This Project Controls Report analyzes the Kerb Works (BW229/15) project, focusing on key aspects of project management. The report is structured around controllable categories, including deliverables, configuration, status accounts, logs, and identified issues. Within each category, the report outlines specific items, relevant PMBOK knowledge areas, and procedural outputs. The analysis includes configuration control procedures, detailing input, tools & techniques, and output for each item. Furthermore, the report examines time-driven items, assessing how various factors impact the project schedule. The report also references sources like the Washington State Department of Transportation and Leadership Formation. The report provides a comprehensive overview of project controls, addressing issues such as safety, quality, cost, schedule, and procurement challenges, with recommendations for change control and risk mitigation.
Document Page
PROJECT CONTROLS REPORT
KERB WORKS (BW229/15) PROJECT
PPMP20010 Project Controls Report for
Controls Assignment
1 PROJECT INFORMATION
Project Name: Kerb Works (BW229/15) Project
Date: 26th August 2017
Project Ownership: Project Controls
Prepared by: Name of Student, Project Manager
Distribution List: List of those receiving the report
Head Engineer, Client
Project Manager
Sponsor of contractor organisation
2 CONTROLLABLE CATEGORIES
Controllable
Category
Item Applicable PMBOK Knowledge
Area(s)
1. Deliverables 1.1 For maintain safety at night,
all safety equipment must be
installed at construction site
Head: Scope Management
Sub head: define scope
1.2 The contractual schedule
need to be submitted to
head engineer, client
Head: Time Management
Sub head: develop schedule
1.3 All the site establishments
need to be built using good
quality of material
Head: Integration Management
Sub head: direct and manage
project work
2. Configuration 2.1 The quality standard of
concrete need to meet TMR
specifications and
amendment is required
Head: Quality Management
Sub head: Quality Control
2.2 The high safety standards
need to be maintained and
so the slight in situ changes
are required
Head: Integration Management
Sub head: Integrated Change
Control
2.3 To enable more safety at
site, one road is required to
divert from its path.
Head: Integration Management
Sub head: Integrated Change
Control
ENTER YOUR NAME WITH STUDENT ID PAGE 1
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
PROJECT CONTROLS REPORT
KERB WORKS (BW229/15) PROJECT
3. Status
accounts
(Washington
State
Department
of
Transportatio
n, 2008)
3.1 Cost performance index and
variance (CPI & CV)
Head: Cost Management
Sub head: Control Cost
3.2 Schedule performance index
and variance (SPI & SV)
Head: Time Management
Sub head: Control Schedule
3.3 Quality issues need to be
presented to stakeholders
Head: Quality Management
Sub head: Quality Assurance and
Control
4. Logs
(Leadership
Formation,
2017)
4.1 Daily change in weather
condition is required to be
documented for further use
to calculate the reasons for
delay in schedule completion
date
Head: integration Management
Sub head: Direct and Manage
Execution
4.2 As a part of documentation,
photographs are required to
be kept
Head: integration Management
Sub head: Direct and Manage
Execution
4.3 Regular basis site need to be
visited to cross verify the
progress claimed
Head: integration Management
Sub head: Direct and Manage
Execution
5. Issues 5.1 All the underground systems
need to be shifted before
start of earth filling work
Head: Integration Management
Sub head: Monitor and control
work
5.2 Local purchase items for the
construction is not available
Head: Procurement
Management
Sub head: Conduct and Control
Procurement
5.3 More floodlights need to be
installed to resolve the
visibility issue at night
Head: Risk Management
Sub head: Monitor and Control
risks
3 CONFIGURATION PROCEDURAL OUTPUTS
Configuration Item Procedural Outputs
Configuration
Control Level
Coding
System
Used
Baseline
Used in
this
project
Status
Accounting
Periodicity
Verification
and Audit
Review
Period and
Level of
Detail
1.3 All the site
establishments
need to be
Control of
Qulaity
Execution Yes Weekly Regular
review
ENTER YOUR NAME WITH STUDENT ID PAGE 2
Document Page
PROJECT CONTROLS REPORT
KERB WORKS (BW229/15) PROJECT
built using
good quality of
material
2.3 To enable
more safety at
site, one road
is required to
divert from its
path.
