This report presents a comprehensive project documentation for the construction of a residential bungalow, detailing the project's overview, cost management planning, and quality management strategies. The introduction emphasizes the importance of quality and cost control for successful project completion, referencing project management methodologies like PMBOK and PRINCE2. The project overview outlines the construction of a bungalow near a riverbank, including a detailed work breakdown structure (WBS) with 20 activities, timelines, and resource allocation. The cost management section focuses on estimating timelines and costs, providing a breakdown of resources (labor, tradesmen, materials, and plants) and their associated costs. The report also includes a detailed analysis of resource usage, categorized by human and material resources, with specific hours and units allocated for each activity. The report aims to provide a clear and concise understanding of the project's planning and execution, emphasizing the importance of effective management for successful completion.

Running head: PROJECT DOCUMENTATION
Project Documentation
The Bungalow Project
Name of the Student:
Student ID:
Name of the University:
Author’s note:
Project Documentation
The Bungalow Project
Name of the Student:
Student ID:
Name of the University:
Author’s note:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1PROJECT DOCUMENTATION
Table of Contents
Introduction......................................................................................................................................2
Project Overview Statement............................................................................................................2
Cost Management Planning.............................................................................................................5
Quality Management Planning......................................................................................................11
Conclusion.....................................................................................................................................14
Bibliography..................................................................................................................................15
Page 1 of 2
Table of Contents
Introduction......................................................................................................................................2
Project Overview Statement............................................................................................................2
Cost Management Planning.............................................................................................................5
Quality Management Planning......................................................................................................11
Conclusion.....................................................................................................................................14
Bibliography..................................................................................................................................15
Page 1 of 2

2PROJECT DOCUMENTATION
Introduction
The development of the quality control and cost control is a crucial factor for the
achievement of the project and the alignment of the factors for development. The study of books
like PMBOK and PRINCE2 would allow the information development and alignment. The
success of the quality and cost control is dependent on the project management factors and
techniques. The implication of the controlling strategies would be helpful for taking care of the
smart management factors. The following assignment had been developed considering the
Bungalow Project for aligning the management of the specific and smart work development. The
implication of the works and the allowance of the technology management for the project
completion would be effectively deployed with the project completion management. The report
would include the project overview statement providing an overview of the project activities in
alignment of management of the factors for development of strategies. The cost management
planning and quality management planning has been also a part of the project report. The project
management concepts and the tools would support the completion of the report. The utilization
of the factors for the incorporation and administration would support the inclusion of the specific
work alignment.
Project Overview Statement
The Bungalow Project is the construction of a residential bungalow for the residents near
to the river bank which includes the involvement of the construction projects and the
development of the understanding for the construction project management. The completion of
the project would include the construction of the bungalow on the strip footings. The
construction of the project would be dependent on the construction of the external walls with the
internal walls using timber, brick veneer, floor using brick piers and timber joists, tiling of the
Page 1 of 2
Introduction
The development of the quality control and cost control is a crucial factor for the
achievement of the project and the alignment of the factors for development. The study of books
like PMBOK and PRINCE2 would allow the information development and alignment. The
success of the quality and cost control is dependent on the project management factors and
techniques. The implication of the controlling strategies would be helpful for taking care of the
smart management factors. The following assignment had been developed considering the
Bungalow Project for aligning the management of the specific and smart work development. The
implication of the works and the allowance of the technology management for the project
completion would be effectively deployed with the project completion management. The report
would include the project overview statement providing an overview of the project activities in
alignment of management of the factors for development of strategies. The cost management
planning and quality management planning has been also a part of the project report. The project
management concepts and the tools would support the completion of the report. The utilization
of the factors for the incorporation and administration would support the inclusion of the specific
work alignment.
