PROJ6016 - UPS Framework Project Management Capstone Project

Verified

Added on  2023/03/23

|18
|1092
|98
Project
AI Summary
This document presents a solved project focusing on the Uninterrupted Power Supply (UPS) framework for As-Sabuur Nigeria Limited, addressing power outage issues through generator installation. The project plan encompasses initiation, design, planning, execution, monitoring, controlling, and closure phases, detailing the work breakdown structure, Gantt chart, budget, and identified risks with mitigation strategies. It highlights essential skills for the project manager and team, including mechanical, electrical, leadership, communication, and technical expertise in diesel engines and power generation. The project aims to provide a reliable power solution, contributing to financial returns for the organization and improved living conditions for residents facing frequent power interruptions. Desklib provides access to this and other solved assignments.
Document Page
Uninterrupted Power
Supply (UPS) Frame
Work
PROJECT MANAGEMENT CAPSTONE C
(PROJ6016)
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Overview of the Organisation
The assignment represents identification as well as
planning for procurement of the Uninterrupted Power
Supply system.
Company chosen is As-Sabuur Nigeria Limited.
The objective is to install generators in organisations and
various houses.
Document Page
Overview of the Organisation
Houses in Nigeria face numerous issues in relation to
power outages.
Project plan is designed by the project manager.
Installation of generator systems in houses would prove
highly beneficial because the organization would be able
to get more financial returns.
It would allow the company to pay the labours with their
desired wages.
Document Page
Identification of a Problem and
Suggested Solutions
Chosen place does not cover under 24 hours electric
supply range.
The place faced issues due to various power outages.
People face numerous issues in their regular work.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Identification of a Problem and
Suggested Solutions
Help them in installing the two units of generator sets in
the house.
Viable solution would be helpful for the house owner in
solving the issues.
Nigeria Limited to help them in installing the generators
Document Page
Identification of a Problem and
Suggested Solutions
Stakeholders within the project are the project manager,
house owner, and site project lead.
Project manager designs the project schedule.
Design the plan for installing work on the generator,
prepare a financial plan.
Document Page
Project Plan and Budget
Incur various processes that would be important for the
success of the project.
The project would need the project manager who is responsible
for knowing the requirements.
The project will be initiated by performing a particular
negotiation work
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Project Plan and Budget
Signing of documents by both parties will provide an
assurance that would be initiated by the project.
After that the procurement of the generators would be
done.
After the installation phase is done, monitoring as well as
control is done.
Document Page
The Gantt chart of the Project
(Fig 1: The Gantt chart for the Project)
(Source: Created by author)
Document Page
The Work Breakdown Structure
Uninterrupted Power Supply
(UPS) Frame Work
Start of Project Initiation of Project Design
Negotiation with the client
Signing of document
Procurement of generator
and accessories
Installation of cables
Completion of the Initiation
phase
Planning for the
Installation
Procurement of 2
generators
Planning design for
installation
Test running of generators
Completion of planning
phase
Executing the project
Installation of Generators
Test running of generators
Completion of installation
phase
Monitoring and Controlling
Cost Variance
Schedule Variance
Scope Variance
Completion of phase
Project Closing
Payment to contractors
Payment to staffs
Project records into OPA's
Signing off of project
Lessons learnt in to OPA's
Completion of Project
Closure phase
End Project
(Fig 2: The WBS for the Project)
(Source: Created by author)
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
The Milestones of the Project
1. Completion of Initiation Phase of Project
2. Completion of planning phase of project
3. Completion of execution phase of project
4. Completing the monitoring and controlling of
installation of generator.
5. Completion of project closure phase.
Document Page
The Budget of the Project
Initiation of Project Design 19600
Planning for the Installation 4720
Executing the project 7200
Monitoring and Controlling 4800
Project Closing 3200
Total Cost for the project 39520
Total Cost for the project
(Fig 2: The Budget for the
Project)