This project charter assessment analyzes an ICT project undertaken by Virtucon for Globex, focusing on the implementation of an electronic ticketing system to replace a manual one. The project aims to improve customer experience, streamline ticket sales, and increase revenue for charity donations. The assessment covers various aspects of project management, including scope definition, resource allocation, work breakdown structure, risk analysis, quality management, and project closure. It outlines the project's value, metrics, assumptions, and potential risks, along with mitigation strategies. The quality management plan emphasizes maintaining standards and meeting stakeholder expectations. The project closure and evaluation sections assess the project's success based on predefined criteria. Appendices provide supporting literature on project management methodologies and evaluation techniques, highlighting the importance of continuous assessment throughout the project lifecycle.
Document Page
Assessment 3 ICT Project Management
9 / 2 9 / 2 0 1 7
Student’s Name
Name of University
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Project Charter
Index
Part One...........................................................................................................................2
Part Two...........................................................................................................................3
Part Three........................................................................................................................ 4
Part Four.......................................................................................................................... 9
Part Five.........................................................................................................................11
Part Six...........................................................................................................................12
References.....................................................................................................................14
1 | P a g e
Document Page
Project Charter
Part One
MOV
Project Description: A show is sorted out by the Globex partnership in the long stretch
of November consistently, where they introduce their agricultural and way of lifestyle
equipment. The show is held for three back to back days. Tickets are sold for the show
and the cash they procure by offering tickets are given to the charity in ICV. The
ticketing framework is manual so the ticket counter gets packed by individuals and
some of them topple the fence to get inside the limit without paying for the ticket. For
controlling this circumstance the Globex company chose to change its manual ticket
booking framework to electronic ticket booking framework and afterward gave over the
task to Virtucon.
Area of Impact:
Rank 1 - Customer: Now the clients will be exceptionally pleased in light of the fact that
they will never again need to remain in the long line for booking their tickets on the main
day.
Rank 2 - The selling of tickets will turn out to be more straightforward and simple than
some time recently.
Rank 3 – Finance: The money related condition will get expanded as more tickets will
be sold.
Rank 4 – Strategy: Globex Company will succeed now as an ever-increasing number of
tickets will be sold and subsequently they can give more cash to the ICV.
Rank 5 – Social: Now more tickets will be sold so Globex can give more cash to the
Indigenous Community Volunteers (ICV) and will have the capacity to demonstrate their
social advantages or favorable circumstances.
Project value:
Value 1 (Faster): Now the heap of the ticket counter can be diminished as the tickets
will be reserved online by the clients previously the begin of the show.
2 | P a g e
Document Page
Project Charter
Value 2 (Do more): This positive result will motivate Globex to expand the show and
grow more.
Metrics with time target:
Metrics Target
Start of the capital generation before the show starts. October’ 2018 onwards
Decline the heap of work in the ticket counter and at the
security door to diminish the quantity of volunteer. In November’ 2018
Development in the ticket offering volume consistently
before the show starts in November October’ 2018 onwards
After the venture usage in the primary year the development
of cash gathering and gift to ICV by 17%
End of November’ 2018
(after the RALS)
Part Two
Scope Management Plan (Piscopo, Scope Management Plan, 2017) (Wich, 2009)
Define Scope: The principle worry of this task is to make an electronic system to enable
every one of its clients to book their tickets online to rectify the over-burden of work on
the ticket counter and security entryway.
Requirement Identification: It needs the client’s ID verification to sign in, a unique ID
with a scanner tag for recognizing every guest, to be secured from digital wrongdoing.
Functional Requirements:
In-Scope: While making the electronic online ticket booking framework, another
code for deciding the evidence of the client, give a framework which is anything
but difficult to get to, and ought to contain all the vital hardware and a scanner
label machine for checking the client’s character verification.
Out-of-Scope: all sort of after deals project like the upkeep of the equipment and
afterward give preparing to nonstop change and support of the framework or any
other updating related issue
3 | P a g e
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Project Charter
List of Resources:
People: Project Manager, Database Designer, Network Engineer, Admin Manager
Technology: LAN (Local Area Network), Connected Systems
Facilities: Internet facility, proper office set-up, office boy
Others: travel, training, vehicles, etc.
Part Three
Screenshots of MS Project Software
Work Breakdown Structure (WBS): (Piscopo, Work Breakdown Structure (WBS), 2017)
4 | P a g e
Document Page
Project Charter
5 | P a g e
Document Page
Project Charter
Milestone List:
Activities & its Resources:
6 | P a g e
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Project Charter
Activities & direct labor costs:
7 | P a g e
Document Page
Project Charter
Gantt chart:
8 | P a g e
Document Page
Project Charter
Part Four
Assumptions
Financial plan isn't an issue for the Project
Assets might be constantly accessible all through the task, so no issue with their
accessibility
Partners are very much distinguished and need not stress over their
investigation, as Virtucon is a long-term specialist of Globex
Volunteers are all around qualified with the goal that they can be prepared after
the usage of electronic ticketing framework
Risk Analysis (WordPress, 2009) (ThreatsAndOpportunities, 2017)
RISK
No.
Description Proba
bility
Imp
act
Prod
uct
Ran
k
Own
er
Response
1 Stakeholders are
not identified
properly
40% 80% 320
%
1 PM All the associates
ought to be
distinguished
legitimately and the
9 | P a g e
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Project Charter
undertaking work
ought to be checked
over and over the
event of each
adjustment in the
venture
2 the extent of the
work can get
expanded
because of
wrong necessity
conclusion of
partners
30% 70% 210
%
3 PM After doing the
partners clear proof
reasonably they
ought to be adjusted
according to the
need
3 If the work isn't
overseen by the
partners
legitimately it can
cause numerous
issues in the
project
40% 70% 280
%
2 PM Earlier than finishing
up anything all the
recognized basics
ought to be
examined
4 due to the wrong
choice of
partner, there is
a risk of the
increase in
project scope
40% 50% 200
%
4 PM In each stage,
master consider like
degree check
approach ought to be
finished
5 deficient
submission of all
documents
archives may
defer the project
30% 40% 120
%
5 PM All the finishes of
each unique stage
rather than to be
submitted in the last
stage
10 | P a g e
Document Page
Project Charter
and cost may get
increased
Part Five
Quality Management Plan (Virginia Polytechnic Institute and State University, 2013)
(Project Management Knowledge, 2017)
Team’s Philosophy for Quality Management: The colleagues should endeavor to keep
up required nature of the things and should meet the partner's desires. To evade the
need of expanded time, everything ought to be checked thoroughly before the finish of
each stage. Every one of the necessities ought to be satisfied with a quality standard
and given time. Every one of the laborers should concentrate on their work to counter
rework.
Verification Activity:
Activity Target
The project ought to be conveyed on time. 6th September 2018
Every one of the necessities of the clients should meet. By 6th September 2018
The cash spent on every single work of the task ought not to
overshoot the general project’s financial plan.
By 6th September 2018
The dangers of this task should be perceived and the
progress should be controlled by the same
During project
Validation Activity:
Activity Target
Before shutting the project, all expectations must be conveyed
according to the benchmark plan time and cost
By 6th September
2018
Subsequent to finishing each stage, every one of the criteria By 6th September
11 | P a g e