Project Overview Statement
The Bungalow Project is the construction of a residential bungalow for the residents near
to the river bank which includes the involvement of the construction projects and the
development of the understanding for the construction project management. The completion of
the project would include the construction of the bungalow on the strip footings. The
construction of the project would be dependent on the construction of the external walls with the
internal walls using timber, brick veneer, floor using brick piers and timber joists, tiling of the
Page 1 of 2
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3PROJECT DOCUMENTATION
roof using timber trussed rafters, and construction of the electrics and plumbing using direct
labor. The schedule for the project is shown below,
WBS Task Name Duration Start Finish
0 The Bungalow Project 36 wks Mon 7/2/18 Fri 3/8/19
A Clear Ground 2 wks Mon 7/2/18 Fri 7/13/18
B Lay Foundations 3 wks Mon 7/16/18 Fri 8/3/18
C Build Dwarf Walls 2 wks Mon 8/6/18 Fri 8/17/18
D Oversite Concrete 1 wk Mon 8/6/18 Fri 8/10/18
E Floor Joists 2 wks Mon 8/20/18 Fri 8/31/18
F Main Walls 5 wks Mon 9/3/18 Fri 10/5/18
G Door and Windows Frames 3 wks Mon 9/3/18 Fri 9/21/18
H Ceiling Joists 2 wks Mon 10/8/18 Fri 10/19/18
J Roof Timbers 6 wks Mon 10/8/18 Fri 11/16/18
K Tiles 2 wks Mon
11/19/18 Fri 11/30/18
L Floorboards 3 wks Mon
11/19/18 Fri 12/7/18
M Ceiling Boards 2 wks Mon
12/10/18 Fri 12/21/18
N Skirting 1 wk Mon
12/10/18 Fri 12/14/18
P Glazing 2 wks Mon
12/24/18 Fri 1/4/19
Q Plastering 2 wks Mon 1/7/19 Fri 1/18/19
R Electrics 3 wks Mon 1/7/19 Fri 1/25/19
S Plumbing and heating 4 wks Mon 1/7/19 Fri 2/1/19
T Painting 5 wks Mon 2/4/19 Fri 3/8/19
The project works would include the involvement of the construction project
management along with the documentation and the formation of the operations. The complete
project would involve 20 activities to be followed namely build dwarf walls, ceiling boards,
ceiling joists, roof timbers, clear ground, door and windows frames, electrics, floor joists,
floorboards, glazing, lay foundations, main walls, oversite concrete, painting, plastering,
plumbing and heating, skirting, and tiles. The completion of the works would require individual
work identification and the formation of the smart analysis of the activities. The clearing of the
ground would be effectively deployed for taking care of the site and removal of the wastage. The
Page 1 of 2
roof using timber trussed rafters, and construction of the electrics and plumbing using direct
labor. The schedule for the project is shown below,
WBS Task Name Duration Start Finish
0 The Bungalow Project 36 wks Mon 7/2/18 Fri 3/8/19
A Clear Ground 2 wks Mon 7/2/18 Fri 7/13/18
B Lay Foundations 3 wks Mon 7/16/18 Fri 8/3/18
C Build Dwarf Walls 2 wks Mon 8/6/18 Fri 8/17/18
D Oversite Concrete 1 wk Mon 8/6/18 Fri 8/10/18
E Floor Joists 2 wks Mon 8/20/18 Fri 8/31/18
F Main Walls 5 wks Mon 9/3/18 Fri 10/5/18
G Door and Windows Frames 3 wks Mon 9/3/18 Fri 9/21/18
H Ceiling Joists 2 wks Mon 10/8/18 Fri 10/19/18
J Roof Timbers 6 wks Mon 10/8/18 Fri 11/16/18
K Tiles 2 wks Mon
11/19/18 Fri 11/30/18
L Floorboards 3 wks Mon
11/19/18 Fri 12/7/18
M Ceiling Boards 2 wks Mon
12/10/18 Fri 12/21/18
N Skirting 1 wk Mon
12/10/18 Fri 12/14/18
P Glazing 2 wks Mon
12/24/18 Fri 1/4/19
Q Plastering 2 wks Mon 1/7/19 Fri 1/18/19
R Electrics 3 wks Mon 1/7/19 Fri 1/25/19
S Plumbing and heating 4 wks Mon 1/7/19 Fri 2/1/19
T Painting 5 wks Mon 2/4/19 Fri 3/8/19
The project works would include the involvement of the construction project
management along with the documentation and the formation of the operations. The complete
project would involve 20 activities to be followed namely build dwarf walls, ceiling boards,
ceiling joists, roof timbers, clear ground, door and windows frames, electrics, floor joists,
floorboards, glazing, lay foundations, main walls, oversite concrete, painting, plastering,
plumbing and heating, skirting, and tiles. The completion of the works would require individual
work identification and the formation of the smart analysis of the activities. The clearing of the
ground would be effectively deployed for taking care of the site and removal of the wastage. The
Page 1 of 2
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4PROJECT DOCUMENTATION
perimeter would be developed around the construction works where apart from people working
on projects should not be allowed. It would help in mitigating the possibility of the accident at
the construction site.
