Project Management: Application Development for Blood Donation
VerifiedAdded on  2020/02/03
|14
|3578
|53
Project
AI Summary
This project management report details the development of a blood donation application designed to connect donors with hospitals in need. The project outlines the goals and objectives, focusing on fulfilling emergency blood needs and streamlining the donation process. It includes a comprehensive project scope, risk assessment, and stakeholder analysis. The report also covers project organization structure, roles, responsibilities, and a project control mechanism. The planning section includes project milestones, budget assumptions, and critical success factors. The application aims to provide real-time notifications to donors and hospitals, ensuring timely blood availability. The project emphasizes the use of technology to improve efficiency and address healthcare needs. The project's success will be measured by the number of registered donors and the efficiency of the blood donation process.

Project Management: Blood
Donation
1
Donation
1
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

TABLE OF CONTENTS
INTRODUCTION...........................................................................................................................3
1. Project goals, objectives and critical successive function.......................................................4
2. Project scope............................................................................................................................5
3. Determining the risk and constraints affecting the project......................................................5
4. Assumptions made regarding project......................................................................................6
5. Project organization structure roles and responsibilities.........................................................6
6. Project control mechanism ......................................................................................................8
7. Reporting framework...............................................................................................................8
8. Stakeholder Analysis and their involvement...........................................................................9
9. Project planning with milestone..............................................................................................9
10. Budget assumption...............................................................................................................12
CONCLUSION ............................................................................................................................13
REFERENCES..............................................................................................................................14
2
INTRODUCTION...........................................................................................................................3
1. Project goals, objectives and critical successive function.......................................................4
2. Project scope............................................................................................................................5
3. Determining the risk and constraints affecting the project......................................................5
4. Assumptions made regarding project......................................................................................6
5. Project organization structure roles and responsibilities.........................................................6
6. Project control mechanism ......................................................................................................8
7. Reporting framework...............................................................................................................8
8. Stakeholder Analysis and their involvement...........................................................................9
9. Project planning with milestone..............................................................................................9
10. Budget assumption...............................................................................................................12
CONCLUSION ............................................................................................................................13
REFERENCES..............................................................................................................................14
2

INTRODUCTION
The concept of Project management is regarded as one time efforts which leads to
achievement of particular target. This is comprised of development of project plan. Along witgh
this it involves stating the goals and targets and making determination of the task which are
needed to be utilized for the sake of achieving specified targets. Further it makes determination
and assignment of the resources and identifies the budget for accomplishment of the project plan
in an effective manner (Konstantinou and Müller, 2016). Within the particular report
development of new application is done so that blood donation can be made any time when
required.
Project introduction
Blood donation application is considered as the computerized software that is being
installed within the mobiles in order to attract the donors towards the various hospitals that are
registered in the application. The development of the application is being carried out in order to
persuade the donors so that they can register themselves for blood donation at any point of time.
The system is effective in understanding the blood donation operations and assist in putting
suitable control system. This act as an aid in visualizing of the information, automatic report
collection, creation of alarm for the donors. Under this application the requirement of blood by
the hospital would be updated on the application (Olson and Wu, 2017). Thus with this the
donors who have installed the application would get notification. Thus either they can approach
the hospital or can refer any other person. Here it is important for the donor that after getting the
notification then are required to give instant reply on the same. This is in order to fulfill the
requirement of the hospital on emergency basis. Limited scope of 5 people will be there for
required particular blood group. After this the time of registering would not be seen. This would
assist in making instant decision by the hospital. Thus satisfaction can be provided to the
individuals who are in need of blood on emergency basis. It is considered as ongoing activity
that includes several managerial aspects that involves planning, organizing management of
resources, controlling and others. In the present project management the aim is towards project
schedule designing, scope, determination of need for resources, estimation of cost, time, risk
mitigation, management of quality approaches for development of new application.
