This project management assignment focuses on the implementation of a data warehouse and smart reporting system for the Abu Dhabi Food Control Authority. The assignment begins with a project business case, outlining the need for a system to manage extensive data and generate smart reports for decision-making. It details the project selection criteria, with payback period identified as the most suitable method. The project objectives include implementing a data warehouse within a specified timeframe and budget, and the goals involve integrating and preserving key information across the organization. The assignment further defines the project scope, requirements, and a detailed work breakdown structure (WBS), covering project initiation, planning, design, execution, testing, and closure phases. The WBS includes tasks such as problem identification, scope statement development, resource identification, risk and quality management, and system testing. The assignment emphasizes the use of Agile project development lifecycle and Oracle database connectivity for efficient data management and reporting.

Running head: PROJECT MANAGEMENT
Project Management: Implementation of Data Warehouse in Abu Dhabi food control Authority
Name of the student:
Name o the University:
Project Management: Implementation of Data Warehouse in Abu Dhabi food control Authority
Name of the student:
Name o the University:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

1PROJECT MANAGEMENT
Assignment 1
Selected project: Extensive data available in Abu Dhabi Food Control Authority, and
how these data can be used to classify these data into smart reports that help in decision-making,
prioritizing and shaping the future emirates of Abu Dhabi in food safety and food security.
1.1 Project business case
The purpose of the project is to implement smart business system software as well as data
warehouse in terms of Information System to protect confidential information. The system help
Abu Dhabi food control Authority to build a data warehouse which include all information and
needful data. It can integrate, enhance and preserve the key accurate information across the
business organization. It also helps to provide a common data model for all types of data which
count regardless of the data sources and can add on values for business operation and all other
applications. In order to store the information Oracle database connectivity will be used to fetch,
insert and update key data in the database table. Oracle ERP system will be used to access
information stored in the database by running needful queries.
The Minister of State for Food Security released a roadmap for excellence technical
innovation driven food security in the Middle East. In order to improve the food security
performance the Abu Dhabi food control Authority has introduced certain tools and strategic
initiatives. The United Arab Emirates is bidding frequently to become world’s one of the top 10
food secure nations. It is determined that, extensive data are available in Abu Dhabi Food
Control Authority. Based on type and size, theses data can be classified and used in smart reports
so that the authority can take effective decisions for economic and commercial success.
Assignment 1
Selected project: Extensive data available in Abu Dhabi Food Control Authority, and
how these data can be used to classify these data into smart reports that help in decision-making,
prioritizing and shaping the future emirates of Abu Dhabi in food safety and food security.
1.1 Project business case
The purpose of the project is to implement smart business system software as well as data
warehouse in terms of Information System to protect confidential information. The system help
Abu Dhabi food control Authority to build a data warehouse which include all information and
needful data. It can integrate, enhance and preserve the key accurate information across the
business organization. It also helps to provide a common data model for all types of data which
count regardless of the data sources and can add on values for business operation and all other
applications. In order to store the information Oracle database connectivity will be used to fetch,
insert and update key data in the database table. Oracle ERP system will be used to access
information stored in the database by running needful queries.
The Minister of State for Food Security released a roadmap for excellence technical
innovation driven food security in the Middle East. In order to improve the food security
performance the Abu Dhabi food control Authority has introduced certain tools and strategic
initiatives. The United Arab Emirates is bidding frequently to become world’s one of the top 10
food secure nations. It is determined that, extensive data are available in Abu Dhabi Food
Control Authority. Based on type and size, theses data can be classified and used in smart reports
so that the authority can take effective decisions for economic and commercial success.