The laying of foundation is the first construction work executed at the project site. The
digging of holes and eradicating the pillars would be primary job for the project team members.
The workers would form the building structure with the iron pillars and the dug foundations
would be solidified. The dwarf walls would be developed for boundary of the Bungalow. The
Bungalow would be constructed with the alignment of the works and the formation of the smart
work management. The concrete walls would be effectively constructed with the help of the
contractor and the construction materials and equipment. The oversite concrete would be helpful
for developing concrete base and mixing it for constructing the structure. The development of the
concrete wall would allow the formation of the structure and covering the pillars with solid
cement. The floor joists would be constructed with the help of equipment.
The flooring of the Bungalow would be done for aligning the work later. The floor would
be constructed and aligned with the construction of the main walls. The main walls would be
constructed using the construction raw materials developed at oversite concrete. After that the
door and windows frames would be carved out. The completed Bungalow would include doors
and windows and the construction of the frames and framework would be effectively helpful.
Later on the ceiling joists would be developed considering the implication of the roof timbers for
shed. The ceiling and floor works can be done side by side and it would help in completing the
work faster. The laying of the tiles would be done later on supporting the implication of the
cement and tiles all over the floors of the Bungalow. Apart from floors, any other part of the
Bungalow requiring the laying of the tiles would be done also.
The floorboards would be effectively developed using the required wood and timber. The
construction would involve the hiring of the mason for executing the floorboard works at the
Page 1 of 2
perimeter would be developed around the construction works where apart from people working
on projects should not be allowed. It would help in mitigating the possibility of the accident at
the construction site.
The laying of foundation is the first construction work executed at the project site. The
digging of holes and eradicating the pillars would be primary job for the project team members.
The workers would form the building structure with the iron pillars and the dug foundations
would be solidified. The dwarf walls would be developed for boundary of the Bungalow. The
Bungalow would be constructed with the alignment of the works and the formation of the smart
work management. The concrete walls would be effectively constructed with the help of the
contractor and the construction materials and equipment. The oversite concrete would be helpful
for developing concrete base and mixing it for constructing the structure. The development of the
concrete wall would allow the formation of the structure and covering the pillars with solid
cement. The floor joists would be constructed with the help of equipment.
The flooring of the Bungalow would be done for aligning the work later. The floor would
be constructed and aligned with the construction of the main walls. The main walls would be
constructed using the construction raw materials developed at oversite concrete. After that the
door and windows frames would be carved out. The completed Bungalow would include doors
and windows and the construction of the frames and framework would be effectively helpful.
Later on the ceiling joists would be developed considering the implication of the roof timbers for
shed. The ceiling and floor works can be done side by side and it would help in completing the
work faster. The laying of the tiles would be done later on supporting the implication of the
cement and tiles all over the floors of the Bungalow. Apart from floors, any other part of the
Bungalow requiring the laying of the tiles would be done also.
The floorboards would be effectively developed using the required wood and timber. The
construction would involve the hiring of the mason for executing the floorboard works at the
Page 1 of 2

5PROJECT DOCUMENTATION
Bungalow. The mason would also be helpful for ceiling board activities. The ceiling joists would
be added with the boards for ensuring that the work is effectively employed. The Bungalow
construction would be aligned with the small works like skirting, glazing, plastering, electrics,
plumbing and heating, and painting. The activities would consume specific work people to be
included in the Bungalow Project like carpenter, technician, painter, and plumber.