Time
Cost &
Scope
Safety Yes. Weekly Regular
review
3.1 Cost
performance
index and
variance (CPI
& CV)
Cost Budget Yes. Weekly Regular
review
5.3 More
floodlights
need to be
installed to
resolve the
visibility issue
at night
Scope Public
Safety
Yes. Weekly Regular
review
4 EVENT DRIVEN CONTROLS
Controllable
Category
Item &
Explanation
PMBOK Knowledge Area
Input
Tool &
Technique Output
1. Deliverable 1.1 To
maintain
safety at
night, all
safety
equipment
must be
installed at
construction
site
Different
metrics of
Quality
Variance
analysis
Raise request for
accepting the
Changes
To maintain proper level of safety at construction site, some changes are
required to be maintained and need scope and cost.
2. Configuration 2.3 To enable
more safety at
site, one road
is required to
divert from its
path
Validation of all
required
Deliverables
Inspection Raise request for
accepting the
Changes
To implement zero accident policy, one more road is required to be
blocked for the night service of construction and hence rerouting is
required to be done with additional time and cost.
3. Status
Accounts
3.1 Cost
performance
index and
variance (CPI
Work
Performance
Trends
Information
Analysis of
Variance
Raise request for
accepting the
Changes
ENTER YOUR NAME WITH STUDENT ID PAGE 3
Document Page
PROJECT CONTROLS REPORT
KERB WORKS (BW229/15) PROJECT
& CV) &
Update the
document
accordingly
Due to some unforseen situation of high monsoon at site, the earth has
flown away and the cash flow was blocked and so the cash crunch can
happen and it can raise to delay in work completion
5. Issues 5.1 All the
underground
systems need
to be shifted
before start of
earth filling
work
Work
Performance
Trends
Information
Analysis of
Variance
Raise request for
accepting the
Changes
&
Update the
document
accordingly
As per drawing all the underground facilities are already shifted but there
are still some facility discovered while doing deep excavation and it is
required to be rerouted first an need more time and cost.
5 TIME DRIVEN ITEMS
Controllable
Category
Item &
Explanation
PMBOK Knowledge Area
Input
Tool &
Technique Output
1. Deliverable 1.3 All the site
establishment
s need to be
built using
good quality
of material
Work
Performance
Trends
Information
Analysis of
Variance
Raise request for
accepting the
Changes
&
Update the
document
accordingly
Just after the deep excavation of the site establishment facility area was
completed to do the sub structure work, the very next day heavy rainfall
was continued for several days and the whole area was under water,
which delayed the work like anything and the whole schedule got affected
3. Status
Accounts
3.2 Schedule
performance
index and
variance (SPI
& SV)
Work
Performance
Trends
Information
&
Extra
Requirement of
Fund
Analysis of
Variance
&
Forecasting of
the schedule
Forecasting of the
budgeted cost and
schedule
&
Update the
document
accordingly
While compiling data for monthly progress reporting, the SV was observed
to be less than zero and the SPI below 1. Schedule overrun is definitely
there.
5. Issues 5.2 Local
purchase
Project
management
Change control
procedure
Update the
document
ENTER YOUR NAME WITH STUDENT ID PAGE 4
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
PROJECT CONTROLS REPORT
KERB WORKS (BW229/15) PROJECT
items for the
construction is
not available
plan developed
covering the
Procurement
procedure
accordingly
&
Raise request for
accepting the
Changes
All the required construction items necessary for the execution of kerb
works, was unavailable at local market. So need to be procured form
outside market shall attract more time and cost.
6 REFERENCES
Leadership Formation. (2017). Project Control Log. Retrieved August 25, 2017, from
http://philipdiab.com: http://philipdiab.com/templates/project-control-log/
Washington State Department of Transportation. (2008, July 1). Control Account Guidelines.
Retrieved August 25, 2017, from http://www.wsdot.wa.gov:
http://www.wsdot.wa.gov/publications/fulltext/PMRS/Guidance_Desktop_Procedures/
ControlAccountGuidelines.pdf
ENTER YOUR NAME WITH STUDENT ID PAGE 5