Integrated Information System Project Charter for Health-Life Ltd
VerifiedAdded on  2019/09/24
|5
|1052
|154
Project
AI Summary
This project charter details the implementation of an integrated information system for Health-Life Ltd, a healthcare provider aiming to improve operational efficiency and patient data management. The project addresses the need for a more robust system to handle an increased patient load at a new facility. The charter outlines the business case, project scope including computer implementation, online connectivity, cloud services, software and website development, and data security. It provides a detailed milestone schedule with completion dates, responsible personnel, and acceptance criteria. The document also includes resource requirements, a stakeholder list, team operating principles, and a risk mitigation plan to address potential challenges such as team member departures and cost or duration extensions. The project aims to integrate all hospital functions, enhance data security, and train employees on the new system, with a completion target of December 31, 2017.

Project Charter
Implementing Integrated Information System
Student Name:
Student ID:
Course Name:
Course ID:
Faculty Name:
University Name:
Implementing Integrated Information System
Student Name:
Student ID:
Course Name:
Course ID:
Faculty Name:
University Name:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Business Case
Health-Life Ltd provides various health services to the local community and to the patients who
come from other cities. The hospital is running good and there are brighter opportunities ahead.
It is expected that due to the improvement in the economy, people will prefer better medical
services. The current operational procedures of the hospital can process only 20-25 patients a day
with the total number of physicians it has in place. The management sees good opportunities
ahead and wants to step up the processes. The company will start the new operation at its new
facility in the next premise. The additional facility will allow the hospital to manage additional
20-25 patients a day. However, the management is concerned about the effective management of
the increased patient number and tracking all the records on regular basis. Moreover, the security
of the patients’ personal information is another concern. The paper based mechanisms of
managing the patient data will no longer be effective after the commencement of the new
facility. Apart from this, the management wants to integrate the entire functions within the
organization together so that it can keep track of all the activities and get updates when desired.
The management has hired a consultant who can help them overcome this challenge. The
consultant has suggested the management to implement integrated information technology.
Project Scope
The project is focused towards upgrading the entire mechanisms of the hospital system. The new
system will increase the operational efficiency and more patients will be handled well. The
project will bring together the heads of various departments and will implement an integrated
information technology. Mentioned below is the project scope that will be kept in consideration
while moving ahead with the project:
- Implementation of computers in all the five departments (Marketing, Finance, Human
Resources, Supply Chain, and Operations)
- Online Connectivity of the entire computer system through LAN
- Establishment of Cloud Service for data storage
- Operation specific software development
- Website and Mobile App Development for online appointment and patient tracking
- Storage of patient data on cloud
- Safety and Security Implementation
Milestone Schedule and Acceptance Criteria
Milestone Completion
Date
Responsible
Personnel
Acceptance Criteria
Need Assessed November 1,
2016
Project Manager,
Project Analyst
Entire need of the hospital
identified
Health-Life Ltd provides various health services to the local community and to the patients who
come from other cities. The hospital is running good and there are brighter opportunities ahead.
It is expected that due to the improvement in the economy, people will prefer better medical
services. The current operational procedures of the hospital can process only 20-25 patients a day
with the total number of physicians it has in place. The management sees good opportunities
ahead and wants to step up the processes. The company will start the new operation at its new
facility in the next premise. The additional facility will allow the hospital to manage additional
20-25 patients a day. However, the management is concerned about the effective management of
the increased patient number and tracking all the records on regular basis. Moreover, the security
of the patients’ personal information is another concern. The paper based mechanisms of
managing the patient data will no longer be effective after the commencement of the new
facility. Apart from this, the management wants to integrate the entire functions within the
organization together so that it can keep track of all the activities and get updates when desired.
The management has hired a consultant who can help them overcome this challenge. The
consultant has suggested the management to implement integrated information technology.
