This project report details the importance of developing a proper project initiation, planning, and execution plan, using a house-shifting project as a case study for Jeff and Kelly. The report outlines the project's purpose, status, completion slips, and delays. It emphasizes the need for project schedule changes, including Gantt charts, and addresses implications of these changes. The project phases include initiation, planning, preparation, implementation, and closure, highlighting activities like time and budget estimation, packing, transportation, and utility management. The report also incorporates a personal reflection on the process, emphasizing the significance of the triple constraints (time, budget, and scope) and concludes with the key takeaways for successful project completion within the estimated budget and time. The report includes updated milestones, task lists, and a revised Gantt chart to visualize the project timeline and dependencies.

Running head: PROJECT INITIATION PLANNING AND EXECUTION
Project Initiation, Planning and Execution: Shifting Project
Name of the student:
Name of the university:
Project Initiation, Planning and Execution: Shifting Project
Name of the student:
Name of the university:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

1PROJECT INITIATION PLANNING AND EXECUTION
Table of Contents
1. Introduction outlining the project purpose..................................................................................2
2. The project status detailing completion slips and delays.............................................................2
2.1 Shifting initiation...................................................................................................................3
2.2 Planning for shifting and packing..........................................................................................3
2.3 Project preparation.................................................................................................................3
2.4 Implementation of shifting plan.............................................................................................4
2.5 Project closure.......................................................................................................................4
3. Implication of the project changes...............................................................................................4
4. Changes incorporate to the project schedule...............................................................................4
4.1 Gantt chart.............................................................................................................................5
5. Personal reflection on the process...............................................................................................8
Conclusion.......................................................................................................................................8
References........................................................................................................................................9
Appendices....................................................................................................................................11
Appendix 1.................................................................................................................................11
Appendix 2.................................................................................................................................11
Appendix 3.................................................................................................................................13
Table of Contents
1. Introduction outlining the project purpose..................................................................................2
2. The project status detailing completion slips and delays.............................................................2
2.1 Shifting initiation...................................................................................................................3
2.2 Planning for shifting and packing..........................................................................................3
2.3 Project preparation.................................................................................................................3
2.4 Implementation of shifting plan.............................................................................................4
2.5 Project closure.......................................................................................................................4
3. Implication of the project changes...............................................................................................4
4. Changes incorporate to the project schedule...............................................................................4
4.1 Gantt chart.............................................................................................................................5
5. Personal reflection on the process...............................................................................................8
Conclusion.......................................................................................................................................8
References........................................................................................................................................9
Appendices....................................................................................................................................11
Appendix 1.................................................................................................................................11
Appendix 2.................................................................................................................................11
Appendix 3.................................................................................................................................13

2PROJECT INITIATION PLANNING AND EXECUTION
1. Introduction outlining the project purpose
This report depicts the importance of developing proper project initiation, planning and
execution plan so that any project could be implemented within the estimated budget and cost as
well. The purpose of the report is to develop the project initiation, planning and execution
details. However, the main purpose is to develop a proper project initiation, planning and
execution plan for Jeff and Kelly so that could implement their shifting plan successfully within
estimated time phase. The date of Jeff’s joining was decided to be 5th February thus they have to
shift to their new flat before 5th February. They have decided to complete their entire shifting
within 28th January.
In order to accomplish the shifting project the project head should divide the activities
according to the project requirement. The phases those are needed to be maintained by the
project manager include project initiation, planning and execution. In the initial phase Jeff and
Kelly have decided certain activities, however in order to accomplish the entire shifting it is
necessary to modify some of the activities. The need for project schedule changes and the
updated or revised milestone are also elaborated in this report.
2. The project status detailing completion slips and delays
From the project background the details of dates and time span, needed to commence and
complete the entire shifting project, are estimated easily by the project head. With the help of the
project schedule the project manager will be able to complete the shifting within estimated time
and cost. Jeff has to report to the new job designation on 5th February,2018 and thus they have to
1. Introduction outlining the project purpose
This report depicts the importance of developing proper project initiation, planning and
execution plan so that any project could be implemented within the estimated budget and cost as
well. The purpose of the report is to develop the project initiation, planning and execution
details. However, the main purpose is to develop a proper project initiation, planning and
execution plan for Jeff and Kelly so that could implement their shifting plan successfully within
estimated time phase. The date of Jeff’s joining was decided to be 5th February thus they have to
shift to their new flat before 5th February. They have decided to complete their entire shifting
within 28th January.
In order to accomplish the shifting project the project head should divide the activities
according to the project requirement. The phases those are needed to be maintained by the
project manager include project initiation, planning and execution. In the initial phase Jeff and
Kelly have decided certain activities, however in order to accomplish the entire shifting it is
necessary to modify some of the activities. The need for project schedule changes and the
updated or revised milestone are also elaborated in this report.
2. The project status detailing completion slips and delays
From the project background the details of dates and time span, needed to commence and
complete the entire shifting project, are estimated easily by the project head. With the help of the
project schedule the project manager will be able to complete the shifting within estimated time
and cost. Jeff has to report to the new job designation on 5th February,2018 and thus they have to

