a building has to construct
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3
PROJECT MANAGEMENT
(Fleming & Koppelman, 2016). The paving should construct with asphalt along with concrete
curb as well as gutter and the runoff will construct with catch basins and also metal pipe for
draining purpose. At the opening of the project, the project boss has made a contract with a
general contractor for executing this project within the allocated time and also cost (Walker,
2015). Within this vehicle maintenance service centre, there has to keep enough space for
parking the vehicles or moving the vehicles during the servicing time. Moreover, during the
building construction, it has to construct within two parts including servicing area and also
office or training area.
Project scope
Project scope are mainly referred as the project deliverables through the entire life
span of the project (Mir & Pinnington, 2014). The project scope includes the project related
information that are required for beginning of the project. The project scope is also defined as
the process of managing project tasks that must be completed within the resources, time as
well as cost. Based on the project management oriented principles, the project scope depends
on the project requirements and for that within the project, if the requirements are not cleared,
therefore it is difficult for meeting the project scope (Leach, 2014). According to this project,
the project location is selected on the city street in the industrial park. During the starting
time of the project, the project manager has made a contract with a general contractor for
executing this project within the allocated time and also cost (Too & Weaver, 2014). Within
the scope management of the project, there exists in scope, out scope as well project
constraints and also project assumptions.
PROJECT MANAGEMENT
(Fleming & Koppelman, 2016). The paving should construct with asphalt along with concrete
curb as well as gutter and the runoff will construct with catch basins and also metal pipe for
draining purpose. At the opening of the project, the project boss has made a contract with a
general contractor for executing this project within the allocated time and also cost (Walker,
2015). Within this vehicle maintenance service centre, there has to keep enough space for
parking the vehicles or moving the vehicles during the servicing time. Moreover, during the
building construction, it has to construct within two parts including servicing area and also
office or training area.
Project scope
Project scope are mainly referred as the project deliverables through the entire life
span of the project (Mir & Pinnington, 2014). The project scope includes the project related
information that are required for beginning of the project. The project scope is also defined as
the process of managing project tasks that must be completed within the resources, time as
well as cost. Based on the project management oriented principles, the project scope depends
on the project requirements and for that within the project, if the requirements are not cleared,
therefore it is difficult for meeting the project scope (Leach, 2014). According to this project,
the project location is selected on the city street in the industrial park. During the starting
time of the project, the project manager has made a contract with a general contractor for
executing this project within the allocated time and also cost (Too & Weaver, 2014). Within
the scope management of the project, there exists in scope, out scope as well project
constraints and also project assumptions.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4
PROJECT MANAGEMENT
In scope
The project in scope is described as the project activities that are required to conduct
during the lifespan of the project for succeeding the project goal (Joslin & Müller, 2015).
Here, based on this project, the in scope for this project are as follows:
The entire project has to be delivered within the deliverables so that the project can be
considered as successful project.
The project must complete within the allocated budget because it maintain the
feasibility of this project.
Though this project is centred on the scenario of vehicle maintenance, therefore the
project requires to construct a parking zone for vehicles during the servicing time.
This project is controlled by a general contractor and for this project, a number of
team members has to allocate for this project under the supervision of project
contractor (Müller et al., 2014).
Another in scope is that the project must construct a building and the building should
be divided by two parts including a servicing area and also office purpose.
Out scope
The out scope is the project actions which do not occur during the project lifespan.
The out scope of the project are as follows:
It does not require any air-conditioned place for the servicing area of the vehicle
maintenance facility.
It does not require a huge level of excavation of the project site for completing this
with a grade.
It does not install hidden camera within the servicing area of the vehicle maintenance
centre.
PROJECT MANAGEMENT
In scope
The project in scope is described as the project activities that are required to conduct
during the lifespan of the project for succeeding the project goal (Joslin & Müller, 2015).
Here, based on this project, the in scope for this project are as follows:
The entire project has to be delivered within the deliverables so that the project can be
considered as successful project.
The project must complete within the allocated budget because it maintain the
feasibility of this project.
Though this project is centred on the scenario of vehicle maintenance, therefore the
project requires to construct a parking zone for vehicles during the servicing time.
