This project management assignment details the construction and development of a Wired Café within a university campus. The project encompasses various phases, including preliminary planning, design, project management planning, execution, survey, hiring, and project closure. The requirements document outlines the need for a coffee bar atmosphere, food storage, staff, comfortable furniture, charging outlets, technology tutoring, and a reliable internet connection. The project scope statement defines deliverables such as a suitable coffee bar, food storage, staff, furniture, outlets, tutoring, and internet. The work breakdown structure (WBS) breaks down the project into tasks, durations, and costs. The WBS includes detailed planning, design, execution, and closing phases. The project involves hiring contractors, procuring materials, constructing the café, installing furniture and equipment, conducting surveys, hiring and training staff, and managing risks. The project's success depends on meeting the specified requirements, adhering to the budget, and delivering the project on time. The assignment includes a detailed WBS, work breakdown dictionary, quality management plan, and network diagram, providing a comprehensive overview of the project's planning and execution. The project aims to provide students with a comfortable space for interaction and study, with modern amenities and a reliable internet connection.
Document Page
Running Head: PROJECT MANAGEMENT
Wired Café Project
Name of the Student
Name of the University
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1PROJECT MANAGEMENT
Table of Contents
Requirements Document.................................................................................................................2
Project Scope Statement..................................................................................................................3
Project Scope Description............................................................................................................3
Project Deliverables.....................................................................................................................3
Product Acceptance Criteria........................................................................................................3
Project Exclusions.......................................................................................................................4
Work Breakdown Structure.............................................................................................................4
Work Breakdown Dictionary...........................................................................................................6
Quality Management Plan.............................................................................................................11
Network Diagram..........................................................................................................................11
Estimations using Various Techniques..........................................................................................13
Communication Plan.....................................................................................................................14
Bibliography..................................................................................................................................16
Document Page
2PROJECT MANAGEMENT
Requirements Document
The project is basically based on the construction and development of a coffee bar with
appropriate atmosphere for the students of the university who can discuss various study related
and other topics within the university campus along with some coffee and snacks. The main
requirements to be delivered in this project are as follows.
Suitable coffee bar atmosphere
Specific area for storage of food materials
Hiring of staff for managing the coffee bar during the university class hours
Comfortable furniture for the students
Outlet ports for electronic charging and other purposes
Technology tutoring facility
Reliable internet connection with access to all relevant educational websites
Following the list above, the high level requirements of the project include the following.
Setting up IT compatible coffee bar with various facilities that will benefit the
students
Comfortable seating areas for the students inside the coffee bar
Specific area where the students can purchase and consume food and beverage
While the requirements above are more or less straightforward, there are also certain risks
and threats that the project team needs to be aware of while executing the project. Some of the
possible project risks include personal conflicts within the project team and the contracts, use of
non-secure networks while developing IT infrastructure and others.
Document Page
3PROJECT MANAGEMENT
Project Scope Statement
The scope statement for the project includes a number of different elements regarding
what deliverables will be fulfilled by the project and what aspects will be excluded from the
project. The scope statement includes the following items.
Project Scope Description
For this particular project, the scope includes construction and development of a new café
bar inside the university campus that will serve the purpose of a discussion area for the students
along with providing them with snacks and coffee.
Project Deliverables
The project deliverables are as follows.
Suitable coffee bar atmosphere
Specific area for storage of food materials
Hiring of staff for managing the coffee bar during the university class hours
Comfortable furniture for the students
Outlet ports for electronic charging and other purposes
Technology tutoring facility
Reliable internet connection with access to all relevant educational websites
Product Acceptance Criteria
Once the project is completed, it will be accepted on the condition that all the
deliverables are fulfilled and delivered that include the new kitchen area, sitting area, installed
equipments and amenities, reliable and secure internet connection and others. Furthermore, the
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4PROJECT MANAGEMENT
hired employees must be trained and the training report must be submitted before the project is
formally accepted and closed.
Project Exclusions
There are certain aspects that have been excluded from the project. These aspects are as
follows.