3PROJECT INITIATION PLANNING AND EXECUTION
complete the entire shifting before 27th January though they have time for shifting up to 4th
February, 2018. They have to vacate their existing house within 20th January and thus Jeff and
Kelly have to stay in a hotel room for the rest of the days up to 5th February, 2018 as they do not
have any relative in Sunshine Coast. For this particular project the phases those have been
considered include
2.1 Shifting initiation
In the project shifting initiation phase, Jeff and Kelly are needed to consider all the
process and procedures accurately. Based on the changes project activity dates and time span are
needed to be measured by the project manager so that the project could be completed within the
estimated budget and time as well. They have to shift to Perth with two children and their dog.
They have to talk to the transport company (both the movers and packers) so that they could
easily transfer their vehicles to the new place. They have hired the transportation company to
move their vehicles according to the requirement. The transportation company is responsible to
move two of their cars to the new place with proper security.
2.2 Planning for shifting and packing
In this particular phase the project head is needed to plan for the relevant shifting and
packing processes. In order to accomplish the entire shifting proper time schedule and budget is
needed to be estimated by the project head. For shifting the cars and large furniture securely
without any damage proper packing is also needed to be done by the project manager.
2.3 Project preparation
The considered background scenario of the project is about the room shifting of Kelly
and Jeff with their two children and dog from sunshine coast to Perth. Mainly the shifting is
complete the entire shifting before 27th January though they have time for shifting up to 4th
February, 2018. They have to vacate their existing house within 20th January and thus Jeff and
Kelly have to stay in a hotel room for the rest of the days up to 5th February, 2018 as they do not
have any relative in Sunshine Coast. For this particular project the phases those have been
considered include
2.1 Shifting initiation
In the project shifting initiation phase, Jeff and Kelly are needed to consider all the
process and procedures accurately. Based on the changes project activity dates and time span are
needed to be measured by the project manager so that the project could be completed within the
estimated budget and time as well. They have to shift to Perth with two children and their dog.
They have to talk to the transport company (both the movers and packers) so that they could
easily transfer their vehicles to the new place. They have hired the transportation company to
move their vehicles according to the requirement. The transportation company is responsible to
move two of their cars to the new place with proper security.
2.2 Planning for shifting and packing
In this particular phase the project head is needed to plan for the relevant shifting and
packing processes. In order to accomplish the entire shifting proper time schedule and budget is
needed to be estimated by the project head. For shifting the cars and large furniture securely
without any damage proper packing is also needed to be done by the project manager.
2.3 Project preparation
The considered background scenario of the project is about the room shifting of Kelly
and Jeff with their two children and dog from sunshine coast to Perth. Mainly the shifting is
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