This project is controlled by a general contractor and for this project, a number of
team members has to allocate for this project under the supervision of project
contractor (Müller et al., 2014).
Another in scope is that the project must construct a building and the building should
be divided by two parts including a servicing area and also office purpose.
Out scope
The out scope is the project actions which do not occur during the project lifespan.
The out scope of the project are as follows:
It does not require any air-conditioned place for the servicing area of the vehicle
maintenance facility.
It does not require a huge level of excavation of the project site for completing this
with a grade.
It does not install hidden camera within the servicing area of the vehicle maintenance
centre.

5
PROJECT MANAGEMENT
Constraints
The project constraints are measured as the limitations for the project. Each of the
project has a certain number of boundaries in which the project has to complete (Todorović et
al., 2015). Based on this project, the project constraints are as follows:
The project must formulate the aims or objectives for achieving success.
The project needs to finish within the assigned budget and also times so that it can
prove the feasibility of the project (Kerzner, 2019).
It requires to maintain the quality for the project because within this project it has to
construct the paving as well as runoff and also two divisional building.
Assumptions
The project assumptions are as follows:
The project manager has suspected that this project must complete within the assigned
budget.
It has expected that this project will conduct under the supervision of general
contractor to achieve the goals.
Another assumption is based on the project time. It has highly expected that the
project should completed within the assigned timeframe.
PROJECT MANAGEMENT
Constraints
The project constraints are measured as the limitations for the project. Each of the
project has a certain number of boundaries in which the project has to complete (Todorović et
al., 2015). Based on this project, the project constraints are as follows:
The project must formulate the aims or objectives for achieving success.
The project needs to finish within the assigned budget and also times so that it can
prove the feasibility of the project (Kerzner, 2019).
It requires to maintain the quality for the project because within this project it has to
construct the paving as well as runoff and also two divisional building.
Assumptions
The project assumptions are as follows:
The project manager has suspected that this project must complete within the assigned
budget.
It has expected that this project will conduct under the supervision of general
contractor to achieve the goals.
Another assumption is based on the project time. It has highly expected that the
project should completed within the assigned timeframe.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6
PROJECT MANAGEMENT
Work breakdown structure (WBS)
The work break down structure represents the division of the project activities through
project phases (Kerzner, 2017). The work break down structure is as follows:
Figure: WBS figure
(Source: created by author)
Project schedule
Task Name Duration Resource Names
Vehicle maintenance facility project 125 days
Project initiation phase 17 days
Development of the project case 3 days project manager
Checking feasibility report 2 days financial manager,project manager
Establishing project charter 4 days project manager ,project team
Contract with general contractor 2 days general contractor,project manager
Recruit project team 5 days project manager ,project team
Approval of permission from higher
authority 1 day higher authority,project manager
Milestone 1: Completion of initiation 0 days
vehicle maintenance
facility project
Project initiation phase
Development of the
project case
Checking feasibility
report
Establishing project
charter
Contract with
general contractor
Recruit project team
Approval of
permission from
higher authority
Milestone 1:
Completion of
initiation phase
Project planning phase
Making of project
plan
Site selection
Making of resource
plan
Making of financial
plan
Creation of quality
plan
Creation of risk plan
Procurement plan
Milestone 2:
Completion of
planning phase
Project execution phase
Collection of raw
maetrials
Allocate tasks among
team member
Making of paving
with asphalt and
concrete curb
Making of runoff
with catch basins
and metal pipes
Construction of
building with two
division
Implementation of
service bay in
servicin area
Construction of
restrooms, locker
rooms
Installation of data
system
Installation of fire
alarm
Milestone 3:
Completion of
execution phase
Project monitoring and
controlling phase
Testing of servicing
equipement
Testing of data
system
Testing of fire alarm
Providing training to
employees
Milestone 4:
Completion of
monitoring and
controlling phase
Project closing phase
Signoff stakeholder
Ending of contract