Allocating duties and roles to the hired staff
Procurement of food and consumables for initiating the operations
Work Breakdown Structure
WBS Task Name
0 Project for Construction and Development of Coffee Bar
1 Preliminary Planning and Discussions
1.1 Conduct meeting with the students' representatives
1.2 Discuss their issues and requirements regarding a coffee bar
1.3 Prepare an initial evaluation report
1.4 Forward to the university authority
1.5 Conduct meeting with the university authority
1.6 Discuss the requirements the students have requested
1.7 Receive approval to go ahead with the plan
1.8 Develop project proposal
1.9 Forward proposal to the authority
1.10 Receive green light for the project
2 Planning and Design
2.1 Location Selection
2.1.1 Create a project planning team
2.1.2 Conduct survey of the university campus for the location of the café
Document Page
5PROJECT MANAGEMENT
2.1.3 Consider a number of different locations for the coffee bar
2.1.4 Milestone: Identify a specific location
2.2 Architecture Planning and Design
2.2.1 Hire architect for the design
2.2.2 Forward the requirements to the architect
2.2.3 Develop café blueprint
2.2.4 Develop architecture plan for the café
2.2.5 Milestone: Receive approval for the architecture plans
3 Project Management Planning
3.1 Develop project charter
3.2 Determine project scope
3.3 Determine objectives and deadline
3.4 Estimate budget
3.5 Risk management
3.6 Milestone: Project plan document delivered and approved
4 Project Execution
4.1 Construction Works
4.1.1 Hire contractor
4.1.2 Hire workers for the construction purposes
4.1.3 Procurement of materials for construction
4.1.4 Construction of the café as per the design
4.1.5 Interior and exterior designs and plastering
4.1.6 Application of colours on interiors and exteriors
4.1.7 Milestone: Construction Complete
4.2 Product Delivery and Installation
4.2.1 Order furniture from the vendors
4.2.2 Order equipments from the vendors
4.2.3 Milestone: Furniture delivered
4.2.4 Installation of the furniture
4.2.5 Installation of the equipments
Document Page
6PROJECT MANAGEMENT
4.2.6 Milestone: Equipments installed
5 Survey and Hiring
5.1 Inspection
5.1.1 Conduct a detailed survey and inspection on the new café
5.1.2 Identify if there are some mistakes and errors in the same
5.1.3 Develop an inspection report for the café
5.1.4 Milestone: Final inspection
5.2 Hiring
5.2.1 Hire workers for the café
5.2.2 Provide training to the workers
5.2.3 Milestone: Operations and technical training complete
6 Closing of the Project and Opening Day
6.1 Review of the project
6.2 Sign from stakeholders and closing
6.3 Milestone: Opening day
Work Breakdown Dictionary
WBS Task Name Duration Due Date Resources / Cost Elements Cost
0 Project for Construction and
Development of Coffee Bar 160 days Mon 05-10-20 $70,840.00
1 Preliminary Planning and Discussions 21 days Mon 23-03-20 $8,400.00
1.1 Conduct meeting with the students'
representatives 2 days Tue 25-02-20 Project Manager $800.00
1.2 Discuss their issues and requirements
regarding a coffee bar 2 days Thu 27-02-20 Project Manager $800.00
1.3 Prepare an initial evaluation report 2 days Mon 02-03-20 Project Manager $800.00
1.4 Forward to the university authority 2 days Wed 04-03-20 Project Manager $800.00
1.5 Conduct meeting with the university 2 days Fri 06-03-20 Project Manager $800.00
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7PROJECT MANAGEMENT
authority
1.6 Discuss the requirements the students
have requested 2 days Tue 10-03-20 Project Manager $800.00
1.7 Receive approval to go ahead with the
plan 2 days Thu 12-03-20 Project Manager $800.00
1.8 Develop project proposal 2 days Mon 16-03-20 Project Manager $800.00
1.9 Forward proposal to the authority 2 days Wed 18-03-20 Project Manager $800.00
1.10 Receive green light for the project 3 days Mon 23-03-20 Project Manager $1,200.00
