This report provides a comprehensive analysis of the project planning, reporting, and completion aspects of the South Australian Health and Medical Research Institute (SAHMRI) construction project. The report begins with an executive summary outlining the project manager's role in construction, emphasizing planning and time management. It then delves into various project contracts, including cost-plus-fee, cost of work plus fee, GMP, and design-build, along with their legal considerations and advantages. The pre-planning section assesses key concerns like scope changes, accountability, and risk management, and analyzes approaches for on-time delivery, cost breakdowns, and Work Breakdown Structure (WBS) details. The report further investigates communication management strategies, including communication plans, stakeholder reporting, and report details. Finally, it examines project close-out, discussing the roles of various elements and methods for coordinating understandings. The report utilizes a case study approach, referencing the SAHMRI project, and includes a Gantt chart and WBS to visually represent project timelines and task breakdowns, offering valuable insights into construction project management.
Document Page
Running head: PROJECT PLANNING, REPORTING AND COMPLETION
Project planning, reporting and completion
(South Australian Health and Medical Research Institute)
Name of the student:
Name of the university:
Author Note
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1PROJECT PLANNING, REPORTING AND COMPLETION
Executive summary
The project manager has different roles in the sector of constructions. This has included the planning
and time management. This has been helpful to ensure that projects get completed under particular
frames of time. For evaluating the activities more effectively, the construction project management
of South Australian Health and Medical Research Institute is chosen in the report as the case study.
Apart from this, various types of contracts in the projects are discussed in the study. Additionally,
the pre-planning of the project is evaluated. Then, various methods to make communication is been
investigated in the study along with a description of the closeout of the present project.
Document Page
2PROJECT PLANNING, REPORTING AND COMPLETION
Table of Contents
Introduction:..........................................................................................................................................3
1. Discussion on the project contracts:..................................................................................................3
1.1. Legal concerns and various advantages of various expected experiences through the projects:3
1.2. Contracts recommended for the projects:...................................................................................5
2. Discussion on project pre-planning:..................................................................................................6
2.1. Assessing the main concerns needed to be indicated prior to beginning the construction of
SAHMRI:...........................................................................................................................................6
2.2. Analyzing the smartest approach for meeting the on-time-delivery for SAHMRI’s
construction project:..........................................................................................................................7
2.3. Cost breakdown to be used:........................................................................................................7
2.4. Levels of details for the present Work Breakdown Structure:...................................................8
3. Analyzing the ways of Controlling Communication:......................................................................11
3.1. The development of the plan of communication management to deliver a suitable status for
the stakeholders of SAHMRI:.........................................................................................................11
3.2. Evaluation of how to use the reports to denote the stakeholder expectations:.........................12
3.3. Investigation of the details of levels for making the reports of stakeholders regularly:...........12
4. Investigating project close-out:........................................................................................................13
4.1. Discussion on the roles of various elements during the project close-out:...............................13
4.2. Analyzing the methods of coordinating with the components of the understandings:.............15
Conclusion:..........................................................................................................................................15
References:..........................................................................................................................................16
Document Page
3PROJECT PLANNING, REPORTING AND COMPLETION
Introduction:
The project manager has various roles in the area of construction. It involves time
management and planning. It is useful to assure that the projects are finished under specific set
timeframes. To understand the activity better, the case study of SAHMRI or “South Australian
Health and Medical Research Institute” is chosen.
In this report, at first different kinds of contracts in projects are demonstrated. Next, the pre-
planning of the project is discussed. Apart from this, the ways in which communication is sustained
is investigated in the paper. Ultimately, the study makes a demonstration on the project closeout.
1. Discussion on the project contracts:
1.1. Legal concerns and various advantages of various expected experiences through the
projects:
Different stipulated and lump-sum contracts:
For this, the cost-plus-fee is required to be implemented. Under the contract, SAHMRI must
provide permission to pay the contractors for different incurred costs. Apart from this, it has includes
the agreed-upon fees, with a specific amount of the fees (Sears et al., 2015).
Contracts that are the cost of work plus fee:
The costs have included labours and materials. It has consisted of the costs that can be
incurred in the entire activity. Further, SAHMRI has been found to be preferring the contracts. This
comprises of the expenses meeting the flexibility to undertake modifications as the project makes
developments (Zheng et al., 2016). Nevertheless, as the business shows any lack of experience under
the construction project, a strong budget must be implemented. This must be better off with different
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4PROJECT PLANNING, REPORTING AND COMPLETION
prices that are lump-sum. The reason is that there are different unavoidable uncertainties about the
ultimate cost of the project. This is priced through the base of the cost-plus.