3
The concept of Project management is regarded as one time efforts which leads to
achievement of particular target. This is comprised of development of project plan. Along witgh
this it involves stating the goals and targets and making determination of the task which are
needed to be utilized for the sake of achieving specified targets. Further it makes determination
and assignment of the resources and identifies the budget for accomplishment of the project plan
in an effective manner (Konstantinou and Müller, 2016). Within the particular report
development of new application is done so that blood donation can be made any time when
required.
Project introduction
Blood donation application is considered as the computerized software that is being
installed within the mobiles in order to attract the donors towards the various hospitals that are
registered in the application. The development of the application is being carried out in order to
persuade the donors so that they can register themselves for blood donation at any point of time.
The system is effective in understanding the blood donation operations and assist in putting
suitable control system. This act as an aid in visualizing of the information, automatic report
collection, creation of alarm for the donors. Under this application the requirement of blood by
the hospital would be updated on the application (Olson and Wu, 2017). Thus with this the
donors who have installed the application would get notification. Thus either they can approach
the hospital or can refer any other person. Here it is important for the donor that after getting the
notification then are required to give instant reply on the same. This is in order to fulfill the
requirement of the hospital on emergency basis. Limited scope of 5 people will be there for
required particular blood group. After this the time of registering would not be seen. This would
assist in making instant decision by the hospital. Thus satisfaction can be provided to the
individuals who are in need of blood on emergency basis. It is considered as ongoing activity
that includes several managerial aspects that involves planning, organizing management of
resources, controlling and others. In the present project management the aim is towards project
schedule designing, scope, determination of need for resources, estimation of cost, time, risk
mitigation, management of quality approaches for development of new application.
3
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

1. Project goals, objectives and critical successive function
Goal and mission: The major aim beside development of the new application is towards making
sure the fulfillment of the emergency need of blood. This is effective in satisfying the needs of
the target market to a greater extent.
Objectives:
ï‚· To ensure that proper notification is provided to the one who have downloaded the
application
ï‚· To make sure that registration of the individuals are being viewed (Gao, Chen and Shi,
2017)ï‚· To make sure that limited scope kept is filled in an effective manner so that need of
hospital is accomplished.
Critical success factorsï‚· Experienced and talented developers: Project planner possess major need that is towards
having skilled and talented designers of software who are able to gain knowledge in
relation to actual need of the new blood donation application in accordance with the
specification of the hospitals (Heagney, 2016).ï‚· Management of risk: Each project has some risk associated with it. This can be in
association with the technical failure, scope, lack of finance and other kind of risks that
needs to be managed in an effective manner in order to reduce the number of threats and
make sure planning in successful manner.ï‚· Management of time and cost: It has significance in making sure execution of work in
accordance with the planned action in addition with the schedule of time that application
of Blood donation can be devised in specified span of time (Hobbs, 2009). Further
management of finance is important towards not exceeding the actual costs beyond the
target limit.
ï‚· Effectiveness in communication: For the purpose of increasing awareness among the
members of team set plan, policies as well as process, suitable communication is of
greater importance. Further the subordinates needs to report their authorities within
specified time that whether the operations are going in line with the plan of the project or
4
Goal and mission: The major aim beside development of the new application is towards making
sure the fulfillment of the emergency need of blood. This is effective in satisfying the needs of
the target market to a greater extent.
Objectives:
ï‚· To ensure that proper notification is provided to the one who have downloaded the
application
ï‚· To make sure that registration of the individuals are being viewed (Gao, Chen and Shi,
2017)ï‚· To make sure that limited scope kept is filled in an effective manner so that need of
hospital is accomplished.
Critical success factorsï‚· Experienced and talented developers: Project planner possess major need that is towards
having skilled and talented designers of software who are able to gain knowledge in
relation to actual need of the new blood donation application in accordance with the
specification of the hospitals (Heagney, 2016).ï‚· Management of risk: Each project has some risk associated with it. This can be in
association with the technical failure, scope, lack of finance and other kind of risks that
needs to be managed in an effective manner in order to reduce the number of threats and
make sure planning in successful manner.ï‚· Management of time and cost: It has significance in making sure execution of work in
accordance with the planned action in addition with the schedule of time that application
of Blood donation can be devised in specified span of time (Hobbs, 2009). Further
management of finance is important towards not exceeding the actual costs beyond the
target limit.
