Concepts of Project Management and Planning for Renovation Projects
VerifiedAdded on 2022/11/19
|7
|861
|136
Report
AI Summary
This report provides a comprehensive overview of project management concepts and their application to renovation projects, specifically focusing on kitchen and basement renovations. It explores various project evaluation techniques, including traditional, waterfall, Kanban, agile, scrum, and lean methodologies, analyzing their suitability for different project scenarios. The report emphasizes the importance of selecting the appropriate technique based on project requirements. Additionally, it includes Gantt charts to illustrate project timelines and task dependencies for both kitchen and basement renovation projects. The report highlights the significance of effective planning and management in ensuring successful project outcomes, considering budget, time frame, and project scope. It offers valuable insights into the practical application of project management principles in the context of renovation projects.

Running head: CONCEPTS OF PROJECT MANAGEMENT AND PLANNING
Concepts of Project Management and Planning
Name of the Student
Name of the University
Author note
Concepts of Project Management and Planning
Name of the Student
Name of the University
Author note
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1CONCEPTS OF PROJECT MANAGEMENT AND PLANNING
Table of Contents
1. Appropriate Techniques of Project Evaluation............................................................................2
2. Gantt chart of Project...................................................................................................................4
References........................................................................................................................................6
Table of Contents
1. Appropriate Techniques of Project Evaluation............................................................................2
2. Gantt chart of Project...................................................................................................................4
References........................................................................................................................................6

2CONCEPTS OF PROJECT MANAGEMENT AND PLANNING
1. Appropriate Techniques of Project Evaluation
The different techniques of evaluation of the room and kitchen renovation project are:
1. Traditional – The traditional form of project management technique mainly focuses
over the main activities involved in project management. Based on the renovation project, it
could be used for understanding that the traditional form of project management could be useful.
In this project, each of the activities would be completed in proper sequence.
2. Waterfall – This technique of project management is mainly useful in such kind of
projects in which every activity would need to be performed in a sequential manner or parallel
manner. As per the discussed project, it can be seen that the waterfall methodology could be
helpful for the management of projects (Kuhrmann et al., 2017). Tasks can be done in a
sequential manner. Moreover, the waterfall methodology would also help in finding the critical
activities that need to be done in order to proceed on to the next task of the development process.
3. Kanban – Although this form of project management could be useful in software
development process, however, this technique is not suitable for construction and renovation
projects. In this process, the work is mostly divided into small manageable tasks (Pheng &
Meng, 2018). Efficient work could be done with the help of different groups.
4. Agile – The agile project management approach can be defined as an iterative
approach for guiding the planning process for the project development. This process could be
useful for the kitchen renovation project as they would help in understanding of issues and
bringing necessary changes at any part of the project (Tomek & Kalinichuk, 2015). This would
also be helpful in saving of resources and help in delivering the project within the proper
1. Appropriate Techniques of Project Evaluation
The different techniques of evaluation of the room and kitchen renovation project are:
1. Traditional – The traditional form of project management technique mainly focuses
over the main activities involved in project management. Based on the renovation project, it
could be used for understanding that the traditional form of project management could be useful.
In this project, each of the activities would be completed in proper sequence.
2. Waterfall – This technique of project management is mainly useful in such kind of
projects in which every activity would need to be performed in a sequential manner or parallel
manner. As per the discussed project, it can be seen that the waterfall methodology could be
helpful for the management of projects (Kuhrmann et al., 2017). Tasks can be done in a
sequential manner. Moreover, the waterfall methodology would also help in finding the critical
activities that need to be done in order to proceed on to the next task of the development process.
3. Kanban – Although this form of project management could be useful in software
development process, however, this technique is not suitable for construction and renovation
projects. In this process, the work is mostly divided into small manageable tasks (Pheng &
Meng, 2018). Efficient work could be done with the help of different groups.
4. Agile – The agile project management approach can be defined as an iterative
approach for guiding the planning process for the project development. This process could be
useful for the kitchen renovation project as they would help in understanding of issues and
bringing necessary changes at any part of the project (Tomek & Kalinichuk, 2015). This would
also be helpful in saving of resources and help in delivering the project within the proper
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3CONCEPTS OF PROJECT MANAGEMENT AND PLANNING
assigned budget and time. In this part of project management, the project manager working over
the project could also help in discussing about specific aspects of project.
5. Scrum – This technique is mainly used in software development projects and thus
could also be useful for maintaining and managing an efficient mode of software delivery.
However, this technique could not be useful for renovation projects as this technique divides the
task in smaller sprints. During the performing of renovation work, this technique would not be a
viable technique to manage different forms of projects (Machado, Pinheiro & Tamanini, 2015).
The failure of prioritizing the set of features would mostly result in producing low quality over
the projects.
6. Lean – This technique of project management could be helpful in producing greater
form of customer satisfaction. Different concepts such as lean manufacturing, lean construction
and lean thinking could be useful in the aspects of project management. This technique would
also help in taking an account of the waste that might be created with overburden. This form of
technique would also help in reducing the efforts of others during the hours of engineering. The
primary goal of the lean management technique is to reduce the amount of effort that is being put
by every individual and would also help in achieving an operational excellence.
assigned budget and time. In this part of project management, the project manager working over
the project could also help in discussing about specific aspects of project.