2 Planning and Design 23 days Thu 23-04-20 $6,400.00
2.1 Location Selection 9 days Fri 03-04-20 $3,600.00
2.1.1 Create a project planning team 3 days Thu 26-03-20 Project Manager $1,200.00
2.1.2 Conduct survey of the university
campus for the location of the café 3 days Tue 31-03-20 Project Manager $1,200.00
2.1.3 Consider a number of different
locations for the coffee bar 3 days Fri 03-04-20 Project Manager $1,200.00
2.1.4 Milestone: Identify a specific location 0 days Fri 03-04-20 $0.00
2.2 Architecture Planning and Design 14 days Thu 23-04-20 $2,800.00
2.2.1 Hire architect for the design 3 days Wed 08-04-20 $0.00
2.2.2 Forward the requirements to the
architect 1 day Thu 09-04-20 Project Manager $400.00
2.2.3 Develop café blueprint 5 days Thu 16-04-20 Design Engineer $1,200.00
2.2.4 Develop architecture plan for the café 5 days Thu 23-04-20 Design Engineer $1,200.00
2.2.5 Milestone: Receive approval for the
architecture plans 0 days Thu 23-04-20 $0.00
3 Project Management Planning 10 days Thu 07-05-20 $4,000.00
3.1 Develop project charter 2 days Mon 27-04-20 Project Manager $800.00
3.2 Determine project scope 2 days Wed 29-04-20 Project Manager $800.00
3.3 Determine objectives and deadline 2 days Fri 01-05-20 Project Manager $800.00
3.4 Estimate budget 2 days Tue 05-05-20 Project Manager $800.00
3.5 Risk management 2 days Thu 07-05-20 Project Manager $800.00
3.6 Milestone: Project plan document
delivered and approved 0 days Thu 07-05-20 $0.00
Document Page
8PROJECT MANAGEMENT
4 Project Execution 50 days Thu 16-07-20 $32,040.00
4.1 Construction Works 42 days Mon 06-07-20 $20,840.00
4.1.1 Hire contractor 3 days Tue 12-05-20 Project Manager $1,200.00
4.1.2 Hire workers for the construction
purposes 2 days Thu 14-05-20 Contractor $320.00
4.1.3 Procurement of materials for
construction 2 days Mon 18-05-20 Contractor, Construction
Materials[1] $5,320.00
4.1.4 Construction of the café as per the
design 25 days Mon 22-06-20 Workers $10,000.00
4.1.5 Interior and exterior designs and
plastering 5 days Mon 29-06-20 Workers $2,000.00
4.1.6 Application of colours on interiors and
exteriors 5 days Mon 06-07-20 Workers $2,000.00
4.1.7 Milestone: Construction Complete 0 days Mon 06-07-20 $0.00
4.2 Product Delivery and Installation 8 days Thu 16-07-20 $11,200.00
4.2.1 Order furniture from the vendors 2 days Wed 08-07-20 Furniture Costs[1], Project
Manager $5,800.00
4.2.2 Order equipments from the vendors 2 days Fri 10-07-20 Other Material Costs[1],
Project Manager $3,800.00
4.2.3 Milestone: Furniture delivered 0 days Fri 10-07-20 $0.00
4.2.4 Installation of the furniture 2 days Tue 14-07-20 Workers $800.00
4.2.5 Installation of the equipments 2 days Thu 16-07-20 Workers $800.00
4.2.6 Milestone: Equipments installed 0 days Thu 16-07-20 $0.00
5 Survey and Hiring 45 days Thu 17-09-20 $18,000.00
5.1 Inspection 20 days Thu 13-08-20 $8,000.00
5.1.1 Conduct a detailed survey and
inspection on the new café 10 days Thu 30-07-20 Project Manager $4,000.00
5.1.2 Identify if there are some mistakes and
errors in the same 5 days Thu 06-08-20 Project Manager $2,000.00
5.1.3 Develop an inspection report for the
café 5 days Thu 13-08-20 Project Manager $2,000.00
5.1.4 Milestone: Final inspection 0 days Thu 13-08-20 $0.00
5.2 Hiring 25 days Thu 17-09-20 $10,000.00
5.2.1 Hire workers for the café 10 days Thu 27-08-20 Project Manager $4,000.00
Document Page
9PROJECT MANAGEMENT
5.2.2 Provide training to the workers 15 days Thu 17-09-20 Project Manager $6,000.00
5.2.3 Milestone: Operations and technical
training complete 0 days Thu 17-09-20 $0.00
6 Closing of the Project and Opening Day 11 days Mon 05-10-20 $2,000.00
6.1 Review of the project 2 days Mon 21-09-20 Project Manager $800.00
6.2 Sign from stakeholders and closing 3 days Thu 24-09-20 Project Manager $1,200.00
6.3 Milestone: Opening day 0 days Mon 05-10-20 $0.00
The resource usage in the project based on the above wbs dictionary is as follows.
