This project management assignment, undertaken by students, delves into the core principles and practices of project management, using a case study of APIC Construction Pvt. Ltd. The assignment begins with the creation of a project charter, outlining project objectives, budgetary information, and timescales. It then proceeds to develop a detailed work breakdown structure (WBS) to organize project tasks. A crucial aspect of the assignment involves establishing initial cost estimations, considering resource allocation, material costs, and potential penalties for contractors due to delays. The project's timeline, including start and finish dates for various tasks, is meticulously documented. The project also addresses the approach adopted by SMART Construction, the stakeholders involved, and the resources utilized. The assignment also includes references to relevant literature in the field, providing a comprehensive overview of project management concepts.
Document Page
Running head: PROJECT MANAGEMENT FUNDAMENTALS AND PRACTICES
Project management fundamentals and practices
APIC Constrction Pvt. Ltd.
PART-A
Names:
1) Adil vahora - 201700508
2) Puneet singh virk – 201502424
3) Sagar Gumber - 201502710
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
PROJECT MANAGEMENT FUNDAMENTALS AND PRACTICES
Table of Contents
Unit Project A...............................................................................................................................................................................................................3
1. Project Charter..........................................................................................................................................................................................................3
Objectives.................................................................................................................................................................................................................3
Budgetary information..............................................................................................................................................................................................3
Timescales................................................................................................................................................................................................................5
Approach...................................................................................................................................................................................................................8
Stakeholder and Resources.......................................................................................................................................................................................8
2. Work Breakdown Structure....................................................................................................................................................................................10
3. Establishing Initial Cost Estimation.......................................................................................................................................................................10
Resource Stakeholder Cost.....................................................................................................................................................................................10
Resource Materials Costs.......................................................................................................................................................................................11
Fine for Contractor.................................................................................................................................................................................................12
Total Project Cost...................................................................................................................................................................................................12
References..................................................................................................................................................................................................................14
Document Page
PROJECT MANAGEMENT FUNDAMENTALS AND PRACTICES
Unit Project A
1. Project Charter
Sponsor: Mr Bob Smithes (CEO of SMART Construction)
Project Name: Project Management based on case study of QAHE
Prepared By: Project Manager of SMART Construction Date
: 23/03/2018
Objectives
ï‚· To construct a high quality luxurious construction building for Asia pacific International College (APIC) based in Sydney
ï‚· To complete the building within 268 days
ï‚· To construct a building which will have car parks, storage rooms and the building facilities rooms
Budgetary information
Task Name Resource Names % Complete Cost
APIC Construction Project 4% $837,752.00
Approval 0% $11,200.00
Draft Proposal Department Manager 0% $1,200.00
Submit Proposal Project Manager,Construction Project managers[1] 0% $4,900.00