ï‚· Effectiveness in communication: For the purpose of increasing awareness among the
members of team set plan, policies as well as process, suitable communication is of
greater importance. Further the subordinates needs to report their authorities within
specified time that whether the operations are going in line with the plan of the project or
4
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

not. This is considered as key need in Blood donation project and promote the planner in
strengthening the process of communication as well as system.
2. Project scope
The scope of the present project is essential part of the project planning that assist in
making determination of several functions that are included within the project for the sake of
achieving the desired targets in an effective manner. This is important for the manager of project
to state the scope of the project on every day basis in order to develop the boundaries that can be
covered in the software of Blood donation (Kloppenborg, 2011). The criteria associated with the
plan is that donors are available when there is greater requirement among the hospital.
Standardization of the software system offers greater facilities to the users. It makes the
determination of people who have willingness towards donating the blood. In this there is
presence of two advanced features that includes higher level of interface as well as energy
optimization that would assist the project manager in making creation of online platform that is
ensuring safety, management of the operations and timely fulfillment of the need. The
functionality is kept sound in terms that as the aspect is related with health care thus any delays
can result in affecting the deliverance of the services to a greater extent. Thus application needs
to be devised with proper attention considering the scope as well. Here SMART technique is
being used so that progress of the application can be assessed in an effective manner. SMART
reflects specific, measurable, achievable, reliable as well as time bound. The project plan needs
to be developed with 7 months time and its success can be measured by the number of people
who are registering themselves as donor.
3. Determining the risk and constraints affecting the project
Risk analysis
Each project is comprised of various risk that has to be managed in an effective manner
with suitable planning, monitoring as well as controlling. Through the present project the major
emphasis of the project planner is at introduction of the blood donation application in order to
offer adequate services. In the present era with the increase in number of uncertainties related
with the health. There is greater need towards in the present towards making development of
application that does not includes risk. So that it can effectively meet the need of the target
customers in an effective manner (Sommerville, 2011). Along with this proper care needs to be
5
strengthening the process of communication as well as system.
2. Project scope
The scope of the present project is essential part of the project planning that assist in
making determination of several functions that are included within the project for the sake of
achieving the desired targets in an effective manner. This is important for the manager of project
to state the scope of the project on every day basis in order to develop the boundaries that can be
covered in the software of Blood donation (Kloppenborg, 2011). The criteria associated with the
plan is that donors are available when there is greater requirement among the hospital.
Standardization of the software system offers greater facilities to the users. It makes the
determination of people who have willingness towards donating the blood. In this there is
presence of two advanced features that includes higher level of interface as well as energy
optimization that would assist the project manager in making creation of online platform that is
ensuring safety, management of the operations and timely fulfillment of the need. The
functionality is kept sound in terms that as the aspect is related with health care thus any delays
can result in affecting the deliverance of the services to a greater extent. Thus application needs
to be devised with proper attention considering the scope as well. Here SMART technique is
being used so that progress of the application can be assessed in an effective manner. SMART
reflects specific, measurable, achievable, reliable as well as time bound. The project plan needs
to be developed with 7 months time and its success can be measured by the number of people
who are registering themselves as donor.
3. Determining the risk and constraints affecting the project
Risk analysis
Each project is comprised of various risk that has to be managed in an effective manner
with suitable planning, monitoring as well as controlling. Through the present project the major
emphasis of the project planner is at introduction of the blood donation application in order to
offer adequate services. In the present era with the increase in number of uncertainties related
with the health. There is greater need towards in the present towards making development of
application that does not includes risk. So that it can effectively meet the need of the target
customers in an effective manner (Sommerville, 2011). Along with this proper care needs to be
5

given so that work can be performed with greater effectiveness. The risk associated with such
can be controlled and managed by means of taking various steps. Further technical failure can
increase by mitigating it through regular consultation with IT department who possess the
accountability towards updating the application to a greater extent. Further they are responsible
for determining the technical errors and reduce such. By the means of this software the company
is able to attain the success through the execution of the particular project plan.
