This document presents a solution to a project management assignment, addressing key concepts such as scheduling operations, capacity planning, and critical path analysis. The solution includes a Gantt chart, makespan calculation, machine idle time analysis, and machine utilization. The assignment also involves network diagrams, forward and backward passes, and identification of the critical path. The document provides detailed calculations and answers related to job delivery times, bottleneck identification, and waiting times for different jobs, offering a comprehensive understanding of project management principles. This assignment is a good resource for understanding project management concepts and preparing for similar assignments.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: PROJECT MANAGEMENT
PROJECT MANAGEMENT
Name of the Student
Name of the University
Author Note
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1PROJECT MANAGEMENT
Question 1
Job Work Center/Machine Hours
Due Date (days)
1 A/3, B/2, C/2 3
2 C/2, A/4 2
3 B/6, A/1, C/3 4
4 C/4, A/1, B/2 3
a. Gantt chart using finite capacity scheduling
Mahchine/
Hr
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
A 1 1 1 2 2 2 2 4 3
B 1 1 3 3 3 3 3 3 4 4
C 2 2 4 4 4 4 1 1 3 3 3
b. Makespan = 18 hour
c. Machine idle time:
For machine A= 9 hrs, B= 10 hrs and C= 11 hrs.
Total Idle Time = 30 hrs.
d. Waiting time for each job:
Job 1 = 2 hrs.
Document Page
2PROJECT MANAGEMENT
Job 2 = 1 hr.
Job 3 = 8 hrs.
Job 4 = 7 hrs.
e. Job delivery Time
Job 1 = 9 hrs.
Job 2 = 7 hrs.
Job 3 = 18 hrs.
Job 4 = 14 hrs.
f. Bottleneck = Machine C.
g. Machine Utilization:
Machine utilization = Total machine idle time/ total hours = 30/54 = 55.55%
Question 2:
Activity Immediate Predecessor Activity time
A - 3
B A 2
C - 5
D B, C 2
E A 4
F B, C 6
G E, D 5
a. Network of the Project
Document Page
3PROJECT MANAGEMENT
b. Forward pass and backward pass
c. Critical path:
ABDG
AEG
chevron_up_icon
1 out of 4
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]