Final Details Project Manager,Construction Project managers[1] 0% $5,100.00
Milestone 1: Completion of Approval 0% $0.00
Foundations 4% $269,488.00
Level Ground Cement[1],Flooring Materials[1],Labourer 4% $47,160.00
Dig Trenches Labourer,Plumbing Material[1],Labour[1] 4% $47,880.00
Sewage Connections Plumber,Plumbing Material[1] 5% $19,800.00
Electrical (to mains) Electrician,Electrical Equipment[1] 3% $17,880.00
Document Page
PROJECT MANAGEMENT FUNDAMENTALS AND PRACTICES
Gas (to mains) Skilled Labourer,Plumbing Material[1] 3% $18,168.00
Pour Concrete Slabs Labourer,Cement[1],Concrete Rods[1],Labour[1] 3% $72,160.00
Brick Foundations Labourer,Bricks[1],Labour[1] 3% $46,440.00
Walls + Roof 4% $85,800.00
Brick walls Labourer[200%],Bricks[1] 7% $18,600.00
Wooden rafters Labourer,Woods[1] 8% $15,720.00
Windows preparation Labourer[200%],Glass Windows[1] 3% $17,880.00
Lay roof tiles Labourer,Labour[1] 2% $33,600.00
Milestone 2: Completion of constructing walls and
roofs 0% $0.00
Interiors (needs roof) 5% $124,680.00
Electrical wiring Electrician,Electrical Equipment[1] 7% $17,240.00
Pipes and Plumbing Plumber,Plumbing Material[1] 5% $17,240.00
Doors Carpenter,Paint[1],Woods[1] 5% $31,152.00
Windows installation Skilled Labourer,Glass Windows[1] 4% $16,408.00
Floor Boards Skilled Labourer,Flooring Materials[1],Woods[1] 4% $42,640.00
Milestone 3: Completion of Interiors Design 0% $0.00
Bathroom and Kitchen 3% $250,024.00
Walls Labourer,Bricks[1] 3% $16,440.00
Bathroom fitting Skilled Labourer,Plumber,Plumbing Material[1],Labour[1] 3% $48,360.00
Bathroom tiling Skilled Labourer,Cement[1],Labour[1] 5% $51,760.00
Bathroom flooring Skilled Labourer,Flooring Materials[1] 4% $27,640.00
Kitchen fitting Skilled Labourer,Plumber,Plumbing Material[1],Labour[1] 3% $48,360.00
Kitchen slate flooring Skilled Labourer,Flooring Materials[1],Labour[1] 2% $57,464.00
Milestone 4: Completion of Bathrooms and Kitchen 0% $0.00
Finish 5% $96,560.00
Plasterboard walls Skilled Labourer,Labour[1],Woods[1] 5% $46,760.00
Painting Skilled Labourer,Carpenter,Paint[1],Labour[1] 5% $49,800.00
Milestone 5: Project Closure 0% $0.00
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
PROJECT MANAGEMENT FUNDAMENTALS AND PRACTICES
Timescales
Task Name Duration Start Finish
APIC Construction Project 385.5 days Thu 22-03-18 Thu 11-04-19
Approval 14 days Thu 22-03-18 Wed 04-04-18
Draft Proposal 5 days Thu 22-03-18 Wed 28-03-18
Submit Proposal 2 days Thu 29-03-18 Fri 30-03-18
Final Details 3 days Mon 02-04-18 Wed 04-04-18
Milestone 1: Completion of Approval 0 days Wed 04-04-18 Wed 04-04-18
Foundations 126 days Thu 05-04-18 Wed 08-08-18
Level Ground 15 days Thu 05-04-18 Wed 25-04-18
Dig Trenches 20 days Thu 26-04-18 Wed 23-05-18
Sewage Connections 30 days Thu 24-05-18 Wed 04-07-18
Electrical (to mains) 18 days Thu 24-05-18 Mon 18-06-18
Gas (to mains) 18 days Thu 24-05-18 Mon 18-06-18
Pour Concrete Slabs 15 days Thu 05-07-18 Wed 25-07-18
Brick Foundations 10 days Thu 26-07-18 Wed 08-08-18
Walls + Roof 74.5 days Thu 09-08-18 Mon 22-10-18
Document Page
PROJECT MANAGEMENT FUNDAMENTALS AND PRACTICES
Brick walls 12.5 days Thu 09-08-18 Mon 27-08-18
Wooden rafters 5 days Mon 27-08-18 Mon 03-09-18
Windows preparation 10 days Mon 03-09-18 Mon 17-09-18
Lay roof tiles 25 days Mon 17-09-18 Mon 22-10-18
Milestone 2: Completion of constructing
walls and roofs 0 days Mon 22-10-18 Mon 22-10-18
Interiors (needs roof) 39 days Mon 22-10-18 Fri 30-11-18
Electrical wiring 14 days Mon 22-10-18 Fri 09-11-18
Pipes and Plumbing 14 days Mon 22-10-18 Fri 09-11-18
Doors 8 days Mon 22-10-18 Thu 01-11-18
Windows installation 8 days Mon 22-10-18 Thu 01-11-18
Floor Boards 15 days Fri 09-11-18 Fri 30-11-18
Milestone 3: Completion of Interiors Design 0 days Fri 30-11-18 Fri 30-11-18
Bathroom and Kitchen 97 days Fri 30-11-18 Thu 07-03-19
Walls 10 days Fri 30-11-18 Fri 14-12-18
Bathroom fitting 10 days Fri 14-12-18 Fri 28-12-18
Document Page
PROJECT MANAGEMENT FUNDAMENTALS AND PRACTICES
Bathroom tiling 10 days Fri 28-12-18 Fri 11-01-19
Bathroom flooring 15 days Fri 11-01-19 Fri 01-02-19
Kitchen fitting 10 days Fri 01-02-19 Fri 15-02-19
Kitchen slate flooring 14 days Fri 15-02-19 Thu 07-03-19
Milestone 4: Completion of Bathrooms and
Kitchen 0 days Thu 07-03-19 Thu 07-03-19
Finish 35 days Thu 07-03-19 Thu 11-04-19
Plasterboard walls 10 days Thu 07-03-19 Thu 21-03-19
Painting 15 days Thu 21-03-19 Thu 11-04-19
Milestone 5: Project Closure 0 days Thu 11-04-19 Thu 11-04-19
Approach
SMART Construction is a reliable construction company based in Sydney. They are known to provide high quality as well as luxury
construction buildings. SMART Construction recently signs a contract for erecting a building for APIC. The project is expected to complete
within 268 days. The building area will be 700 square meters and will have staff offices, administration and dean office. The basement will
include storage rooms, car parks, building facilities room. The ground level will have three meeting rooms, administration office and the reception
room. There will be staff rooms and dean room at the first level. The project manager of the project has engaged plumber, electrician, carpenter.