4PROJECT INITIATION PLANNING AND EXECUTION
required to be done by Jeff due to the promotion as a marketing director interstate. In this phase,
proper budget and time schedule are also required to be estimated by the Kelly and Jeff.
2.4 Implementation of shifting plan
In order to implement the shifting plan Jeff and Kelly are needed to consider all the
necessary activities. Even the already planned activities should also be modified according to the
project needs.
2.5 Project closure
In the project closure phase, Jeff and Kelly are needed to understand each of the activities
associated to the project. It would help them to enhance the safety, functionality and economy
altogether.
3. Implication of the project changes
Before implementation of house shifting project proper packers and movers are needed to
be hired by Kelly and Jeff. Among these different activities, some activities are modified in the
current room shifting project. The project activities are implemented for the house shifting
project so that they could obtain the followings:
 To reduce the rate of failure
 To eliminate confusion
 To make the changes faster
 To implement the changes accordingly
required to be done by Jeff due to the promotion as a marketing director interstate. In this phase,
proper budget and time schedule are also required to be estimated by the Kelly and Jeff.
2.4 Implementation of shifting plan
In order to implement the shifting plan Jeff and Kelly are needed to consider all the
necessary activities. Even the already planned activities should also be modified according to the
project needs.
2.5 Project closure
In the project closure phase, Jeff and Kelly are needed to understand each of the activities
associated to the project. It would help them to enhance the safety, functionality and economy
altogether.
3. Implication of the project changes
Before implementation of house shifting project proper packers and movers are needed to
be hired by Kelly and Jeff. Among these different activities, some activities are modified in the
current room shifting project. The project activities are implemented for the house shifting
project so that they could obtain the followings:
 To reduce the rate of failure
 To eliminate confusion
 To make the changes faster
 To implement the changes accordingly

5PROJECT INITIATION PLANNING AND EXECUTION
4. Changes incorporate to the project schedule
In order to complete the project implication of different changes are needed to be
implemented by Kelly and Jeff. It is their responsibility to accomplish the task within estimated
time and budget as well. The modified activity list and responsible person are as follows:
4.1 Gantt chart
WBS Task Name Duration Start Finish Predecessors
Resource
Names
1 Project initiation 28 days
Mon
2/12/18
Wed
3/21/18
1.1
Estimation of time
for house shifting
8 days
Mon
2/12/18
Wed
2/21/18
Jeff
1.2 Budget estimation 4 days
Thu
2/22/18
Tue
2/27/18
2 Kelly
1.3 Project planning 6 days
Wed
2/28/18
Wed 3/7/18 3
both Kelly and
Jeff
1.4
List of items to be
shifted
3 days Thu 3/8/18
Mon
3/12/18
4 Jeff
4. Changes incorporate to the project schedule
In order to complete the project implication of different changes are needed to be
implemented by Kelly and Jeff. It is their responsibility to accomplish the task within estimated
time and budget as well. The modified activity list and responsible person are as follows:
4.1 Gantt chart
WBS Task Name Duration Start Finish Predecessors
Resource
Names
1 Project initiation 28 days
Mon
2/12/18
Wed
3/21/18
1.1
Estimation of time
for house shifting
8 days
Mon
2/12/18
Wed
2/21/18
Jeff
1.2 Budget estimation 4 days
Thu
2/22/18
Tue
2/27/18
2 Kelly
1.3 Project planning 6 days
Wed
2/28/18
Wed 3/7/18 3
both Kelly and
Jeff
1.4
List of items to be
shifted
3 days Thu 3/8/18
Mon
3/12/18
4 Jeff