Milestone 5: Project
closing phase
PROJECT MANAGEMENT
Work breakdown structure (WBS)
The work break down structure represents the division of the project activities through
project phases (Kerzner, 2017). The work break down structure is as follows:
Figure: WBS figure
(Source: created by author)
Project schedule
Task Name Duration Resource Names
Vehicle maintenance facility project 125 days
Project initiation phase 17 days
Development of the project case 3 days project manager
Checking feasibility report 2 days financial manager,project manager
Establishing project charter 4 days project manager ,project team
Contract with general contractor 2 days general contractor,project manager
Recruit project team 5 days project manager ,project team
Approval of permission from higher
authority 1 day higher authority,project manager
Milestone 1: Completion of initiation 0 days
vehicle maintenance
facility project
Project initiation phase
Development of the
project case
Checking feasibility
report
Establishing project
charter
Contract with
general contractor
Recruit project team
Approval of
permission from
higher authority
Milestone 1:
Completion of
initiation phase
Project planning phase
Making of project
plan
Site selection
Making of resource
plan
Making of financial
plan
Creation of quality
plan
Creation of risk plan
Procurement plan
Milestone 2:
Completion of
planning phase
Project execution phase
Collection of raw
maetrials
Allocate tasks among
team member
Making of paving
with asphalt and
concrete curb
Making of runoff
with catch basins
and metal pipes
Construction of
building with two
division
Implementation of
service bay in
servicin area
Construction of
restrooms, locker
rooms
Installation of data
system
Installation of fire
alarm
Milestone 3:
Completion of
execution phase
Project monitoring and
controlling phase
Testing of servicing
equipement
Testing of data
system
Testing of fire alarm
Providing training to
employees
Milestone 4:
Completion of
monitoring and
controlling phase
Project closing phase
Signoff stakeholder
Ending of contract
Milestone 5: Project
closing phase
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7
PROJECT MANAGEMENT
phase
Project planning phase 20 days
Making of project plan 4 days project manager
Site selection 3 days project manager ,Land[1]
Making of resource plan 2 days general contractor,Materials
[1],project manager
Making of financial plan 2 days financial manager,project manager
Creation of quality plan 3 days project manager ,risk analyst
Creation of risk plan 2 days project manager ,project team,risk
analyst
Procurement plan 4 days general contractor,project manager
Milestone 2: Completion of planning
phase 0 days
Project execution phase 71 days
Collection of raw maetrials 3 days Materials [1],project team
Allocate tasks among team member 4 days project manager ,project team
Making of paving with asphalt and
concrete curb 7 days Cement[1],Materials [1],project team
Making of runoff with catch basins and
metal pipes 8 days Cement[1],Materials [1],project team
Construction of building with two division 10 days Cement[1],Materials [1],project team
Implementation of service bay in servicin
area 12 days Materials [1],project team
Construction of restrooms, locker rooms 15 days project team
Installation of data system 7 days Equipment [1],project
manager ,software developer
Installation of fire alarm 5 days Equipment [1],project team
Milestone 3: Completion of execution
phase 0 days
Project monitoring and controlling phase 14 days
Testing of servicing equipement 3 days project manager ,tester
Testing of data system 3 days project manager ,tester
Testing of fire alarm 2 days Additional charges[1],project
manager ,tester
Providing training to employees 6 days project manager ,project team
Milestone 4: Completion of monitoring
and controlling phase 0 days
Project closing phase 3 days
Signoff stakeholder 2 days
financial manager,general
contractor,project manager ,project
team,risk analyst,software
developer,tester
Ending of contract 1 day general contractor,project manager
Milestone 5: Project closing phase 0 days
PROJECT MANAGEMENT
phase
Project planning phase 20 days
Making of project plan 4 days project manager
Site selection 3 days project manager ,Land[1]
Making of resource plan 2 days general contractor,Materials
[1],project manager
Making of financial plan 2 days financial manager,project manager
Creation of quality plan 3 days project manager ,risk analyst
Creation of risk plan 2 days project manager ,project team,risk
analyst
Procurement plan 4 days general contractor,project manager
Milestone 2: Completion of planning
phase 0 days
Project execution phase 71 days
Collection of raw maetrials 3 days Materials [1],project team
Allocate tasks among team member 4 days project manager ,project team
Making of paving with asphalt and
concrete curb 7 days Cement[1],Materials [1],project team
Making of runoff with catch basins and
metal pipes 8 days Cement[1],Materials [1],project team