Project Scope
The project is focused towards upgrading the entire mechanisms of the hospital system. The new
system will increase the operational efficiency and more patients will be handled well. The
project will bring together the heads of various departments and will implement an integrated
information technology. Mentioned below is the project scope that will be kept in consideration
while moving ahead with the project:
- Implementation of computers in all the five departments (Marketing, Finance, Human
Resources, Supply Chain, and Operations)
- Online Connectivity of the entire computer system through LAN
- Establishment of Cloud Service for data storage
- Operation specific software development
- Website and Mobile App Development for online appointment and patient tracking
- Storage of patient data on cloud
- Safety and Security Implementation
Milestone Schedule and Acceptance Criteria
Milestone Completion
Date
Responsible
Personnel
Acceptance Criteria
Need Assessed November 1,
2016
Project Manager,
Project Analyst
Entire need of the hospital
identified

Implementation Plan
Development
November 15,
2016
PM, Management Approved from Management
Resources Requirement
Prepared
November 25,
2016
Project Analyst,
Procurement
Manager
Approved by Project
Manager
Resources Procured December 25,
2016
Procurement
Manager
Resources are as per the
requirements
Computer
Implementation
February 15,
2017
PM, System
Engineers
Computers have been
installed in each of the five
departments
Online Connectivity
through LAN
March 20,
2017
Network Engineers All the computers are
connected to the web
Cloud Service Vendor
Identified
April 15,
2017
PM, Project Analyst Suitable cloud service vendor
has been identified and
approved by the management
Cloud Service Installed May 30, 2017 Software Designers,
Software
Developers
Cloud service has been
installed and running
Software Development July 30, 2017 Software Designers,
Software
Developers
Software designed and
developed.
Website Development March 15,
2017
Outsourced Outsourced to external
developer. Developed as per
requirement
Mobile App
Development
April 15,
2017
Outsourced Outsourced to external
developer. Developed as per
requirement
Cloud, Mobile App,
Website, and Computers
Integrated
September 5,
2017
Software
Developers,
Network Engineers
Entire system is integrated
and working as required
Patient Data Stored October 30,
2017
PM, Data Entry
Operators
Entire paper based recorded
updated to the online system
Safety and Security
Provision
November 15,
2017
PM, Security
Analyst, Software
Developers
Effective security is in place
Training and
Development
December 31,
2017
PM, Trainers Concerned employees are
trained to use the system
Risks and Mitigation Plan
Identified Risks Responsible Personnel Mitigation Plan
Members leaving in between
as project duration is very
long
Project Manager Should have proper backup of
members and staffs in case
this happens
Cost and Duration Extension Project Manager Ensure that the project moves
Development
November 15,
2016
PM, Management Approved from Management
Resources Requirement
Prepared
November 25,
2016
Project Analyst,
Procurement
Manager
Approved by Project
Manager
Resources Procured December 25,
2016
Procurement
Manager
Resources are as per the
requirements
Computer
Implementation
February 15,
2017
PM, System
Engineers
Computers have been
installed in each of the five
departments
Online Connectivity
through LAN
March 20,
2017
Network Engineers All the computers are
connected to the web
Cloud Service Vendor
Identified
April 15,
2017
PM, Project Analyst Suitable cloud service vendor
has been identified and
approved by the management
Cloud Service Installed May 30, 2017 Software Designers,
Software
Developers
Cloud service has been
installed and running
Software Development July 30, 2017 Software Designers,
Software
Developers
Software designed and
developed.