6PROJECT INITIATION PLANNING AND EXECUTION
1.5
Hiring
transportation
company
7 days
Tue
3/13/18
Wed
3/21/18
5 Jeff
2
Planning for
packing furniture
9 days
Tue
3/13/18
Fri 3/23/18
2.1
Planning for
packing cars
2 days
Tue
3/13/18
Wed
3/14/18
5
both Kelly and
Jeff
2.2 Hotel booking 4 days
Thu
3/15/18
Tue
3/20/18
8
both Kelly and
Jeff
2.3
Elimination of
unwanted stuffs
2 days
Wed
3/21/18
Thu
3/22/18
9 Kelly
2.4
Payment approach
development
3 days
Wed
3/21/18
Fri 3/23/18 9
both Kelly and
Jeff
3 Project preparation 19 days Fri 3/23/18
Wed
4/18/18
3.1
Labeling the
important item to
avoid loss and
damage
4 days Fri 3/23/18
Wed
3/28/18
10 Jeff
3.2 Application drafting 5 days Thu Wed 4/4/18 13 Jeff
1.5
Hiring
transportation
company
7 days
Tue
3/13/18
Wed
3/21/18
5 Jeff
2
Planning for
packing furniture
9 days
Tue
3/13/18
Fri 3/23/18
2.1
Planning for
packing cars
2 days
Tue
3/13/18
Wed
3/14/18
5
both Kelly and
Jeff
2.2 Hotel booking 4 days
Thu
3/15/18
Tue
3/20/18
8
both Kelly and
Jeff
2.3
Elimination of
unwanted stuffs
2 days
Wed
3/21/18
Thu
3/22/18
9 Kelly
2.4
Payment approach
development
3 days
Wed
3/21/18
Fri 3/23/18 9
both Kelly and
Jeff
3 Project preparation 19 days Fri 3/23/18
Wed
4/18/18
3.1
Labeling the
important item to
avoid loss and
damage
4 days Fri 3/23/18
Wed
3/28/18
10 Jeff
3.2 Application drafting 5 days Thu Wed 4/4/18 13 Jeff
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT INITIATION PLANNING AND EXECUTION
3/29/18
3.3
Pending utility
clearances
3 days
Thu
3/29/18
Mon 4/2/18 11,13 Kelly
3.4
Shifting project
implementation
4 days Thu 4/5/18
Tue
4/10/18
14 Jeff
3.5
Utility subscription
cancelation
6 days Tue 4/3/18
Tue
4/10/18
15
both Kelly and
Jeff
3.6 House cleaning 4 days
Wed
4/11/18
Mon
4/16/18
16 Jeff
3.7 Partial payment 2 days
Wed
4/11/18
Thu
4/12/18
16
both Kelly and
Jeff
3.8 Cars transport 3 days
Wed
4/11/18
Fri 4/13/18 16,17 Kelly
3.9
Payment
completion
2 days
Tue
4/17/18
Wed
4/18/18
18 Jeff
4 Project closure 4 days
Thu
4/19/18
Tue
4/24/18
4.1 Final date
considerate for
2 days Thu
4/19/18
Fri 4/20/18 21 both Kelly and
Jeff
3/29/18
3.3
Pending utility
clearances
3 days
Thu
3/29/18
Mon 4/2/18 11,13 Kelly
3.4
Shifting project
implementation
4 days Thu 4/5/18
Tue
4/10/18
14 Jeff
3.5
Utility subscription
cancelation
6 days Tue 4/3/18
Tue
4/10/18
15
both Kelly and
Jeff
3.6 House cleaning 4 days
Wed
4/11/18
Mon
4/16/18
16 Jeff
3.7 Partial payment 2 days
Wed
4/11/18
Thu
4/12/18
16
both Kelly and
Jeff
3.8 Cars transport 3 days
Wed
4/11/18
Fri 4/13/18 16,17 Kelly
3.9
Payment
completion
2 days
Tue
4/17/18
Wed
4/18/18
18 Jeff
4 Project closure 4 days
Thu
4/19/18
Tue
4/24/18
4.1 Final date
considerate for
2 days Thu
4/19/18
Fri 4/20/18 21 both Kelly and
Jeff