Cost Management Planning
The cost management is a crucial factor defining the estimation of the resource usage and
identification of a specific project budget aligning the management of the successful completion
of the works. The cost management planning involves the following points,
a) Estimating timeline: The process of estimation of the timeline is very crucial as it
involves the consideration of the project effective timeline development. The project
resource would be implied cohesively for integrating the development of the work
and aligning the management of the project. The timeline for the cost formation
would be effectively implied with the listing of the works. The timeline estimation of
the cost required for the Bungalow Project would be implied with the consideration of
the improved work development. The timeline for the estimation of the work would
result in forming the analysis of the usage of the resource and the implication
management and formation of the cost entry analysis. The following is the resource
used for the Bungalow Project along with the scheduled time duration and timeline,
Resource Names Duration Start Finish
Resource A Labors[600%],
Material and Plant @2[100] 2 wks Mon 7/2/18 Fri 7/13/18
Resource A Labors[400%],
Resource B
Tradesmen[200%],
Material and Plant @3[1,200]
3 wks Mon 7/16/18 Fri 8/3/18
Page 1 of 2
Bungalow. The mason would also be helpful for ceiling board activities. The ceiling joists would
be added with the boards for ensuring that the work is effectively employed. The Bungalow
construction would be aligned with the small works like skirting, glazing, plastering, electrics,
plumbing and heating, and painting. The activities would consume specific work people to be
included in the Bungalow Project like carpenter, technician, painter, and plumber.
Cost Management Planning
The cost management is a crucial factor defining the estimation of the resource usage and
identification of a specific project budget aligning the management of the successful completion
of the works. The cost management planning involves the following points,
a) Estimating timeline: The process of estimation of the timeline is very crucial as it
involves the consideration of the project effective timeline development. The project
resource would be implied cohesively for integrating the development of the work
and aligning the management of the project. The timeline for the cost formation
would be effectively implied with the listing of the works. The timeline estimation of
the cost required for the Bungalow Project would be implied with the consideration of
the improved work development. The timeline for the estimation of the work would
result in forming the analysis of the usage of the resource and the implication
management and formation of the cost entry analysis. The following is the resource
used for the Bungalow Project along with the scheduled time duration and timeline,
Resource Names Duration Start Finish
Resource A Labors[600%],
Material and Plant @2[100] 2 wks Mon 7/2/18 Fri 7/13/18
Resource A Labors[400%],
Resource B
Tradesmen[200%],
Material and Plant @3[1,200]
3 wks Mon 7/16/18 Fri 8/3/18
Page 1 of 2
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6PROJECT DOCUMENTATION
Resource A Labors[200%],
Resource B
Tradesmen[400%],
Material and Plant @2[700]
2 wks Mon 8/6/18 Fri 8/17/18
Resource A Labors[400%],
Material and Plant @1[800] 1 wk Mon 8/6/18 Fri 8/10/18
Resource B
Tradesmen[200%],
Material and Plant @2[500]
2 wks Mon 8/20/18 Fri 8/31/18
Resource A Labors[200%],
Resource B
Tradesmen[400%],
Material and Plant @5[1,400]
5 wks Mon 9/3/18 Fri 10/5/18
Resource B
Tradesmen[200%],
Material and Plant @3[600]
3 wks Mon 9/3/18 Fri 9/21/18
Resource B
Tradesmen[200%],
Material and Plant @2[600]
2 wks Mon 10/8/18 Fri 10/19/18
Resource B
Tradesmen[200%],
Material and Plant @6[600]
6 wks Mon 10/8/18 Fri 11/16/18
Resource A Labors[200%],
Resource B
Tradesmen[300%],
Material and Plant @2[1,200]
2 wks Mon
11/19/18 Fri 11/30/18
Resource B
Tradesmen[200%],
Material and Plant @3[700]
3 wks Mon
11/19/18 Fri 12/7/18
Resource B
Tradesmen[200%],
Material and Plant @2[200]
2 wks Mon
12/10/18 Fri 12/21/18
Resource B
Tradesmen[200%],
Material and Plant @1[200]
1 wk Mon
12/10/18 Fri 12/14/18
Resource B
Tradesmen[200%],
Material and Plant @2[400]
2 wks Mon
12/24/18 Fri 1/4/19
Resource A Labors,
Resource B
Tradesmen[300%],
