Project Management: Critical Path Analysis and Speeding Activities
VerifiedAdded on 2022/08/25
|2
|401
|16
Project
AI Summary
This project management assignment solution analyzes a project's critical path, calculating the shortest possible time for completion. The solution identifies the critical path, which is A-G, and determines the project's variance and standard deviation. It calculates the probability of completing the project in 24 days using the z-score. Furthermore, the assignment explores the impact of speeding up activities B and E, examining the resulting changes in path durations and associated costs. The analysis concludes that speeding up activities B or E does not affect the critical path, so focusing on speeding up activities A or G is more effective.
1 out of 2