This report details a project management consultancy case study focusing on the launch of Tesla Motors' Powerwall 2.0 home battery. It covers defining project outcomes and purposes, establishing SMART objectives, specifying project scope (including inclusions and exclusions), cost estimation and budgeting (£150,000 total budget), project scheduling using a Gantt chart and network diagram, stakeholder analysis via a RACI chart, assessment of procurement strategies, and a critical analysis of uncertainties and risks using a risk register. The report also includes a reflective section discussing the challenges faced during the assignment and the skills and knowledge gained, such as improved research skills, understanding of project scope and SMART objectives, and proficiency in using MS Project and Excel for planning and budgeting.
Document Page
Project Management Consultancy Report
1
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Table of Contents
INTRODUCTION................................................................................................................................3
SECTION 1..........................................................................................................................................3
1. Defining the project in terms of outcomes and purposes.............................................................3
2. Project SMART objectives..........................................................................................................4
3 Specifying the project scope.........................................................................................................4
4. Cost estimation for the project budget.........................................................................................5
5. Clarifying project scheduling.......................................................................................................6
6. Gantt chart, breakdown of all activities, network diagram with critical path and key milestones
.........................................................................................................................................................7
7. Critical analysis of the project stakeholders i.e. Project Stakeholder Analysis.........................12
8. Assessment of project procurement strategies...........................................................................12
9. Critical analysis the uncertainties that may affect the project objectives by creating a risk
register...........................................................................................................................................13
SECTION 2........................................................................................................................................15
CONCLUSION..................................................................................................................................17
REFERENCES...................................................................................................................................18
2
Document Page
INTRODUCTION
Project Management can be considered as an art to manage the project and its outcomes with
a view to produce finished service or product. Without any significant approach of managing
project and achieve set objectives, it is hard for a company to successfully implement the plan with
the various constraints such as time, quality, scope, budget etc (Adak and Yumuşak, 2013). In
simple word, it can be said that there should be a framework and defined way to perform a work
and ensure that the plan work can be effectively manage and deliver the expected outcomes. So,
project management is about creating structure and managing the project to convey agreed results.
There are several reasons which promotes the usefulness of project management are organizing
chaos, managing risks, quality management, learn from mistakes, managing changes etc. The
present consultancy report is based on project management to understand its importance;
ProjectPlus Case Study is taking into the consideration (Burke, 2013). It is a small influential
advisory firm that specialises in project and programme management consultancy. It is particularly
strong in implementing the processes and systems for Project Planning, Risk Management, Project
Reporting and Benefits Realisation. Recently, firm has signed with new clients: Tesla Motors
(automotive), GE Healthcare (healthcare), and DropBox (could technology). These three companies
want that ProjectPlus help them in launching of their new product and service.
SECTION 1
1. Defining the project in terms of outcomes and purposes
As per the given case of ProjectPlus, it has identified that firm has signed with the three new
clients. There are Tesla Motors (automotive), GE Healthcare (healthcare), and DropBox (could
technology) and they have developed their new service and product and want the help of company
to launch them in the market (Gemünden, Huemann and Martinsuo, 2013). One of the projects
chosen by consultant is Tesla Motors new second generation product i.e. Tesla home battery:
POWERWALL 2.0. Project purpose is the reason why a venture establishes a project. It defines the
mission of that project and helps in understand about the viability of a plan. The purpose of
launching of the following project is to communicate the customers about new second generation
battery which transform solar energy into electricity and powers to home utilities in the evening
(Kerzner, 2013). This is the one of the stronger step of organization in the direction of energy
storage battery. There are some features and characteristics of POWERWALL 2.0 battery which will
be deliver to the attendees at the time of launching of products. These are as follows:
Simplification to the handling and wiring requirements for installers,
3
Document Page
Compactable with inverters,
Store more than 6.4 kWh worth of energy and its backup provide electric energy to homes.
Meet the large energy needs which reduce the dependence on the power grid all the time
(Colin and Vanhoucke, 2014),
Based on ecosystem energy concept that brings the reduction in the cost of electric energy
bill of people,
Easily compatible with single and three phase utility grid compatible,
Low pricing and require less space to install in home (Gyawali, Tao and Müller, 2013),
Also compactable for businesses, institutes etc,
Rechargeable battery option more alluring to homeowners.
Therefore, the above stated points will be the purpose of POWERWALL 2.0 product launch.
These will satisfy the needs of social and environment needs in the right manner (Hazır, 2015).