Material and Plant @2[300]
2 wks Mon 1/7/19 Fri 1/18/19
Resource B
Tradesmen[200%],
Material and Plant @3[600]
3 wks Mon 1/7/19 Fri 1/25/19
Resource A Labors,
Resource B
4 wks Mon 1/7/19 Fri 2/1/19
Page 1 of 2
Resource A Labors[200%],
Resource B
Tradesmen[400%],
Material and Plant @2[700]
2 wks Mon 8/6/18 Fri 8/17/18
Resource A Labors[400%],
Material and Plant @1[800] 1 wk Mon 8/6/18 Fri 8/10/18
Resource B
Tradesmen[200%],
Material and Plant @2[500]
2 wks Mon 8/20/18 Fri 8/31/18
Resource A Labors[200%],
Resource B
Tradesmen[400%],
Material and Plant @5[1,400]
5 wks Mon 9/3/18 Fri 10/5/18
Resource B
Tradesmen[200%],
Material and Plant @3[600]
3 wks Mon 9/3/18 Fri 9/21/18
Resource B
Tradesmen[200%],
Material and Plant @2[600]
2 wks Mon 10/8/18 Fri 10/19/18
Resource B
Tradesmen[200%],
Material and Plant @6[600]
6 wks Mon 10/8/18 Fri 11/16/18
Resource A Labors[200%],
Resource B
Tradesmen[300%],
Material and Plant @2[1,200]
2 wks Mon
11/19/18 Fri 11/30/18
Resource B
Tradesmen[200%],
Material and Plant @3[700]
3 wks Mon
11/19/18 Fri 12/7/18
Resource B
Tradesmen[200%],
Material and Plant @2[200]
2 wks Mon
12/10/18 Fri 12/21/18
Resource B
Tradesmen[200%],
Material and Plant @1[200]
1 wk Mon
12/10/18 Fri 12/14/18
Resource B
Tradesmen[200%],
Material and Plant @2[400]
2 wks Mon
12/24/18 Fri 1/4/19
Resource A Labors,
Resource B
Tradesmen[300%],
Material and Plant @2[300]
2 wks Mon 1/7/19 Fri 1/18/19
Resource B
Tradesmen[200%],
Material and Plant @3[600]
3 wks Mon 1/7/19 Fri 1/25/19
Resource A Labors,
Resource B
4 wks Mon 1/7/19 Fri 2/1/19
Page 1 of 2
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT DOCUMENTATION
Tradesmen[300%],
Material and Plant @4[900]
Resource B
Tradesmen[400%],
Material and Plant @3[300]
5 wks Mon 2/4/19 Fri 3/8/19
The project has considered the usage of the resources for enabling the work completion
management. The analysis from the above table is clear that the required resources for the project
include Resource A Labors and Resource B Tradesmen. The two classification of the human
resource type have individually more than 5 for labors and 4 tradesmen. They have divided the
work of the project according to the skills and competencies. The completion of the work would
be effectively aligned with the utilization of the material as well as material resources. The
materials and the plant used in the construction of the Bungalow Project would consume six
classification of them. These classification have been done using their specific rates like Material
& plan @1, Material & plan @2, Material & plan @3, Material & plan @4, and Material & plan
@5. These were the resources exhausted in the project for successful building of Bungalow at
the foot strip.
b) Estimation of the costs: The estimation of the costs has been done for analyzing the
formation of the successful and effective work system calculation. The cost
estimation has been done for enabling the analysis of the smart work development
and the estimation of the effective work alignment. The cost estimation would be
done for making sure that the resources have been utilized successfully. The
estimated project cost and resource usages is given below,
Resource Name Work
Resource A Labors 1,720 hrs
Clear Ground 480 hrs
Lay Foundations 120 hrs
Build Dwarf Walls 160 hrs
Oversite Concrete 160 hrs
Main Walls 400 hrs
Page 1 of 2
Tradesmen[300%],
Material and Plant @4[900]
Resource B
Tradesmen[400%],
Material and Plant @3[300]
5 wks Mon 2/4/19 Fri 3/8/19
The project has considered the usage of the resources for enabling the work completion
management. The analysis from the above table is clear that the required resources for the project
include Resource A Labors and Resource B Tradesmen. The two classification of the human
resource type have individually more than 5 for labors and 4 tradesmen. They have divided the
work of the project according to the skills and competencies. The completion of the work would
be effectively aligned with the utilization of the material as well as material resources. The
materials and the plant used in the construction of the Bungalow Project would consume six
classification of them. These classification have been done using their specific rates like Material
& plan @1, Material & plan @2, Material & plan @3, Material & plan @4, and Material & plan
@5. These were the resources exhausted in the project for successful building of Bungalow at
the foot strip.