5. Scrum – This technique is mainly used in software development projects and thus
could also be useful for maintaining and managing an efficient mode of software delivery.
However, this technique could not be useful for renovation projects as this technique divides the
task in smaller sprints. During the performing of renovation work, this technique would not be a
viable technique to manage different forms of projects (Machado, Pinheiro & Tamanini, 2015).
The failure of prioritizing the set of features would mostly result in producing low quality over
the projects.
6. Lean – This technique of project management could be helpful in producing greater
form of customer satisfaction. Different concepts such as lean manufacturing, lean construction
and lean thinking could be useful in the aspects of project management. This technique would
also help in taking an account of the waste that might be created with overburden. This form of
technique would also help in reducing the efforts of others during the hours of engineering. The
primary goal of the lean management technique is to reduce the amount of effort that is being put
by every individual and would also help in achieving an operational excellence.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4CONCEPTS OF PROJECT MANAGEMENT AND PLANNING
2. Gantt chart of Project
Initiation of the Project
Development of Preliminary design of kitchen 7/1 7/4 0 4 100%
Securing of funding source for the event 7/5 7-8 4 4 80%
Selection of subcontractors for the project 7/9 7/10 8 2 60%
Procurement of materials 7/11 7/12 10 2 40%
Designing of Work Packages
Demolishing of old kitchen space 7/15 7/24 14 10 100%
Securing the old equipment 7/25 7/26 24 2 80%
Rubbing of walls and painting 7/29 8/9 28 12 60%
Installation of kitchen appliances
Installation of cabinetry 8/12 8/13 42 2 100%
Installation of Refrigerator, Microwave and
Dishwasher 8/14 8/15 44 2 80%
Testing of the installed components 8/16 8/16 46 1 60%
Clean-Up Procedure
Removal of unused material 8/19 8/20 49 2 100%
Removal of trash 8/21 8/21 51 1 80%
Sign off on procurement 8/22 8/22 52 1 60%
Sign off on contractors 8/23 8/23 53 1 0%
TASK NAME START ON
DAY*
PERCENT
COMPLETE
DURATION*
(WORK DAYS)
END DATESTART DATE
WEEK 8WEEK 7WEEK 3 - 4WEEK 1 - 2
0 10 20 30 40 50 60
Development of Preliminary design of kitchen
Securing of funding source for the event
Selection of subcontractors for the project
Procurement of materials
Demolishing of old kitchen space
Securing the old equipment
Rubbing of walls and painting
Installation of cabinetry
Installation of Refrigerator, Microwave and Dishwasher
Testing of the installed components
Removal of unused material
Removal of trash
Sign off on procurement
Sign off on contractors
Days of the Project
(Figure 1: The Kitchen Renovation Project)
(Source: Created by author)
2. Gantt chart of Project
Initiation of the Project
Development of Preliminary design of kitchen 7/1 7/4 0 4 100%
Securing of funding source for the event 7/5 7-8 4 4 80%
Selection of subcontractors for the project 7/9 7/10 8 2 60%
Procurement of materials 7/11 7/12 10 2 40%
Designing of Work Packages
Demolishing of old kitchen space 7/15 7/24 14 10 100%
Securing the old equipment 7/25 7/26 24 2 80%
Rubbing of walls and painting 7/29 8/9 28 12 60%
Installation of kitchen appliances
Installation of cabinetry 8/12 8/13 42 2 100%
Installation of Refrigerator, Microwave and
Dishwasher 8/14 8/15 44 2 80%
Testing of the installed components 8/16 8/16 46 1 60%
Clean-Up Procedure
Removal of unused material 8/19 8/20 49 2 100%
Removal of trash 8/21 8/21 51 1 80%
Sign off on procurement 8/22 8/22 52 1 60%
Sign off on contractors 8/23 8/23 53 1 0%
TASK NAME START ON
DAY*
PERCENT
COMPLETE
DURATION*
(WORK DAYS)
END DATESTART DATE
WEEK 8WEEK 7WEEK 3 - 4WEEK 1 - 2
0 10 20 30 40 50 60
Development of Preliminary design of kitchen
Securing of funding source for the event
Selection of subcontractors for the project
Procurement of materials
Demolishing of old kitchen space
Securing the old equipment
Rubbing of walls and painting
Installation of cabinetry
Installation of Refrigerator, Microwave and Dishwasher
Testing of the installed components
Removal of unused material
Removal of trash
Sign off on procurement
Sign off on contractors
Days of the Project
(Figure 1: The Kitchen Renovation Project)
(Source: Created by author)

5CONCEPTS OF PROJECT MANAGEMENT AND PLANNING
Inspection or Occular of the house
Construction Permit for Renovation 7/1 7/3 0 3 100%
Deciding the Contractor and Builders 7/4 7-8 3 5 80%
Deciding the budget 7/9 7/10 8 2 60%
Measuring Size of the basement and lighting 7/11 7/12 10 2 40%