In blood donation Application there are many risk involves in it. In technical risk, it
included all the technical factors which are ever changing in nature. Due to change in techniques
such as adopting new technology are effected in it.
Financial risk is also kind of risk which are analysis in Blood Donation Application. It
include shortage of fund, lack of resources, lack of availability of suppliers are the factors which
is related to financial risk.
Human Resource risk is also a type of risk, in which the potential of employees may
affect in it. In addition to this, it can be said that risk in regard to operational values is also high
because it allows to have effective development of tools. Application of measures in regard to
operations might be improper due to lack of understanding. It might affect the overall outcome
so managers need to ensure about the standards.
4. Assumptions made regarding projectï‚· Need for resources: The new application need several resources that includes internet,
hardware, software, man power and Sufficient amount of financial resourcesï‚· Cost: The development of application require cost so that Blood donation application can
be developed in an effective manner.ï‚· Time: The development of the application is expected to be completed in specified
duration of time that 7 months.
ï‚· Deliverable: Designing of the web platform so that requirement of the hospitals can be
managed. Along with this monitoring of the activities has to be done.
5. Project organization structure roles and responsibilities
Structure: It is a structure which support and operate the blood donation application in proper
way. All this bodies in this structure are responsible of there work and make an effective
6
can be controlled and managed by means of taking various steps. Further technical failure can
increase by mitigating it through regular consultation with IT department who possess the
accountability towards updating the application to a greater extent. Further they are responsible
for determining the technical errors and reduce such. By the means of this software the company
is able to attain the success through the execution of the particular project plan.
In blood donation Application there are many risk involves in it. In technical risk, it
included all the technical factors which are ever changing in nature. Due to change in techniques
such as adopting new technology are effected in it.
Financial risk is also kind of risk which are analysis in Blood Donation Application. It
include shortage of fund, lack of resources, lack of availability of suppliers are the factors which
is related to financial risk.
Human Resource risk is also a type of risk, in which the potential of employees may
affect in it. In addition to this, it can be said that risk in regard to operational values is also high
because it allows to have effective development of tools. Application of measures in regard to
operations might be improper due to lack of understanding. It might affect the overall outcome
so managers need to ensure about the standards.
4. Assumptions made regarding projectï‚· Need for resources: The new application need several resources that includes internet,
hardware, software, man power and Sufficient amount of financial resourcesï‚· Cost: The development of application require cost so that Blood donation application can
be developed in an effective manner.ï‚· Time: The development of the application is expected to be completed in specified
duration of time that 7 months.
ï‚· Deliverable: Designing of the web platform so that requirement of the hospitals can be
managed. Along with this monitoring of the activities has to be done.
5. Project organization structure roles and responsibilities
Structure: It is a structure which support and operate the blood donation application in proper
way. All this bodies in this structure are responsible of there work and make an effective
6
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

reporting about the performance and execution of work (Thomson and El-Haram, 2014). With
the current project of blood donation application, the structure will be as follows:
The project of new application development will require a team of various members who
will be assigned with the following roles and responsibilities that has been presented here as
under:ï‚· Project manager: The role and responsibilities of the project manager to make
development of strategies and keep control on the activities of new project plan. Further
his role is determine the resource needed for project of blood donation application.