b) Estimation of the costs: The estimation of the costs has been done for analyzing the
formation of the successful and effective work system calculation. The cost
estimation has been done for enabling the analysis of the smart work development
and the estimation of the effective work alignment. The cost estimation would be
done for making sure that the resources have been utilized successfully. The
estimated project cost and resource usages is given below,
Resource Name Work
Resource A Labors 1,720 hrs
Clear Ground 480 hrs
Lay Foundations 120 hrs
Build Dwarf Walls 160 hrs
Oversite Concrete 160 hrs
Main Walls 400 hrs
Page 1 of 2

8PROJECT DOCUMENTATION
Tiles 160 hrs
Plastering 80 hrs
Plumbing and heating 160 hrs
Resource B Tradesmen 3,560 hrs
Lay Foundations 240 hrs
Build Dwarf Walls 80 hrs
Floor Joists 160 hrs
Main Walls 200 hrs
Door and Windows
Frames 240 hrs
Ceiling Joists 160 hrs
Roof Timbers 480 hrs
Tiles 80 hrs
Floorboards 240 hrs
Ceiling Boards 160 hrs
Skirting 80 hrs
Glazing 160 hrs
Plastering 80 hrs
Electrics 240 hrs
Plumbing and heating 160 hrs
Painting 800 hrs
Material and Plant @1 1,000
Oversite Concrete 800
Skirting 200
Material and Plant @2 4,000
Clear Ground 100
Build Dwarf Walls 700
Floor Joists 500
Ceiling Joists 600
Tiles 1,200
Ceiling Boards 200
Glazing 400
Plastering 300
Material and Plant @3 3,400
Lay Foundations 1,200
Door and Windows
Frames 600
Floorboards 700
Electrics 600
Painting 300
Material and Plant @4 900
Plumbing and heating 900
Material and Plant @5 1,400
Page 1 of 2
Tiles 160 hrs
Plastering 80 hrs
Plumbing and heating 160 hrs
Resource B Tradesmen 3,560 hrs
Lay Foundations 240 hrs
Build Dwarf Walls 80 hrs
Floor Joists 160 hrs
Main Walls 200 hrs
Door and Windows
Frames 240 hrs
Ceiling Joists 160 hrs
Roof Timbers 480 hrs
Tiles 80 hrs
Floorboards 240 hrs
Ceiling Boards 160 hrs
Skirting 80 hrs
Glazing 160 hrs
Plastering 80 hrs
Electrics 240 hrs
Plumbing and heating 160 hrs
Painting 800 hrs
Material and Plant @1 1,000
Oversite Concrete 800
Skirting 200
Material and Plant @2 4,000
Clear Ground 100
Build Dwarf Walls 700
Floor Joists 500
Ceiling Joists 600
Tiles 1,200
Ceiling Boards 200
Glazing 400
Plastering 300
Material and Plant @3 3,400
Lay Foundations 1,200
Door and Windows
Frames 600
Floorboards 700
Electrics 600
Painting 300
Material and Plant @4 900
Plumbing and heating 900
Material and Plant @5 1,400
Page 1 of 2
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9PROJECT DOCUMENTATION
Main Walls 1,400
Material and Plant @6 600
Roof Timbers 600
The table had made the clear indication of the usage of the resources (both human and
material) for the Bungalow Project. The usage of the resource have two classification namely
hours for the human resources and the units for the material resources. The standard rates of the
human resources is in USD/hrs and that of the materials are USD/unit. The resource A labors and
resource B tradesmen were the two human resources used in the project. the material resources
of the project include material & plan @1, material & plan @2, material & plan @3, material &
plan @4, and material & plan @5. The resource A labors would be used in activities like build
dwarf walls, clear ground, lay foundations, main walls, plastering, oversite concrete, and
plumbing and heating. The resource B tradesmen would be used in the activities of build dwarf
walls, ceiling boards, ceiling joists, door and windows frames, electrics, floor joists, floorboards,
glazing, lay foundations, main walls, painting, plastering, plumbing and heating, roof timbers,
skirting, and tiles, The material resources used for the project are material and plant @1 (used for
oversite concrete and skirting), material and plant @2 (used for build dwarf walls, plastering,
ceiling boards, ceiling joists, glazing, floor joists, clear ground, and tiles), material and plant @3
(used for door and windows frames, lay foundations, painting, electrics, and floorboards),
material and plant @4 (used for plumbing and heating), material and plant @5 (used for main
walls), and material and plant @6 (used for roof timbers).