Start of Construction of the House
Deciding the wiring plans 7/15 7/25 14 11 100%
Heating and Air Condition Systems and Wi-Fi Signals 7/26 7/31 25 6 80%
Deciding the Technical Equipment, playing
equipment and colors 8/1 8/9 31 9 60%
Delivery of the equipment and checking them
Delivery of the equipment 8/12 8/14 42 3 100%
Checking the equipment 8/15 8/16 45 2 80%
Inspection by Sponsor or Home Owner
Checking over the designed equipment 8/19 8/21 49 3 100%
Checking over any unforeseen incidents 8/22 8/22 52 1 80%
Making of payments 8/23 8/23 53 1 60%
Signing off the project 8/23 8/23 53 1 0%
TASK NAME START ON
DAY*
PERCENT
COMPLETE
DURATION*
(WORK DAYS)
END DATESTART DATE
WEEK 8WEEK 1
0 10 20 30 40 50 60
Construction Permit for Renovation
Deciding the Contractor and Builders
Deciding the budget
Measuring Size of the basement and lighting
Deciding the wiring plans
Heating and Air Condition Systems and Wi-Fi Signals
Deciding the Technical Equipment, playing equipment and colors
Delivery of the equipment
Checking the equipment
Checking over the designed equipment
Checking over any unforeseen incidents
Making of payments
Signing off the project
DAYS OF THE PROJECT
(Figure 2: Simple Renovation – Basement Play and Theatre Room)
(Source: Created by author)
Inspection or Occular of the house
Construction Permit for Renovation 7/1 7/3 0 3 100%
Deciding the Contractor and Builders 7/4 7-8 3 5 80%
Deciding the budget 7/9 7/10 8 2 60%
Measuring Size of the basement and lighting 7/11 7/12 10 2 40%
Start of Construction of the House
Deciding the wiring plans 7/15 7/25 14 11 100%
Heating and Air Condition Systems and Wi-Fi Signals 7/26 7/31 25 6 80%
Deciding the Technical Equipment, playing
equipment and colors 8/1 8/9 31 9 60%
Delivery of the equipment and checking them
Delivery of the equipment 8/12 8/14 42 3 100%
Checking the equipment 8/15 8/16 45 2 80%
Inspection by Sponsor or Home Owner
Checking over the designed equipment 8/19 8/21 49 3 100%
Checking over any unforeseen incidents 8/22 8/22 52 1 80%
Making of payments 8/23 8/23 53 1 60%
Signing off the project 8/23 8/23 53 1 0%
TASK NAME START ON
DAY*
PERCENT
COMPLETE
DURATION*
(WORK DAYS)
END DATESTART DATE
WEEK 8WEEK 1
0 10 20 30 40 50 60
Construction Permit for Renovation
Deciding the Contractor and Builders
Deciding the budget
Measuring Size of the basement and lighting
Deciding the wiring plans
Heating and Air Condition Systems and Wi-Fi Signals
Deciding the Technical Equipment, playing equipment and colors
Delivery of the equipment
Checking the equipment
Checking over the designed equipment
Checking over any unforeseen incidents
Making of payments
Signing off the project
DAYS OF THE PROJECT
(Figure 2: Simple Renovation – Basement Play and Theatre Room)
(Source: Created by author)
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6CONCEPTS OF PROJECT MANAGEMENT AND PLANNING
References
Kuhrmann, M., Diebold, P., Münch, J., Tell, P., Garousi, V., Felderer, M., ... & Prause, C. R.
(2017, July). Hybrid software and system development in practice: waterfall, scrum, and
beyond. In Proceedings of the 2017 International Conference on Software and System
Process (pp. 30-39). ACM.
Machado, T. C. S., Pinheiro, P. R., & Tamanini, I. (2015). Project management aided by verbal
decision analysis approaches: a case study for the selection of the best SCRUM
practices. International Transactions in Operational Research, 22(2), 287-312.
Pheng, L. S., & Meng, C. Y. (2018). Managing productivity in construction: JIT operations and
measurements. Routledge.
Tomek, R., & Kalinichuk, S. (2015). Agile PM and BIM: A hybrid scheduling approach for a
technological construction project. Procedia Engineering, 123, 557-564.
References
Kuhrmann, M., Diebold, P., Münch, J., Tell, P., Garousi, V., Felderer, M., ... & Prause, C. R.
(2017, July). Hybrid software and system development in practice: waterfall, scrum, and
beyond. In Proceedings of the 2017 International Conference on Software and System
Process (pp. 30-39). ACM.
Machado, T. C. S., Pinheiro, P. R., & Tamanini, I. (2015). Project management aided by verbal
decision analysis approaches: a case study for the selection of the best SCRUM
practices. International Transactions in Operational Research, 22(2), 287-312.
Pheng, L. S., & Meng, C. Y. (2018). Managing productivity in construction: JIT operations and
measurements. Routledge.
Tomek, R., & Kalinichuk, S. (2015). Agile PM and BIM: A hybrid scheduling approach for a
technological construction project. Procedia Engineering, 123, 557-564.
1 out of 7
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2026 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.