The expense of the work plus fee having the contract of GMP or guaranteed maximum price:
Here, the contractors have been tendering the greater cost of the current project. Thus, they
have been pricing the risks that are to be considered. In this way, they are accepted to the client in
terms of the certainty priority. Here, for example, as any client acquires any specific available fund,
the expense can never get exceeded (Saunders et al., 2017). However, the client has been found to be
requesting for extra expenses and then the scope of working evolves. At this situation, the contract
has been delivered with the expense to be raised. Similarly, as the activity is neglected, the expense
can also be decreased. Instead of the word the “GMP”, the clients should be assured that they
acquire enough quantity of contingency.
Contract of CM or construction management:
The creator of SAHMRI is responsible for engaging the sub-contracts. Thus they can direct
the tasks. It has been providing the owners with a different type of warranties to the working quality.
Under the specific contracts of management of construction, here are denoted third-party for the
representatives of clients (Grover & Froese, 2016).
Design-build or design-and-construct contract:
In the present situation, this has been useful for communicating in an instantaneous way. In this way,
they are able to be effectively making communication having a quick pace. Moreover, it has
included the entire process to develop the project schedule.
Document Page
5PROJECT PLANNING, REPORTING AND COMPLETION
Manners for eradicating the changes under contract kinds:
In the following demonstration, there should be providing of various phases. This must be
useful for project management in effectively managing the contractors (Martínez-Rojas, Marín &
Vila, 2015).
Contract planning:
In starting the contract in a proper manner, there is the necessity of reserving enough time
and prepare the contracting methods.
Contractor selection:
In this way, it has been including the documentation of the companies and employees having
smart references of prior activities (Igwe, Nasiri & Hammad, 2017).
Contract administration:
Thus, one can be assumed that enough planning is required to be performed. At this case, the
project managers should be following the activity of the contractors very nearly. It can be compared
to different contractual requirements.
1.2. Contracts recommended for the projects:
Here, various types of contractors for SAHMRI’s project has been involving the following.
Specific fixed price
Particular price fee regarding incentive
Specific expense and adjustment of economic price.
Document Page
6PROJECT PLANNING, REPORTING AND COMPLETION
2. Discussion on project pre-planning:
2.1. Assessing the main concerns needed to be indicated prior to beginning the construction of
SAHMRI:
These are demonstrated below.
Changing of scope:
This is one of the essential concerns for the current project. It has been arising because of the
lack of goals defined.
No amount of accountability:
It has been generating issues for managing a construction project. This is because of the lack
of accountabilities. Here, the managers are responsible for laying out of the project aims and for
assigning that (Siew, 2016).
Lack of risk management:
This is important for the current projects as the risks goes bigger. This is much more
expensive than before.
Stakeholder Indifference:
This can harm the projects. Here, the lack of participation of stakeholders is a common issue
for SAHMRI. Since the stakeholders have been indifferent to the tasks at the site; they have been
resulting in reworks and delays. Apart from this, an important concern for the construction project
management can be performed through the construction management software. Here, for example,
the case of “eSUBs’s mobile-first”, the project management has been on the basis of clouds (Halpin,
Lucko & Senior, 2017). This is to concentrate on the needs of subcontractors. It can be done by
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7PROJECT PLANNING, REPORTING AND COMPLETION
collecting the data in the sectors of initiating activities. Here, the software is able to bridge the gaps
between the area and office. It is useful for providing the visibility of the tasks at the job site (Brioso,
2015).
2.2. Analyzing the smartest approach for meeting the on-time-delivery for SAHMRI’s
construction project:
These are listed below.
Here, the points of closing are useful to provide the projects in a successful manner.
Here, the articulation of the main learning before finishing and using the learning for future
usage must be performed.
Placing the main stakeholder informed and must be found under the buy-in as needed.
A review of the project progress must be done for the project with suitable tasks. This s to
halt the projects to get failed (Dykstra, 2018).
Ensuring the team members having proper information is helpful to undertake the activities
and turn into accountable.
Receiving clear project requirements for the simple analysis of the necessities.
Getting an eye on the details of the risks, tasks, issues, communications and the necessities.
2.3. Cost breakdown to be used:
Here, for example, various kick-off projects can be utilized. It can be used for low costs and high
qualities. Here, all the team members, customers and vendor has been informed and should be aware
of the various expectations. This must be regarding the time any specific task can begin. Further, the
time of performances and completion time and data is to be laced under the timesheets, expenses,
documents and deliverables that are to be involved (Ulhaq et al., 2017).