8PROJECT INITIATION PLANNING AND EXECUTION
complete shifting
4.2 End of shifting 2 days
Mon
4/23/18
Tue
4/24/18
23
both Kelly and
Jeff
5. Personal reflection on the process
I have realized that the time estimated for the house shifting is very limited and within
that limited time phase it is difficult to accomplish the entire task securely. Before planning and
implementing the project the project activities are needed to be understood accurately by Kelly
and Jeff. For this particular project triple project constraints have been selected including time,
budget and scope. They should leave their current house within 20th January and must complete
the shift within 27th January. On the other hand the total budget estimated for the project is
$5000. I have also learned that, based on the project budget, some of the project activities are
needed to be modified rather should be done simultaneously.
Conclusion
From the overall discussion it can be concluded that, in order to accomplish the shifting
project it is necessary for the project head to consider three basic project phases in terms of
initiation, planning and execution. For this particular shifting Jeff and Kelly both are responsible
to develop the project schedule and activities. It is expected that, if all of these steps are
maintained accurately by both Jeff and Kelly, then the project will be completed within
estimated time and project budget as well. As Jeff is currently posted as a marketing director thus
they have to change their current location. After detailing the project report, the completion, slips
complete shifting
4.2 End of shifting 2 days
Mon
4/23/18
Tue
4/24/18
23
both Kelly and
Jeff
5. Personal reflection on the process
I have realized that the time estimated for the house shifting is very limited and within
that limited time phase it is difficult to accomplish the entire task securely. Before planning and
implementing the project the project activities are needed to be understood accurately by Kelly
and Jeff. For this particular project triple project constraints have been selected including time,
budget and scope. They should leave their current house within 20th January and must complete
the shift within 27th January. On the other hand the total budget estimated for the project is
$5000. I have also learned that, based on the project budget, some of the project activities are
needed to be modified rather should be done simultaneously.
Conclusion
From the overall discussion it can be concluded that, in order to accomplish the shifting
project it is necessary for the project head to consider three basic project phases in terms of
initiation, planning and execution. For this particular shifting Jeff and Kelly both are responsible
to develop the project schedule and activities. It is expected that, if all of these steps are
maintained accurately by both Jeff and Kelly, then the project will be completed within
estimated time and project budget as well. As Jeff is currently posted as a marketing director thus
they have to change their current location. After detailing the project report, the completion, slips

9PROJECT INITIATION PLANNING AND EXECUTION
and delay details are also elaborated accurately. The reasons for which the changes are found to
be necessary to implemented are also elaborated in this report. Apart from this, the details of
adjustment, incorporated to the project schedule and need for the modification are demonstrated
in this report. From the entire project discussion it has been found that, if all of these aspects are
followed accurately by the project manager, then the project will be completed within estimated
budget and cost as well.
and delay details are also elaborated accurately. The reasons for which the changes are found to
be necessary to implemented are also elaborated in this report. Apart from this, the details of
adjustment, incorporated to the project schedule and need for the modification are demonstrated
in this report. From the entire project discussion it has been found that, if all of these aspects are
followed accurately by the project manager, then the project will be completed within estimated
budget and cost as well.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

10PROJECT INITIATION PLANNING AND EXECUTION
References
Alzahrani, J.I. and Emsley, M.W., 2013. The impact of contractors’ attributes on construction
project success: A post construction evaluation. International Journal of Project
Management, 31(2), pp.313-322.
Batselier, J. and Vanhoucke, M., 2015. Construction and evaluation framework for a real-life
project database. International Journal of Project Management, 33(3), pp.697-710.
Bryde, D., Broquetas, M. and Volm, J.M., 2013. The project benefits of building information
modelling (BIM). International journal of project management, 31(7), pp.971-980.
Chen, L. and Luo, H., 2014. A BIM-based construction quality management model and its
applications. Automation in construction, 46, pp.64-73.
Dallasega, P., Frosolini, E. and Matt, D.T., 2016. An approach supporting Real-Time Project
Management in Plant Building and the Construction Industry. Proceedings of the XXI Summer
School Francesco Turco, Naples, Italy, pp.13-15.
Deng, X., Pheng, L.S. and Zhao, X., 2014. Project system vulnerability to political risks in
international construction projects: The case of Chinese contractors. Project Management
Journal, 45(2), pp.20-33.
Eadie, R., Browne, M., Odeyinka, H., McKeown, C. and McNiff, S., 2013. BIM implementation
throughout the UK construction project lifecycle: An analysis. Automation in Construction, 36,
pp.145-151.
References
Alzahrani, J.I. and Emsley, M.W., 2013. The impact of contractors’ attributes on construction
project success: A post construction evaluation. International Journal of Project
Management, 31(2), pp.313-322.
Batselier, J. and Vanhoucke, M., 2015. Construction and evaluation framework for a real-life
project database. International Journal of Project Management, 33(3), pp.697-710.
Bryde, D., Broquetas, M. and Volm, J.M., 2013. The project benefits of building information
modelling (BIM). International journal of project management, 31(7), pp.971-980.
Chen, L. and Luo, H., 2014. A BIM-based construction quality management model and its
applications. Automation in construction, 46, pp.64-73.
Dallasega, P., Frosolini, E. and Matt, D.T., 2016. An approach supporting Real-Time Project
Management in Plant Building and the Construction Industry. Proceedings of the XXI Summer
School Francesco Turco, Naples, Italy, pp.13-15.
Deng, X., Pheng, L.S. and Zhao, X., 2014. Project system vulnerability to political risks in
international construction projects: The case of Chinese contractors. Project Management
Journal, 45(2), pp.20-33.
Eadie, R., Browne, M., Odeyinka, H., McKeown, C. and McNiff, S., 2013. BIM implementation
throughout the UK construction project lifecycle: An analysis. Automation in Construction, 36,
pp.145-151.