Resource Name Work Cost
Project Manager 784 hrs $39,200.00
Conduct meeting with the students'
representatives 16 hrs $800.00
Discuss their issues and requirements regarding
a coffee bar 16 hrs $800.00
Prepare an initial evaluation report 16 hrs $800.00
Forward to the university authority 16 hrs $800.00
Conduct meeting with the university authority 16 hrs $800.00
Discuss the requirements the students have
requested 16 hrs $800.00
Receive approval to go ahead with the plan 16 hrs $800.00
Develop project proposal 16 hrs $800.00
Forward proposal to the authority 16 hrs $800.00
Receive green light for the project 24 hrs $1,200.00
Create a project planning team 24 hrs $1,200.00
Conduct survey of the university campus for the
location of the café 24 hrs $1,200.00
Consider a number of different locations for the
coffee bar 24 hrs $1,200.00
Forward the requirements to the architect 8 hrs $400.00
Develop project charter 16 hrs $800.00
Determine project scope 16 hrs $800.00
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10PROJECT MANAGEMENT
Determine objectives and deadline 16 hrs $800.00
Estimate budget 16 hrs $800.00
Risk management 16 hrs $800.00
Hire contractor 24 hrs $1,200.00
Order furniture from the vendors 16 hrs $800.00
Order equipments from the vendors 16 hrs $800.00
Conduct a detailed survey and inspection on the
new café 80 hrs $4,000.00
Identify if there are some mistakes and errors in
the same 40 hrs $2,000.00
Develop an inspection report for the café 40 hrs $2,000.00
Hire workers for the café 80 hrs $4,000.00
Provide training to the workers 120 hrs $6,000.00
Review of the project 16 hrs $800.00
Sign from stakeholders and closing 24 hrs $1,200.00
Design Engineer 80 hrs $2,400.00
Develop café blueprint 40 hrs $1,200.00
Develop architecture plan for the café 40 hrs $1,200.00
Contractor 32 hrs $640.00
Hire workers for the construction purposes 16 hrs $320.00
Procurement of materials for construction 16 hrs $320.00
Workers 312 hrs $15,600.00
Construction of the café as per the design 200 hrs $10,000.00
Interior and exterior designs and plastering 40 hrs $2,000.00
Application of colours on interiors and exteriors 40 hrs $2,000.00
Installation of the furniture 16 hrs $800.00
Installation of the equipments 16 hrs $800.00
Furniture Costs 1 $5,000.00
Order furniture from the vendors 1 $5,000.00
Other Material Costs 1 $3,000.00
Document Page
11PROJECT MANAGEMENT
Order equipments from the vendors 1 $3,000.00
Construction Materials 1 $5,000.00
Procurement of materials for construction 1 $5,000.00
Quality Management Plan
Ensuring fulfilment of certain quality standards is essential to any project and this project
is no different. Before the project work is started, a suitable quality management plan needs to be
developed. The aspects of the project that will have to be emphasized on include: quality of
materials utilised to build the coffee bar, quality of the equipments that will be procured and
installed, quality of the internet network services that will provided to the students and others.
For ensuring quality, detailed testing is recommended while procuring the products from the
vendors. Furthermore, frequent monitoring of the project is recommended so as to ensure the
quality standards are being fulfilled.
Network Diagram
Document Page
12PROJECT MANAGEMENT
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
13PROJECT MANAGEMENT
Figure: Network Diagram of the Project
(Source: Created by Author)
Estimations using Various Techniques
Previously above, the overall budget of the project has been estimated using bottom up
estimation technique where the usage rates and costs of the resources (human and material) are
determined and then allocated to individual work packages such that they total costs can be
calculated. However, this is not always the most accurate calculation because the durations of the
work packages themselves are not 100% reliable. The duration estimates are only ‘most likely
durations’ and they may change. Hence, it is recommended to calculate the most accurate
estimated duration for finding the more accurate budget; where:
Estimated duration = (Optimistic duration + Pessimistic Duration + 4*Most Likely
Duration) / 6
Document Page
14PROJECT MANAGEMENT
In this project, the most likely duration is 160 days, let the optimistic duration is 150 days
and pessimistic duration is 180 days. Hence, the estimated duration is: (150 + (4*160) + 180) / 6
= 162 days.
Accordingly, the budget will also change as the estimated duration is not equal to the
most likely duration. Based on this formula, the estimation calculations are done in the
spreadsheet attached with this document.
Communication Plan
An appropriate communication plan is developed for the project as follows.
Project Stakeholder Communication
Purpose
Communication
Frequency
Communication
Medium
Project Manager Requirements for
guidance, design
suggestions and other
requirements in the
project
Weekly Face to face / reports
Finance Manager Requirements for
allocation of funds for
the project
Biweekly Reports
Project Assistant Monitoring Daily Face to face
Excel
Worksheet.xlsx
Document Page
15PROJECT MANAGEMENT
requirements
Project Supervisor Project reporting
requirements
Daily Face to face
University Authority Sponsorship and
approvals
Weekly Reports / emails
Design Engineer
(Architect)
Design requirements Once Face to face
Contractor Construction
requirements
Weekly Face to face, design
documents
Students Ideas, inputs and their
own requirements
Weekly Face to face
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
16PROJECT MANAGEMENT
Bibliography
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach.
Routledge.
Heagney, J. (2016). Fundamentals of project management. Amacom.
Kerzner, H. (2017). Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Meredith, J. R., Mantel Jr, S. J., & Shafer, S. M. (2017). Project management: a managerial
approach. John Wiley & Sons.