Document Page
8PROJECT PLANNING, REPORTING AND COMPLETION
Apart from this, there should be variable expenses. Further, the change in the project life-cycle
has never consisted of the longer duration and time of different years. For instance, the channel or
euro Tunnel project started. Since the construction has been taking place, there have been various
costs of variables such as rates of labours and costs for fuels (Dave et al., 2016). Further, for
SAHMRI, the particular expenses have been altering around the life-cycle of the project. Again, for
example, whenever roads are constructed, the excavators and the bulldozers are the particular costs.
2.4. Levels of details for the present Work Breakdown Structure:
Task Name Duration Start Finish Predecessors
Schedule of baseline for the
construction project of
SAHMRI
2 days Thu 5/9/19 Fri 5/10/19
Managing schedule for
SAHMRI's construction
project
5 days Mon 5/13/19 Fri 5/17/19 1
Developing various
contingency plans
5 days Mon 5/20/19 Fri 5/24/19 2
Making communication
and collaboration
5 days Mon 5/27/19 Fri 5/31/19 3
Budgeting and forecasting 4 days Mon 6/3/19 Thu 6/6/19 4
Budgeting and business 4 days Fri 6/7/19 Wed 6/12/19 5
Document Page
9PROJECT PLANNING, REPORTING AND COMPLETION
planning
Management leadership 5 days Thu 6/13/19 Wed 6/19/19 6
Risk management 6 days Thu 6/20/19 Thu 6/27/19 7
Controlling and
documenting the overall
progress
6 days Fri 6/28/19 Fri 7/5/19 8
Schedule management of
various types of scope
modifications
4 days Mon 7/8/19 Thu 7/11/19 9
Approval of the schedule
milestones
2 days Fri 7/12/19 Mon 7/15/19 10
Figure 1: “Gantt chart for the current project”
(Source: Created by Author)
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10PROJECT PLANNING, REPORTING AND COMPLETION
0
Project planning,
reporting and
completion of
construction
management of
SAHMRI
1
Schedule of baseline
for the construction
project of SAHMRI
2
Managing schedule for
SAHMRI's construction
project
3
Developing various
contingency plans
4
Making communication
and collaboration
5
Budgeting and
forecasting
6
Budgeting and
business planning
7
Management
leadership
8
Risk management
9
Controlling and
documenting the
overall progress
10
Schedule management
of various types of
scope modifications
11
Approval of the
schedule milestones
0
1234567891 01 1
48 days 0%
5/9/19 7/15/19
2 days 0%
5/9/19 5/10/19
5 days 0%
5/13/19 5/17/19
5 days 0%
5/20/19 5/24/19
5 days 0%
5/27/19 5/31/19
4 days 0%
6/3/19 6/6/19
4 days 0%
6/7/19 6/12/19
5 days 0%
6/13/19 6/19/19
6 days 0%
6/20/19 6/27/19
6 days 0%
6/28/19 7/5/19
4 days 0%
7/8/19 7/11/19
2 days 0%
7/12/19 7/15/19
Figure 2: “WBS for the current project”
(Source: Created by Author)
Document Page
11PROJECT PLANNING, REPORTING AND COMPLETION
Here, the initial level is WBS’s project summary. It has been summarizing the total project
and consisting of the definition of the works under three levels. They have been serving as the
contractors to develop the distinct WBS which is contract specific. Next, there are the contractors of
the Work Break Down Structure (Demirkesen & Ozorhon, 2017). This is developed through
different contractors of the projects n the basis of the tasks of contracts. Thus, it has been based on
the scopes and deliverables that are present in the contract.
3. Analyzing the ways of Controlling Communication:
3.1. The development of the plan of communication management to deliver a suitable status
for the stakeholders of SAHMRI:
Here, the project manager has required to become a more structured approach regarding
communication. Here, the communication models are comprised of three sections. Here, firstly the
receiver, message and the sender are to be determined. All the messages are been encoded by various
senders. It is needed to be transmitted to receivers and is required to be decoded (Mubarak, 2015).
Apart from this, there are different factors of noises such as receiver educations, cultural impacts and
languages and the ways in which the message can get decoded by the help of receivers.
Moreover, the requirements of information and communication of the stakeholders are to be
considered to pan the combination process. Further, the clear and concise communications require
controlling the communications in structured way and move for the impactful types of
communication in the case. Here, initially, the formal written document is to be considered. This is
used during complicacy about the planning of the project planning, charters, and memos for
prolonged distances (Zhou, Goh & Li, 2015). Further, the following one is the verbal format. This
can be used for presentations and speeches. It can be utilized for notes and emails that are
chevron_up_icon