2PROJECT MANAGEMENT
Discrete data are available in the Abu Dhabi Food control Authority. However, managing
large set of data has become a major challenge to the Abu Dhabi Food Control Authority. In
order to resolve this issue the food corporation authority has decided to design and develop an
Information System (IS) and data warehouse. It is identified that implementation of an
Information System and data warehouse will easily resolve all operational and functional
challenges. The Information System and data warehouse or smart reporting system will help the
authority to take effective decisions.
The project roadmap is dependent on some strong pillars such as building as well as food
data strategies, developing professional Research and Development (R&D) Strategies, nutritional
guidelines, regional trading environment and national food waste program that support regional
improvement in the improvement portfolio. The Food Control Authority was established in the
year of 2005 to make sure customer care with quality food delivery. In the year of 2009 the
Farmer’s service centre was established that offer technical agricultural services and technical
advice to the farmers.
1.2 Project selection criteria
This is not mandatory that every project will be successful in any business organization.
In order to implement any project successfully in the business organization it is mandatory for
the project manager and project team members to identify the possible project selection criteria.
Therefore, before selecting any project most of the project leaders consider all contingency that
may come up and use as a yardstick to select the project. The project sponsors are also needed to
get permission from the project manager before selecting the most suitable project for its
competitive advantages and commercial profit. The different project selection methods applied in
this project are as follows:
Discrete data are available in the Abu Dhabi Food control Authority. However, managing
large set of data has become a major challenge to the Abu Dhabi Food Control Authority. In
order to resolve this issue the food corporation authority has decided to design and develop an
Information System (IS) and data warehouse. It is identified that implementation of an
Information System and data warehouse will easily resolve all operational and functional
challenges. The Information System and data warehouse or smart reporting system will help the
authority to take effective decisions.
The project roadmap is dependent on some strong pillars such as building as well as food
data strategies, developing professional Research and Development (R&D) Strategies, nutritional
guidelines, regional trading environment and national food waste program that support regional
improvement in the improvement portfolio. The Food Control Authority was established in the
year of 2005 to make sure customer care with quality food delivery. In the year of 2009 the
Farmer’s service centre was established that offer technical agricultural services and technical
advice to the farmers.
1.2 Project selection criteria
This is not mandatory that every project will be successful in any business organization.
In order to implement any project successfully in the business organization it is mandatory for
the project manager and project team members to identify the possible project selection criteria.
Therefore, before selecting any project most of the project leaders consider all contingency that
may come up and use as a yardstick to select the project. The project sponsors are also needed to
get permission from the project manager before selecting the most suitable project for its
competitive advantages and commercial profit. The different project selection methods applied in
this project are as follows:

3PROJECT MANAGEMENT
Cost benefit ratio: This method calculates the ratio of project investment and expected
benefit from the project. It is an effective way of communication that provides easily understable
terms to the project manager and project team members. It calculates the investment done for any
project and the net return value that may generate from the complete investment. A project that
needs $50,000 as their resource allocation cost must complete with an expected return value of
$100,000 after a certain time period.
Economic model: The economic model is referred to as a very simple benefit
measurement model which describes the difference between the invested cost and the possible
revenue generated from it. It gives a cleat representation on quantifiable benefit of a project as
soon as it completed. In other words it gives solid return that is actually expected from a project.
Payback period: The payback period is referred to as measurement technique which
calculates the time that would be required to get the invested value as a return.
Discounted cash flow: The discounted cash flow is referred to as a value that calculates a
return value may be generated after a certain point of time period. The concept helps the project
managers to translate the future earning into present days.
Net present value: The net present value helps to put the entire project development
lifecycle into project earning perspectives.
Among the above mentioned project selection criteria the project manager and project
team members for this project is require to choose the most suitable project select method. For
this project, payback Period is referred to as the most suitable project selection method. The
Cost benefit ratio: This method calculates the ratio of project investment and expected
benefit from the project. It is an effective way of communication that provides easily understable
terms to the project manager and project team members. It calculates the investment done for any
project and the net return value that may generate from the complete investment. A project that
needs $50,000 as their resource allocation cost must complete with an expected return value of
$100,000 after a certain time period.
Economic model: The economic model is referred to as a very simple benefit
measurement model which describes the difference between the invested cost and the possible
revenue generated from it. It gives a cleat representation on quantifiable benefit of a project as
soon as it completed. In other words it gives solid return that is actually expected from a project.
Payback period: The payback period is referred to as measurement technique which
calculates the time that would be required to get the invested value as a return.
Discounted cash flow: The discounted cash flow is referred to as a value that calculates a
return value may be generated after a certain point of time period. The concept helps the project
managers to translate the future earning into present days.
Net present value: The net present value helps to put the entire project development
lifecycle into project earning perspectives.
Among the above mentioned project selection criteria the project manager and project
team members for this project is require to choose the most suitable project select method. For
this project, payback Period is referred to as the most suitable project selection method. The
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