c) Determining budget: The determination of the project budget would be done enabling
the analysis of the effective budget analysis and development. The project budget has
been developed using the formation of the effective and aligned management works.
The budget estimation is done considering the analysis of the factors for the
formation of the work development. The resources would be calculated and
Page 1 of 2
Main Walls 1,400
Material and Plant @6 600
Roof Timbers 600
The table had made the clear indication of the usage of the resources (both human and
material) for the Bungalow Project. The usage of the resource have two classification namely
hours for the human resources and the units for the material resources. The standard rates of the
human resources is in USD/hrs and that of the materials are USD/unit. The resource A labors and
resource B tradesmen were the two human resources used in the project. the material resources
of the project include material & plan @1, material & plan @2, material & plan @3, material &
plan @4, and material & plan @5. The resource A labors would be used in activities like build
dwarf walls, clear ground, lay foundations, main walls, plastering, oversite concrete, and
plumbing and heating. The resource B tradesmen would be used in the activities of build dwarf
walls, ceiling boards, ceiling joists, door and windows frames, electrics, floor joists, floorboards,
glazing, lay foundations, main walls, painting, plastering, plumbing and heating, roof timbers,
skirting, and tiles, The material resources used for the project are material and plant @1 (used for
oversite concrete and skirting), material and plant @2 (used for build dwarf walls, plastering,
ceiling boards, ceiling joists, glazing, floor joists, clear ground, and tiles), material and plant @3
(used for door and windows frames, lay foundations, painting, electrics, and floorboards),
material and plant @4 (used for plumbing and heating), material and plant @5 (used for main
walls), and material and plant @6 (used for roof timbers).
c) Determining budget: The determination of the project budget would be done enabling
the analysis of the effective budget analysis and development. The project budget has
been developed using the formation of the effective and aligned management works.
The budget estimation is done considering the analysis of the factors for the
formation of the work development. The resources would be calculated and
Page 1 of 2
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10PROJECT DOCUMENTATION
individual cost expectancy would be summed for developing the final budget. The
following is the estimated budget for the Bungalow Project.
Resource Name Work Standard Rate Cost
Resource A Labors 1,720 hrs $30.00/hr $51,600.00
Resource B Tradesmen 3,560
hrs $45.00/hr $160,200.00
Material and Plant @1 1,000 $1.00 $1,000.00
Material and Plant @2 4,000 $2.00 $8,000.00
Material and Plant @3 3,400 $3.00 $10,200.00
Material and Plant @4 900 $4.00 $3,600.00
Material and Plant @5 1,400 $5.00 $7,000.00
Material and Plant @6 600 $6.00 $3,600.00
Total Budget $245,000.00
d) Controlling cost expenditure: The cost expenditure would be done considering the
alignment of the usage of the resources. The expenses of the project would be divided
into quarters or monthly basis for ensuring that the amount should not exceed the
estimated budget. The project cost controlling would be done using the timeline (time
phased budget) as shown below,
July 2018 August
2018 September
2018 October
2018 November
2018 December
2018 January
2019 February
2019 March
2019
$0.00
$5,000.00
$10,000.00
$15,000.00
$20,000.00
$25,000.00
$30,000.00
$35,000.00
$40,000.00
$29,720.00
$26,480.00
$36,800.00
$27,320.00 $29,480.00
$20,500.00
$37,580.00
$28,464.00
$8,856.00
Cost
According to the time phase diagram, it is clear that the resource usage have been
uniformly distributed on monthly basis. The overall budget for the project was $245,000.00 and
Page 1 of 2
individual cost expectancy would be summed for developing the final budget. The
following is the estimated budget for the Bungalow Project.