Another key responsibility is towards motivating the staff for attainment of the targets.ï‚· Quality manager: Their roles and responsibilities is towards designing the policies and
plans towards management of quality. Further they are involved in establishing the
standards of quality. In addition to this quality manager has the responsibility to take
correct actions for improving the quality of application.ï‚· IT manager: The manager of IT possess the roles and responsibilities that is to identify
the error and make effort on it. Further it offer new technical idea. They possess role
towards development of infrastructure for making the blood donation application and
accordingly implement it.ï‚· Software developer: They possess the responsibility towards understanding the need
where is to be needed and design an special security for blood donation application as per
the rules. Moreover they have the role of examining the issues in the existing software
and introduce new advanced features like high level interface and energy optimizing.ï‚· Manager for training: They have role to devise schedules for offering training to
members and develop program associated with induction. Along with this they possess
role of interacting with the project team members to identify the training needs and
launch training accordingly.
ï‚· Finance manager: The manager of finance possess the responsibility to keep a track on
selection or requirement of funds and capital needed to meet financial requirement.
Along with this it includes checking of the use of funds in an effective manner. Also they
have responsibility to monitor the functioning of organization.
7
the current project of blood donation application, the structure will be as follows:
The project of new application development will require a team of various members who
will be assigned with the following roles and responsibilities that has been presented here as
under:ï‚· Project manager: The role and responsibilities of the project manager to make
development of strategies and keep control on the activities of new project plan. Further
his role is determine the resource needed for project of blood donation application.
Another key responsibility is towards motivating the staff for attainment of the targets.ï‚· Quality manager: Their roles and responsibilities is towards designing the policies and
plans towards management of quality. Further they are involved in establishing the
standards of quality. In addition to this quality manager has the responsibility to take
correct actions for improving the quality of application.ï‚· IT manager: The manager of IT possess the roles and responsibilities that is to identify
the error and make effort on it. Further it offer new technical idea. They possess role
towards development of infrastructure for making the blood donation application and
accordingly implement it.ï‚· Software developer: They possess the responsibility towards understanding the need
where is to be needed and design an special security for blood donation application as per
the rules. Moreover they have the role of examining the issues in the existing software
and introduce new advanced features like high level interface and energy optimizing.ï‚· Manager for training: They have role to devise schedules for offering training to
members and develop program associated with induction. Along with this they possess
role of interacting with the project team members to identify the training needs and
launch training accordingly.
ï‚· Finance manager: The manager of finance possess the responsibility to keep a track on
selection or requirement of funds and capital needed to meet financial requirement.
Along with this it includes checking of the use of funds in an effective manner. Also they
have responsibility to monitor the functioning of organization.
7
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

ï‚· Database designer: He has the responsibility to examine the function related with testing
of system. Further they has the role to test system of the blood donation application and
finalized it.
6. Project control mechanism
Project control is an important part of project, in which project managers control the
system by minimizing the difference between the planning of project and its implementation.
There are various type of techniques to control the projects they are:ï‚· Establishing the standards- In this project manager firstly find out the standard and than
compare it with actual performance, on the basis of such performance project manger can
find out the deviations so that it will help to achieve the goals or reduces the risks
(Project Management Methodologies,2014).ï‚· Effective management policies- In an organisation every member are responsible to take
or follow all the effective management policies, so that it can make effective and
smoothly functioning of the blood donation and providing fully security for the people
(Brewer and Strahorn, 2012).ï‚· Observing the activity- Project manager observe each and every activity in blood
donation activity, after that he can find out the deviation between standard to actual
results. In this way, it is helpful to create a good results in an organisation.ï‚· Holding the staff meeting- In an organisation meetings are hold because by holding the
meeting of members, it is easy to identify the difficulties or problem in specific areas, and
also find out the area where improvements are really required for successful operations.
ï‚· Work dislocation structure- It is a best techniques to make control over the project by
project manager, by dividing the areas into sub- groups such as web designing
department, functional department, research departments etc., so that implementation of
work can done easily (Carroll, 2012).
7. Reporting framework
As this is presented above that each project need suitable communication of the policies
as well as strategies planning to the authority. Inadequacy within the communication can result
in creation of obstacles in the coordination, cooperation and effective performance of the project.
Communication with respect to reporting framework are as under:
8
of system. Further they has the role to test system of the blood donation application and
finalized it.