Construction of building with two division 10 days Cement[1],Materials [1],project team
Implementation of service bay in servicin
area 12 days Materials [1],project team
Construction of restrooms, locker rooms 15 days project team
Installation of data system 7 days Equipment [1],project
manager ,software developer
Installation of fire alarm 5 days Equipment [1],project team
Milestone 3: Completion of execution
phase 0 days
Project monitoring and controlling phase 14 days
Testing of servicing equipement 3 days project manager ,tester
Testing of data system 3 days project manager ,tester
Testing of fire alarm 2 days Additional charges[1],project
manager ,tester
Providing training to employees 6 days project manager ,project team
Milestone 4: Completion of monitoring
and controlling phase 0 days
Project closing phase 3 days
Signoff stakeholder 2 days
financial manager,general
contractor,project manager ,project
team,risk analyst,software
developer,tester
Ending of contract 1 day general contractor,project manager
Milestone 5: Project closing phase 0 days

8
PROJECT MANAGEMENT
Network diagram
PROJECT MANAGEMENT
Network diagram
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9
PROJECT MANAGEMENT
Figure: Network diagram
PROJECT MANAGEMENT
Figure: Network diagram
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10
PROJECT MANAGEMENT
(Source: Created by author)
Conclusion
In this part, it has concluded that the project of vehicle maintenance facility project
should complete within cost and time. If the project manager follows the project schedule
therefore the project would complete within the timeframe. This report presents the project
scope as well as project goals and also objectives. Through the work break down structure,
the project activities are divided through project phases. This report also follows the network
diagram of this project. By following all of these things, the project must achieve success.
PROJECT MANAGEMENT
(Source: Created by author)
Conclusion
In this part, it has concluded that the project of vehicle maintenance facility project
should complete within cost and time. If the project manager follows the project schedule
therefore the project would complete within the timeframe. This report presents the project
scope as well as project goals and also objectives. Through the work break down structure,
the project activities are divided through project phases. This report also follows the network
diagram of this project. By following all of these things, the project must achieve success.

11
PROJECT MANAGEMENT
References
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management.
Project Management Institute.
Heagney, J. (2016). Fundamentals of project management. Amacom.
Joslin, R., & Müller, R. (2015). Relationships between a project management methodology
and project success in different project governance contexts. International journal of
project management, 33(6), 1377-1392.
Kerzner, H. (2017). Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Kerzner, H. (2019). Using the project management maturity model: strategic planning for
project management. John Wiley & Sons.
Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring
and monitoring project performance. John Wiley & Sons.
Leach, L. P. (2014). Critical chain project management. Artech House.
Meredith, J. R., Mantel Jr, S. J., & Shafer, S. M. (2017). Project management: a managerial
approach. John Wiley & Sons.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), 202-217.
Müller, R., Rolstadås, A., Tommelein, I., Schiefloe, P. M., & Ballard, G. (2014).
Understanding project success through analysis of project management
approach. International journal of managing projects in business.
PROJECT MANAGEMENT
References
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management.
Project Management Institute.
Heagney, J. (2016). Fundamentals of project management. Amacom.
Joslin, R., & Müller, R. (2015). Relationships between a project management methodology
and project success in different project governance contexts. International journal of
project management, 33(6), 1377-1392.
Kerzner, H. (2017). Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Kerzner, H. (2019). Using the project management maturity model: strategic planning for
project management. John Wiley & Sons.
Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring
and monitoring project performance. John Wiley & Sons.
Leach, L. P. (2014). Critical chain project management. Artech House.
Meredith, J. R., Mantel Jr, S. J., & Shafer, S. M. (2017). Project management: a managerial
approach. John Wiley & Sons.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), 202-217.
Müller, R., Rolstadås, A., Tommelein, I., Schiefloe, P. M., & Ballard, G. (2014).
Understanding project success through analysis of project management
approach. International journal of managing projects in business.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 13
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.