Resource Name Work Standard Rate Cost
Resource A Labors 1,720 hrs $30.00/hr $51,600.00
Resource B Tradesmen 3,560
hrs $45.00/hr $160,200.00
Material and Plant @1 1,000 $1.00 $1,000.00
Material and Plant @2 4,000 $2.00 $8,000.00
Material and Plant @3 3,400 $3.00 $10,200.00
Material and Plant @4 900 $4.00 $3,600.00
Material and Plant @5 1,400 $5.00 $7,000.00
Material and Plant @6 600 $6.00 $3,600.00
Total Budget $245,000.00
d) Controlling cost expenditure: The cost expenditure would be done considering the
alignment of the usage of the resources. The expenses of the project would be divided
into quarters or monthly basis for ensuring that the amount should not exceed the
estimated budget. The project cost controlling would be done using the timeline (time
phased budget) as shown below,
July 2018 August
2018 September
2018 October
2018 November
2018 December
2018 January
2019 February
2019 March
2019
$0.00
$5,000.00
$10,000.00
$15,000.00
$20,000.00
$25,000.00
$30,000.00
$35,000.00
$40,000.00
$29,720.00
$26,480.00
$36,800.00
$27,320.00 $29,480.00
$20,500.00
$37,580.00
$28,464.00
$8,856.00
Cost
According to the time phase diagram, it is clear that the resource usage have been
uniformly distributed on monthly basis. The overall budget for the project was $245,000.00 and
Page 1 of 2

11PROJECT DOCUMENTATION
it was distributed 9 months from July 2018 to March 2019. The work distribution would be
supported by the resource implication and alignment of the works specifically for the improved
work alignment. The expenses of the project would be aligned successfully with the formation of
the work dependent on the time scale. The time division would be effectively implied with the
analysis of the work and formation of the specific alignment of the works. The expenses of the
project has the following timeline,
Month Expense
July 2018 $ 29,720.00
August 2018 $ 26,480.00
September 2018 $ 36,800.00
October 2018 $ 27,320.00
November 2018 $ 29,480.00
December 2018 $ 20,500.00
January 2019 $ 37,580.00
February 2019 $ 28,464.00
March 2019 $ 8,856.00
Quality Management Planning
The quality management planning is helpful for aligning the implication of the works and
the simplification of the smart work development. The quality management planning would be
supported by the utilization of the improved analysis and development. The various tools like
7QC, Pareto chart, and Six Sigma would be helpful for analyzing and evaluating the work. In the
next section, the analysis of the quality planning approach, quality control approach, quality
assurance approach, quality improvement approach, and quality roles and responsibilities. The
following is the quality management plan for the Bungalow Project that can be helpful for
developing effective strategies for the project execution,
Project Title: The Bungalow Project Date Prepared: 2nd December, 2018
Quality Roles and Responsibilities
Role Responsibilities
Page 1 of 2
it was distributed 9 months from July 2018 to March 2019. The work distribution would be
supported by the resource implication and alignment of the works specifically for the improved
work alignment. The expenses of the project would be aligned successfully with the formation of
the work dependent on the time scale. The time division would be effectively implied with the
analysis of the work and formation of the specific alignment of the works. The expenses of the
project has the following timeline,
Month Expense
July 2018 $ 29,720.00
August 2018 $ 26,480.00
September 2018 $ 36,800.00
October 2018 $ 27,320.00
November 2018 $ 29,480.00
December 2018 $ 20,500.00
January 2019 $ 37,580.00
February 2019 $ 28,464.00
March 2019 $ 8,856.00
Quality Management Planning
The quality management planning is helpful for aligning the implication of the works and
the simplification of the smart work development. The quality management planning would be
supported by the utilization of the improved analysis and development. The various tools like
7QC, Pareto chart, and Six Sigma would be helpful for analyzing and evaluating the work. In the
next section, the analysis of the quality planning approach, quality control approach, quality
assurance approach, quality improvement approach, and quality roles and responsibilities. The
following is the quality management plan for the Bungalow Project that can be helpful for
developing effective strategies for the project execution,
Project Title: The Bungalow Project Date Prepared: 2nd December, 2018
Quality Roles and Responsibilities
Role Responsibilities
Page 1 of 2
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 18
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.