6. Project control mechanism
Project control is an important part of project, in which project managers control the
system by minimizing the difference between the planning of project and its implementation.
There are various type of techniques to control the projects they are:ï‚· Establishing the standards- In this project manager firstly find out the standard and than
compare it with actual performance, on the basis of such performance project manger can
find out the deviations so that it will help to achieve the goals or reduces the risks
(Project Management Methodologies,2014).ï‚· Effective management policies- In an organisation every member are responsible to take
or follow all the effective management policies, so that it can make effective and
smoothly functioning of the blood donation and providing fully security for the people
(Brewer and Strahorn, 2012).ï‚· Observing the activity- Project manager observe each and every activity in blood
donation activity, after that he can find out the deviation between standard to actual
results. In this way, it is helpful to create a good results in an organisation.ï‚· Holding the staff meeting- In an organisation meetings are hold because by holding the
meeting of members, it is easy to identify the difficulties or problem in specific areas, and
also find out the area where improvements are really required for successful operations.
ï‚· Work dislocation structure- It is a best techniques to make control over the project by
project manager, by dividing the areas into sub- groups such as web designing
department, functional department, research departments etc., so that implementation of
work can done easily (Carroll, 2012).
7. Reporting framework
As this is presented above that each project need suitable communication of the policies
as well as strategies planning to the authority. Inadequacy within the communication can result
in creation of obstacles in the coordination, cooperation and effective performance of the project.
Communication with respect to reporting framework are as under:
8

Type Objective Medium Frequency Audience
Meeting
for
technical
designing
Discussion on technical
designing issues and
determining the correct
solution
Face to face
communicatio
n will be done
In
accordance
with the
need
IT team and project
manager
Status
report of
project
Reporting to the
manager of the project
Here Email is
medium for
communicatio
n
Per month Entire members of team
8. Stakeholder Analysis and their involvement
In stakeholder analysis it include Donor who are interested to donate their blood, Patients
and Employees. To estimate the condition of donor such as number of donor, there blood group
etc. are considered in it. In patients, there numbers, kind of disease etc. are required in it.
Employees include working style, and there potential which are estimated in stakeholder
analysis.
9. Project planning with milestone
Task Name Duration Start Finish Predecessors
Blood donation application 136 days Fri 4/21/17 Thu
8/24/17
Planning 40 days Fri 4/21/17 Tue 6/6/17
Information search 10 days Fri 4/21/17 Thu 5/4/17
Documentation 4 days Fri 5/5/17 Tue 5/9/17 3
Development of plans 7 days Wed 5/10/17 Tue 5/16/17 4
Determination of the
targets 4 days Wed 5/17/17 Mon
5/22/17 5,4
Plan regarding
management of risk 8 days Tue 5/23/17 Tue 5/30/17 6,4,5
Milestone 2 days Wed 5/31/17 Thu 6/1/17 7
Plan for communication 5 days Fri 6/2/17 Tue 6/6/17 8,6
Implementation 49 days Wed 6/7/17 Wed
7/12/17
Development of team 7 days Wed 6/7/17 Fri 6/16/17 9
Attainment of finances 9 days Wed 6/7/17 Thu 8,9
9
Meeting
for
technical
designing
Discussion on technical
designing issues and
determining the correct
solution
Face to face
communicatio
n will be done
In
accordance
with the
need
IT team and project
manager
Status
report of
project
Reporting to the
manager of the project
Here Email is
medium for
communicatio
n
Per month Entire members of team
8. Stakeholder Analysis and their involvement
In stakeholder analysis it include Donor who are interested to donate their blood, Patients
and Employees. To estimate the condition of donor such as number of donor, there blood group
etc. are considered in it. In patients, there numbers, kind of disease etc. are required in it.
Employees include working style, and there potential which are estimated in stakeholder
analysis.