2. Project SMART objectives
By seen the above listed POWERWALL 2.0 product launch project purpose and outcomes, it
will require to develop some SMART objectives that will be fulfilled in order to complete the
following project (Flyvbjerg, 2013). All kind of businesses needed to define or set some objectives
to achieve the particular outcomes because it helps the firms to know what it is trying to achieve. In
the context of the product launch project, the reason of developing SMART objectives is it is clearly
know exactly what needs to be accomplished. Another motive behind adopting the following
concept to successfully complete the plan is it is easy to monitor the progress of associate project
plan time to time (Azimi and et.al., 2011). Along with this, it assists in identify the missing targets
and make necessary changes to achieve them. So, as per the need, list of SMART objectives in the
context of POWERWALL 2.0 product launch project is as follows:
For the company
Achieve a 90% Tesla Motors satisfaction rating for the launching of its new product project
by the end of October 2016.
To increase the market share from 30% to 60% by the end of launching project.
To raise the sales of project consultancy services from 25% to 40% by the end of October
2016.
For the project manager
Decrease the time from 10 minutes to 5 minutes to responses to client queries.
3 Specifying the project scope
According to given case of ProjectPlus, it has determined that Tesla Motor wants help of a
4
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
consultancy company to launch its product POWEWALL 2.0. The scope of this project is very wide
because it will meet all types of customers needs related to energy. Basically, project scope is the
part of project planning that involves determining and enlisting a list of particular goals, tasks,
deliverables, deadlines and costs (Lanata and et.al., 2015). At the time of developing scope for a
project, it contains three key components: boundaries, deliverables and requirements. In the context
of launching of POWERWALL 2.0 product project, a statement of project scope is as follows:
This project will deliver a new concept of storage of energy for the long time. The new
power storage battery equipment will transform solar energy into electrical energy that will be use
by the homeowners and other customers to lighten the houses, buildings, institute etc (Meredith and
Mantel Jr, 2011). This new concept will reduce the bill of energy and provide the facility of
integrate various equipments to new battery.
Apart from this, it is important to set some project boundaries because it is a key component
of project scope. It can be defined as it is a measurable and auditable characteristic that defines what
belongs to the project and what does not belong to it (Mubarak, 2015). Project boundaries are
closely linked to project objectives and create a holistic perception related to the plan. With the help
of this, it becomes easy to define the content of work in the terms of expected outcomes. So, a clear
project boundary statement assists in to direct the things which are applicable to those areas within
the scope of a project. In the context of launching project of POWERWALL 2.0 product of Tesla
Motor, project boundaries are as follows:
Project Includes: As per the set SAMRT objectives, some boundaries have determined that
needed to be considered are as follows:
Characteristics and features of product, project goals, key project phases and milestones,
roles and responsibilities of key project participants, stakeholder needs, client satisfaction level,
deliverables of project launch and scope creep (Müller and et.al., 2013).
Project Excludes: Some exclusions criteria for POWEWALL 2.0 project launch are as
follows:
This project will not include integration of other products of Tesla Motors to launch
on same day.
This project will not include other employees of Tesla Motors if they want to shift
launching of POWERWALL 2.0 product (Nicholas and Steyn, 2012).
4. Cost estimation for the project budget
Project budget is the total amount of authorized financial resources allocated for the specific
purpose of sponsoring project for a particular time period. Budgeting is an important part of the
5
Document Page
project planning process. The reason of determining or setting of budget is not to lose money at the
time of managing project (Svejvig and Andersen, 2015). At the time of cost estimation of a work, it
is essential to consider different expenses in to the budget.