Website Development March 15,
2017
Outsourced Outsourced to external
developer. Developed as per
requirement
Mobile App
Development
April 15,
2017
Outsourced Outsourced to external
developer. Developed as per
requirement
Cloud, Mobile App,
Website, and Computers
Integrated
September 5,
2017
Software
Developers,
Network Engineers
Entire system is integrated
and working as required
Patient Data Stored October 30,
2017
PM, Data Entry
Operators
Entire paper based recorded
updated to the online system
Safety and Security
Provision
November 15,
2017
PM, Security
Analyst, Software
Developers
Effective security is in place
Training and
Development
December 31,
2017
PM, Trainers Concerned employees are
trained to use the system
Risks and Mitigation Plan
Identified Risks Responsible Personnel Mitigation Plan
Members leaving in between
as project duration is very
long
Project Manager Should have proper backup of
members and staffs in case
this happens
Cost and Duration Extension Project Manager Ensure that the project moves
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

as per schedule along with
provision of extra funds and
more intentional slack time in
hand
Resistance from Employees Management Using Kotter’s Change
Management tool effectively
Required Resources
Description Estimated Cost (Top-Down) ($)
10 Computer Systems 2000
LAN Equipment 1000
Cloud Service 1500 + 500/year
Total Physical Resources 4500
Software Developer, Software Designers, System
Engineers, Network Engineers
20/hr
PM 25/hr
Communication Manager 18/hr
Project Analyst 18/hr
Trainer 20/hr
Data Entry Operators 12/hr
Total (Estimated Human Resource) 246044
[(20*4+25+18+18+20+12)/9*320*40]
Total Estimated 250544
Stakeholder List
Stakeholder Description
Management (Sponsors) Will fund the project and concerned with the
entire project success
Project Manager Look after the project success and entire
resource management
Project Analyst Analyses the project requirement and other
areas
Procurement Manager Procures required resources and talks to
vendors
System Engineer Implement Computers in various departments
Network Engineer Implement LAN in the entire organization
Software Designer Develops designs for software to be used in
hospital operation
Software Developer Develops software based on designed build by
software designer
provision of extra funds and
more intentional slack time in
hand
Resistance from Employees Management Using Kotter’s Change
Management tool effectively
Required Resources
Description Estimated Cost (Top-Down) ($)
10 Computer Systems 2000
LAN Equipment 1000
Cloud Service 1500 + 500/year
Total Physical Resources 4500
Software Developer, Software Designers, System
Engineers, Network Engineers
20/hr
PM 25/hr
Communication Manager 18/hr
Project Analyst 18/hr
Trainer 20/hr
Data Entry Operators 12/hr
Total (Estimated Human Resource) 246044
[(20*4+25+18+18+20+12)/9*320*40]
Total Estimated 250544
Stakeholder List
Stakeholder Description
Management (Sponsors) Will fund the project and concerned with the
entire project success
Project Manager Look after the project success and entire
resource management
Project Analyst Analyses the project requirement and other
areas
Procurement Manager Procures required resources and talks to
vendors
System Engineer Implement Computers in various departments
Network Engineer Implement LAN in the entire organization
Software Designer Develops designs for software to be used in
hospital operation
Software Developer Develops software based on designed build by
software designer
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Outsourced Agency Develops mobile app and website
Data Entry Operator Converts offline data to online
Security Analyst Analyses the online security measures and
helps developers in implementation
Trainer Trains the employees to use the new system
Team Operating Principles
1. The entire team will not be taking any leave without the approval of project manager. PM
must be informed a month earlier
2. Entire communication will take place through emails and all members will be kept in
loop through using group email function
3. All members must attend all meetings no matter what
4. All members will communicate in respectable manner
Signature and Commitment
Management (Sponsors) ____________________________________
Project Manager __________________________________________
Project Analyst ___________________________________________
Procurement Manager ______________________________________
System Engineer ___________________________________________
Network Engineer __________________________________________
Software Designer __________________________________________
Software Developer _________________________________________
Outsourced Agency __________________________________________
Data Entry Operator __________________________________________
Security Analyst _____________________________________________
Trainer ____________________________________________________
Data Entry Operator Converts offline data to online
Security Analyst Analyses the online security measures and
helps developers in implementation
Trainer Trains the employees to use the new system
Team Operating Principles
1. The entire team will not be taking any leave without the approval of project manager. PM
must be informed a month earlier
2. Entire communication will take place through emails and all members will be kept in
loop through using group email function
3. All members must attend all meetings no matter what
4. All members will communicate in respectable manner
Signature and Commitment
Management (Sponsors) ____________________________________
Project Manager __________________________________________
Project Analyst ___________________________________________
Procurement Manager ______________________________________
System Engineer ___________________________________________
Network Engineer __________________________________________
Software Designer __________________________________________
Software Developer _________________________________________
Outsourced Agency __________________________________________
Data Entry Operator __________________________________________
Security Analyst _____________________________________________
Trainer ____________________________________________________
1 out of 5
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.