9. Project planning with milestone
Task Name Duration Start Finish Predecessors
Blood donation application 136 days Fri 4/21/17 Thu
8/24/17
Planning 40 days Fri 4/21/17 Tue 6/6/17
Information search 10 days Fri 4/21/17 Thu 5/4/17
Documentation 4 days Fri 5/5/17 Tue 5/9/17 3
Development of plans 7 days Wed 5/10/17 Tue 5/16/17 4
Determination of the
targets 4 days Wed 5/17/17 Mon
5/22/17 5,4
Plan regarding
management of risk 8 days Tue 5/23/17 Tue 5/30/17 6,4,5
Milestone 2 days Wed 5/31/17 Thu 6/1/17 7
Plan for communication 5 days Fri 6/2/17 Tue 6/6/17 8,6
Implementation 49 days Wed 6/7/17 Wed
7/12/17
Development of team 7 days Wed 6/7/17 Fri 6/16/17 9
Attainment of finances 9 days Wed 6/7/17 Thu 8,9
9
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6/15/17
Development of software 20 days Mon 6/19/17 Wed
7/12/17 11
Testing of system 6 days Fri 6/16/17 Fri 6/23/17 12
Updation of schedules 7 days Mon 6/26/17 Fri 6/30/17 14
Monitoring 31 days Thu 7/13/17 Wed
8/16/17
Inspection of the
functioning of application 12 days Thu 7/13/17 Wed
7/26/17 14,15,13
Analysis of progress
related with work 13 days Thu 7/27/17 Wed
8/16/17 17,15,14
Corrective measures 6 days Thu 7/27/17 Wed 8/2/17 17
Project closure 16 days Thu 8/3/17 Thu
8/24/17
Preparation of Report 9 days Thu 8/3/17 Mon
8/14/17 19
Post-implementation
Review 5 days Tue 8/15/17 Tue 8/22/17 21
Final submission 2 days Wed 8/23/17 Thu
8/24/17 22
Gantt chart
10
Development of software 20 days Mon 6/19/17 Wed
7/12/17 11
Testing of system 6 days Fri 6/16/17 Fri 6/23/17 12
Updation of schedules 7 days Mon 6/26/17 Fri 6/30/17 14
Monitoring 31 days Thu 7/13/17 Wed
8/16/17
Inspection of the
functioning of application 12 days Thu 7/13/17 Wed
7/26/17 14,15,13
Analysis of progress
related with work 13 days Thu 7/27/17 Wed
8/16/17 17,15,14
Corrective measures 6 days Thu 7/27/17 Wed 8/2/17 17
Project closure 16 days Thu 8/3/17 Thu
8/24/17
Preparation of Report 9 days Thu 8/3/17 Mon
8/14/17 19
Post-implementation
Review 5 days Tue 8/15/17 Tue 8/22/17 21
Final submission 2 days Wed 8/23/17 Thu
8/24/17 22
Gantt chart
10
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Network diagram
11
11

In addition to this, it can be said that current project critical path is between 4 to 9. It
takes more time as compared to other activities. Along with this, it can be said that by having an
appropriate understanding about the subject the issues can be overcome. Critical path of project
cannot be delayed because it might impact the overall process in diverse manner.
10. Budget assumption
This is regarded as financial framework that assist in determination of the sum of the
whole spending for designing, development and implementation of the application related to
blood donation.
Particulars Amount ( In GBP)
Acquiring license for application 3000
Cost of equipment 2400
Purchase of hardware 300
Server 1800
Networking cost (LAN, WAN & others) 1000
Salary to man power 2500
Total 11,000
12
takes more time as compared to other activities. Along with this, it can be said that by having an
appropriate understanding about the subject the issues can be overcome. Critical path of project
cannot be delayed because it might impact the overall process in diverse manner.
10. Budget assumption
This is regarded as financial framework that assist in determination of the sum of the
whole spending for designing, development and implementation of the application related to
blood donation.
Particulars Amount ( In GBP)
Acquiring license for application 3000
Cost of equipment 2400
Purchase of hardware 300
Server 1800
Networking cost (LAN, WAN & others) 1000
Salary to man power 2500
Total 11,000
12
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 14
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.