All these stakeholders will carry out the construction project. The resources that will be used in the project have also been defined in the resource
sheet along with the budget. The plumbing materials, glass windows, woods, cement, paint will be constructing the building for APIC.
Stakeholder and Resources
Resource Name Type Max. Units Std. Rate
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
PROJECT MANAGEMENT FUNDAMENTALS AND PRACTICES
Department Manager Work 100% $30.00/hr
Project Manager Work 100% $25.00/hr
Labourer Work 100% $18.00/hr
Plumber Work 100% $20.00/hr
Electrician Work 100% $20.00/hr
Skilled Labourer Work 100% $22.00/hr
Carpenter Work 100% $18.00/hr
Plumbing Material Material $15,000.00
Concrete Rods Material $20,000.00
Paint Material $15,000.00
Flooring Materials Material $25,000.00
Electrical Equipment Material $15,000.00
Glass Windows Material $15,000.00
Woods Material $15,000.00
Cement Material $20,000.00
Bricks Material $15,000.00
Document Page
PROJECT MANAGEMENT FUNDAMENTALS AND PRACTICES
Labour Material $30,000.00
Construction Project managers Material $4,500.00
Administration and Office Work and
Marketing Material $189,500.00
APPROVAL □ Yes │ □ No
______________________________ Date:____________
Sponsor
2. Work Breakdown Structure
Document Page
PROJECT MANAGEMENT FUNDAMENTALS AND PRACTICES
3. Establishing Initial Cost Estimation
Resource Stakeholder Cost
Resource Name Type Max. Units Std. Rate
Department Manager Work 100% $30.00/hr
Project Manager Work 100% $25.00/hr
Labourer Work 100% $18.00/hr
Plumber Work 100% $20.00/hr
Electrician Work 100% $20.00/hr
Skilled Labourer Work 100% $22.00/hr
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
PROJECT MANAGEMENT FUNDAMENTALS AND PRACTICES
Carpenter Work 100% $18.00/hr
Resource Materials Costs
Resource Name Type Max. Units Std. Rate
Plumbing Material Material $15,000.00
Concrete Rods Material $20,000.00
Paint Material $15,000.00
Flooring Materials Material $25,000.00
Electrical Equipment Material $15,000.00
Glass Windows Material $15,000.00
Woods Material $15,000.00
Cement Material $20,000.00
Bricks Material $15,000.00
Labour Material $30,000.00
Construction Project managers Material $4,500.00
Administration and Office Work and Marketing Material $189,500.00
Document Page
PROJECT MANAGEMENT FUNDAMENTALS AND PRACTICES
Fine for Contractor
The project was scheduled to complete within 268 days. However, the project will take 385.5 days to complete. The project will take
extra 117.5 days to complete. The contractor will have to pay fine for taking 117.5 days. He will have to pay AU$200 per day for the rest 117.5
days. He will have to pay overall AU$23500 as fine.
Total Project Cost
Task Name Duration % Complete Cost Actual Cost Baseline Cost % Cost
APIC Construction
Project 385.5 days 4% $837,752.00 $32,253.04 $837,752.00 0
Approval 14 days 0% $11,200.00 $0.00 $11,200.00 0
Draft Proposal 5 days 0% $1,200.00 $0.00 $1,200.00 0
Submit Proposal 2 days 0% $4,900.00 $0.00 $4,900.00 0
Final Details 3 days 0% $5,100.00 $0.00 $5,100.00 0
Foundations 126 days 4% $269,488.00 $9,431.04 $269,488.00 25
Level Ground 15 days 4% $47,160.00 $1,886.40 $47,160.00 4
Dig Trenches 20 days 4% $47,880.00 $1,915.20 $47,880.00 4
Sewage Connections 30 days 5% $19,800.00 $990.00 $19,800.00 5
Electrical (to mains) 18 days 3% $17,880.00 $536.40 $17,880.00 3
Gas (to mains) 18 days 3% $18,168.00 $545.04 $18,168.00 3
Pour Concrete Slabs 15 days 3% $72,160.00 $2,164.80 $72,160.00 3
Brick Foundations 10 days 3% $46,440.00 $1,393.20 $46,440.00 3
Walls + Roof 74.5 days 4% $85,800.00 $3,768.00 $85,800.00 20
Brick walls 12.5 days 7% $18,600.00 $1,302.00 $18,600.00 7
Wooden rafters 5 days 8% $15,720.00 $1,257.60 $15,720.00 8
Windows preparation 10 days 3% $17,880.00 $536.40 $17,880.00 3
Lay roof tiles 25 days 2% $33,600.00 $672.00 $33,600.00 2
Interiors (needs roof) 39 days 5% $124,680.00 $5,988.32 $124,680.00 25
Electrical wiring 14 days 7% $17,240.00 $1,206.80 $17,240.00 7