As per the given case study, it has identified that Tesla Motors develop second generation
battery equipment and ready to launch in the market. For this purpose, company contract to the
ProjectPlus organization in order to launching of new brand. The total available budget for this
product launch project is £150,000 (Pritchard, 2013). So, cost estimation for the overall work is as
follows:
Particulars Cost in £
Human resources
Consultant 1 2000
Consultant 2 2000
Consultant 3 2000
Consultant 4 2000
Consultant 5 2000
Consultant 6 2000
Booking of venue 10000
Giving ads in various source of information 3000
Live broadcasting over the internet 50000
Booking catering 5000
Event execution logistic requirements such as registration, crowd control, health
and safety etc. 6000
Promotion of event 3000
Arranging sound and lighting facilities 6000
Transportation of staff 4000
Invitation to the VIP guests 1000
Miscellaneous expenses 20000
ProjectPlus service fee 30000
Total 150,000
5. Clarifying project scheduling
Project scheduling is the tool which communicates what work needed to be performed,
which kind of resources of the organization will execute the task and timeframe in which that
6
Document Page
activities needs to be performed. Without proper scheduling of a work, it is difficult to complete the
project within the given time period (Svejvig and Andersen, 2015). Effective project scheduling
plays a crucial role in ensuring the success of project. With the help of it, it becomes easy for the
project manager to update status of the work. Along with this, it helps in estimating start and finish
dates. In the context of the POWERWALL 2.0 product launch project scheduling is as follows:
Task Name Duration Start Finish
POWEWALL 2.0 product launch
project 31 days Mon 8/1/16 Mon 9/12/16
Planning 13 days Mon 8/1/16 Wed 8/17/16
Market research 3 days Mon 8/1/16 Wed 8/3/16
Identify the needs of clients 3 days Thu 8/4/16 Mon 8/8/16
Looking for vendors 4 days Tue 8/9/16 Fri 8/12/16
Prepare team 3 days Mon 8/15/16 Wed 8/17/16
Execution 7 days Mon 8/15/16 Tue 8/23/16
Prepare product launch plan 5 days Mon 8/15/16 Fri 8/19/16
Booking venue 3 days Thu 8/18/16 Mon 8/22/16
Selection of vendor 1 day Mon 8/22/16 Mon 8/22/16
Communicate progress to the
client 1 day Tue 8/23/16 Tue 8/23/16
Monitoring 9 days Wed 8/24/16 Mon 9/5/16
Managing contractual relationship
with suppliers 1 day Wed 8/24/16 Wed 8/24/16
Review project plan 5 days Thu 8/25/16 Wed 8/31/16
Make corrective actions 3 days Thu 9/1/16 Mon 9/5/16
Project closure 5 days Tue 9/6/16 Mon 9/12/16
Taking feedback from client 2 days Tue 9/6/16 Wed 9/7/16
Closing of contracts 2 days Thu 9/8/16 Fri 9/9/16
Project Launching 1 day Mon 9/12/16 Mon 9/12/16
6. Gantt chart, breakdown of all activities, network diagram with critical path and key milestones
Project plan:
7
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Task Name Duration Start Finish Predecessors
POWEWALL 2.0 product
launch project 31 days Mon 8/1/16 Mon 9/12/16
Planning 13 days Mon 8/1/16 Wed 8/17/16
Market research 3 days Mon 8/1/16 Wed 8/3/16
Identify the needs of
clients 3 days Thu 8/4/16 Mon 8/8/16 3
Looking for vendors 4 days Tue 8/9/16 Fri 8/12/16 4
Prepare team 3 days Mon 8/15/16 Wed 8/17/16 5
Execution 7 days Mon 8/15/16 Tue 8/23/16
Prepare product launch
plan 5 days Mon 8/15/16 Fri 8/19/16 5
Booking venue 3 days Thu 8/18/16 Mon 8/22/16 6
Selection of vendor 1 day Mon 8/22/16 Mon 8/22/16 8
Communicate progress to
the client 1 day Tue 8/23/16 Tue 8/23/16 9
Monitoring 9 days Wed 8/24/16 Mon 9/5/16
Managing contractual
relationship with suppliers 1 day Wed 8/24/16 Wed 8/24/16 10,11
Review project plan 5 days Thu 8/25/16 Wed 8/31/16 13
Make corrective actions 3 days Thu 9/1/16 Mon 9/5/16 14
Project closure 5 days Tue 9/6/16 Mon 9/12/16
Taking feedback from
client 2 days Tue 9/6/16 Wed 9/7/16 15
Closing of contracts 2 days Thu 9/8/16 Fri 9/9/16 17
Project Launching 1 day Mon 9/12/16 Mon 9/12/16 18
Work Breakdown
8
Document Page
Key milestones:
Key milestones Expected date of completion
Planning Wed 8/17/16
Execution Tue 8/23/16
Monitoring Mon 9/5/16
Project closure Mon 9/12/16
Gantt chart:
9
Document Page
10
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Critical path
11
Document Page
7. Critical analysis of the project stakeholders i.e. Project Stakeholder Analysis
In the context of launching of POWEWALL 2.0 project, it is important to identify the roles
and responsibilities of key stakeholders to ensure successful project completion. For this, RACI
chart is as follows:
Task Projec
t
Manag
er
Consul
tant 1
Consul
tant 2
Consu
ltant 3
Cons
ultan
t 4
Cons
ultan
t 5
Co
nsu
ltan
t 6
Market research A R I I I
Identify the needs of clients A R
Looking for vendors A,R C C C C
Prepare product launch plan I I I C A,R
Booking venue A C R C I
Selection of vendor A R C C I
Communicate progress to the
client
I I C A R
Managing contractual
relationship with suppliers
I A,R
Review project plan A I R C
Make corrective actions I A R
Taking feedback from client A R I
Closing of contracts A R
Project Launching A,R C C C C
8. Assessment of project procurement strategies