11PROJECT INITIATION PLANNING AND EXECUTION
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Heldman, K., 2015. PMP project management professional exam deluxe study guide: updated
for the 2015 Exam. John Wiley & Sons.
Hu, Y., Chan, A.P., Le, Y. and Jin, R.Z., 2013. From construction megaproject management to
complex project management: Bibliographic analysis. Journal of management in
engineering, 31(4), p.04014052.
Hughes, W., Champion, R. and Murdoch, J., 2015. Construction contracts: law and
management. Routledge.
Pemsel, S. and Wiewiora, A., 2013. Project management office a knowledge broker in project-
based organisations. International Journal of Project Management, 31(1), pp.31-42.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Heldman, K., 2015. PMP project management professional exam deluxe study guide: updated
for the 2015 Exam. John Wiley & Sons.
Hu, Y., Chan, A.P., Le, Y. and Jin, R.Z., 2013. From construction megaproject management to
complex project management: Bibliographic analysis. Journal of management in
engineering, 31(4), p.04014052.
Hughes, W., Champion, R. and Murdoch, J., 2015. Construction contracts: law and
management. Routledge.
Pemsel, S. and Wiewiora, A., 2013. Project management office a knowledge broker in project-
based organisations. International Journal of Project Management, 31(1), pp.31-42.

12PROJECT INITIATION PLANNING AND EXECUTION
Appendices
Appendix 1
Updated milestones
Task Name Duration Start Finish
Milestone 4: Completion of project
closure
0 days Tue 4/24/18 Tue 4/24/18
Milestone 1: Completion of project
initiation phase
0 days Wed 3/21/18 Wed 3/21/18
Milestone 2: Completion of Project
planning and packing
0 days Fri 3/23/18 Fri 3/23/18
Milestone 3: Completion of project
preparation phase
0 days Thu 4/12/18 Thu 4/12/18
Milestone 4: Completion of project
closure
0 days Tue 4/24/18 Tue 4/24/18
Appendix 2
Updated task list
Task Name
Appendices
Appendix 1
Updated milestones
Task Name Duration Start Finish
Milestone 4: Completion of project
closure
0 days Tue 4/24/18 Tue 4/24/18
Milestone 1: Completion of project
initiation phase
0 days Wed 3/21/18 Wed 3/21/18
Milestone 2: Completion of Project
planning and packing
0 days Fri 3/23/18 Fri 3/23/18
Milestone 3: Completion of project
preparation phase
0 days Thu 4/12/18 Thu 4/12/18
Milestone 4: Completion of project
closure
0 days Tue 4/24/18 Tue 4/24/18
Appendix 2
Updated task list
Task Name
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

13PROJECT INITIATION PLANNING AND EXECUTION
Project initiation
Estimation of time for house shifting
Budget estimation
Project planning
List of items to be shifted
Hiring transportation company
Planning for packing furniture
Planning for packing cars
Hotel booking
Elimination of unwanted stuffs
Payment approach development
Project preparation
Labeling the important item to avoid loss and damage
Application drafting
Pending utility clearances
Project initiation
Estimation of time for house shifting
Budget estimation
Project planning
List of items to be shifted
Hiring transportation company
Planning for packing furniture
Planning for packing cars
Hotel booking
Elimination of unwanted stuffs
Payment approach development
Project preparation
Labeling the important item to avoid loss and damage
Application drafting
Pending utility clearances
1 out of 14
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024  |  Zucol Services PVT LTD  |  All rights reserved.