Project Charter: Business Case for Online Information System

Verified

Added on  2023/03/17

|18
|2457
|75
Project
AI Summary
This project charter presents a comprehensive plan for the development of an online information system for Globex, addressing the Virtucon/Globex scenario. The document begins with an overview of the Measurable Organizational Value (MOV), detailing the project's impact on strategy, customers, financials, operations, and social aspects. It identifies the types of value (better and do more) and establishes a timeline for MOV achievement. The charter then defines the project's scope (in-scope and out-of-scope), resources (hardware, software, and facilities), and a detailed Work Breakdown Structure (WBS) with milestones and deliverables. Activities, resource assignments, and budget estimations are provided, along with a Gantt chart for project scheduling. A thorough risk analysis and register are included, along with a quality management plan that outlines team philosophy, verification, and validation activities. The charter concludes with a closure checklist, project evaluation criteria, and an annotated bibliography, providing a complete framework for project execution and management.
Document Page
Running head: PROJECT CHARTER
Project charter: Business Case
Name of Student
Name of the University
Author Note
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1
PROJECT CHARTER
Table of Contents
Part One...........................................................................................................................................3
Measurable Organizational Value (MOV)..................................................................................3
Area of impact.........................................................................................................................3
Types of value..............................................................................................................................4
Better........................................................................................................................................4
Do more...................................................................................................................................4
Time frame for MOV...................................................................................................................4
MOV Summary...........................................................................................................................4
Part Two...........................................................................................................................................5
In – Scope....................................................................................................................................5
Out – Scope..................................................................................................................................5
Resources.....................................................................................................................................5
Technologies............................................................................................................................6
Facility and Others...................................................................................................................6
Part Three.........................................................................................................................................7
WBS.............................................................................................................................................7
Milestones for each phase and deliverable..................................................................................7
Activities / Tasks.........................................................................................................................8
Resource Assignments.................................................................................................................9
Estimation of the Activities.........................................................................................................9
Budget........................................................................................................................................12
Part Four Project Risk Analysis and Plan......................................................................................13
Assumptions..............................................................................................................................13
Risk register...........................................................................................................................13
Part Five Quality Management Plan..............................................................................................13
Team Philosophy.......................................................................................................................13
Set of Verification Activities.....................................................................................................14
Set of Validation Activities.......................................................................................................14
Part Six...........................................................................................................................................14
Closure Checklist.......................................................................................................................14
Project Evaluation......................................................................................................................15
References......................................................................................................................................16
Document Page
2
PROJECT CHARTER
Part One
Measurable Organizational Value (MOV)
It can be defined as the standard limit or the baseline set for approving the project
execution. There will be a standard for the accomplishment and delivery of the project and the
final deliveries must meet this standard criterion. The project charter is developed must be
meeting the needs of the project or the charter developed.
Area of impact
Strategy: The planning will be to develop a sophisticated project management plan. It can
allow the different stakeholders to be focused on the strategic modifications those are necessary
for the project delivery (Kerzner, 2018).
Customer: The farmers and the local government will be introduced with fast and smooth
services in their field of concerns.
Financial: The budget plan will be developed considering the project quality, and the
baseline of the project will be based on the same. The budget of the project will be managed in a
way, that the quality of the project does not get hampered.
Operational: The existing system will be upgraded, allowing the staffs and the end
consumers in managing the same operations more smoothly and automatically.
Social:Social friendly approaches will be adopted, considering the involvement of the
different stakeholders and adoption of the sustainable factors for facilitatingthe different project
activities (Cagliano, Grimaldi &Rafele, 2015).
Document Page
3
PROJECT CHARTER
Types of value
Better
The quality and the ways of the service delivery will be improved and fasten, considering
the objectives and scope of the project. The deliverables or the outcomes will be of high quality
comparing with expected deliveries.
Do more
The improved and enhanced approaches of operation deliveries will be allowing the
clients to manage the daily operations in much smooth way (Harrison & Lock). The continuous
growth of the clients will be the major target.
The time frame for MOV
WBS Task Name Duration Start Finish
1 Communication Plan 21 days Mon 27-05-19 Mon 24-06-19
1.1 Consideration of modification required
sectors 5 days Mon 27-05-19 Fri 31-05-19
1.2 Impact analysis 4 days Mon 03-06-19 Thu 06-06-19
1.3 Value identification 3 days Fri 07-06-19 Tue 11-06-19
1.4 Metrics development 4 days Wed 12-06-19 Mon 17-06-19
1.5 Stakeholder informing 3 days Tue 18-06-19 Thu 20-06-19
1.6 Stakeholders confirmation 2 days Fri 21-06-19 Mon 24-06-19
MOV Summary
The attempts being delivered will be allowing an advanced online management system
for the Globex in a manner to allow them to manage and deliver the daily operations. The
centralized and online accessible system will be contributing to the elimination of the workload
and distribution of the workload accordingly (Kerzner & Kerzner, 2017). It will be setting the
exact values for the organization that is required in managing the deliverables.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4
PROJECT CHARTER
Part Two
In – Scope
1. Virtucon will be contributing in the development of the system that can introduce smooth
and effective management of the daily operations for the Globex.
2. Identification and elimination of the existing issues faced by the organization while
developing the system
3. Development of the new information system aligning with the organizational needs and
values
Out – Scope
Future needs have been considered on the assumption basis, and specific considerations
have not been made for future development.
The marketing strategy of the Globex will not be considered throughout the project
delivery
The future enhancement in the existing organizational size will not be considered while
developing the project.
The involvement of the third party and the outsources will also be kept out-scope for the
project.
Document Page
5
PROJECT CHARTER
Resources
Technologies
Hardware: Server, Cables, electricity, External Storage, Setup components, and testing
devices
Software: MYSQL, developer tools, testing platform, network, internet, intranet
Miscellaneous: cabling, switches, network links
Facility and Others
All time availability, accessibility of the resources and the comfort for all the involved
stakeholders involved in the operational activities are the major facility requirement for the
project.
Document Page
6
PROJECT CHARTER
Part Three
WBS
Milestones for each phase and deliverable
Task Name Duration Start Finish
Online Information System development for
Globex 78 days Mon 03-06-19 Wed 18-09-19
Stage 1: Project Planning 37 days Mon 03-06-19 Tue 23-07-19
Approval 0 days Tue 23-07-19 Tue 23-07-19
Stage 1 completed 0 days Fri 12-07-19 Fri 12-07-19
Stage 2: Project Initiation 47 days Mon 03-06-19 Tue 06-08-19
Stage 2 completed 0 days Tue 06-08-19 Tue 06-08-19
Stage 3: Project Execution 59 days Tue 11-06-19 Fri 30-08-19
Stage 3 completed 0 days Fri 30-08-19 Fri 30-08-19
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
PROJECT CHARTER
Stage 4: Training 6 days Mon 02-09-19 Mon 09-09-19
Stage 4 completed 0 days Tue 03-09-19 Tue 03-09-19
Stage 5: Project Closing 11 days Wed 04-09-19 Wed 18-09-19
Stage 5 completed 0 days Mon 16-09-19 Mon 16-09-19
Activities / Tasks
Document Page
8
PROJECT CHARTER
Resource Assignments
Document Page
9
PROJECT CHARTER
Estimation of the Activities
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10
PROJECT CHARTER
Gantt chart:
Document Page
11
PROJECT CHARTER
Budget