4PROJECT MANAGEMENT
1.3 Project objectives
The objectives for the project are as follows:
To implement a data warehouse and smart business system in terms of
Information System (IS)
To discuss all the extensive data available in all sectors in Abu Dhabi Food
Control Authority and also identify how those data be used for smart reporting
system
To accomplish the IS implementation and data warehouse design and
development project within estimated timeframe of 125 days and within the
estimated budget of $65,000
1.4 Goals
Abu Dhabi Food Control Authority is facing major challenges due to availability of huge
discrete data in different sectors. Managing these data is becoming very much challenging these
days. The goal of the project is to build data warehouse which include each type of discrete data
and needful information. It has been assumed that, if the data warehouse is successfully
implemented then it would be able to integrate, increase and preserve all key accurate
information across Abu Dhabi Food Control Authority. The warehouse can merge all data from
multiple sources and successfully provide a common data source and add values for effective
operational business applications. The data warehouse can restructure all information that
provides excellent query tools even for complex analytic queries without giving any negative
impact to the Operating System (OS). Deactivated Operating System can also keep the data
history stored.
1.3 Project objectives
The objectives for the project are as follows:
To implement a data warehouse and smart business system in terms of
Information System (IS)
To discuss all the extensive data available in all sectors in Abu Dhabi Food
Control Authority and also identify how those data be used for smart reporting
system
To accomplish the IS implementation and data warehouse design and
development project within estimated timeframe of 125 days and within the
estimated budget of $65,000
1.4 Goals
Abu Dhabi Food Control Authority is facing major challenges due to availability of huge
discrete data in different sectors. Managing these data is becoming very much challenging these
days. The goal of the project is to build data warehouse which include each type of discrete data
and needful information. It has been assumed that, if the data warehouse is successfully
implemented then it would be able to integrate, increase and preserve all key accurate
information across Abu Dhabi Food Control Authority. The warehouse can merge all data from
multiple sources and successfully provide a common data source and add values for effective
operational business applications. The data warehouse can restructure all information that
provides excellent query tools even for complex analytic queries without giving any negative
impact to the Operating System (OS). Deactivated Operating System can also keep the data
history stored.

5PROJECT MANAGEMENT
The goal of the project is to identify the ways through which discrete data available in
different sectors can be used by the Abu Dhabi Food Control Authority into smart reporting. The
smart reporting system needs to be designed in such a way so that it can take effective business
beneficial decisions and prioritization and future shaping. In order to develop the manual
reporting system to a smart one the Abu Dhabi Food Control Authority require to implement
Information System and data warehouse for food security, safety and quality improvement.
1.5 Requirements
After analyzing the business case in details data warehouse or a business Intelligence can
be developed for successful programs. The data warehouse can be developed successfully on
solid business requirements. It helps to demonstrate the solution requirements in business terms.
Some steps are there required to be followed by the project managers of Abu Dhabi Food
Control Authority while developing data house system. The detail steps are as follows:
Determining the business objectives
Collecting and analyzing Information details
Identification of core business processes
Construction of conceptual data model
Locating data sources and planning for data transformation
Set tracking duration
Implementation of the plan
1.6 Preliminary project scope
Data warehousing business requirement demonstrate the needed solution in the business
terms. It helps to gather and manage all business requirements that include the following steps-
The goal of the project is to identify the ways through which discrete data available in
different sectors can be used by the Abu Dhabi Food Control Authority into smart reporting. The
smart reporting system needs to be designed in such a way so that it can take effective business
beneficial decisions and prioritization and future shaping. In order to develop the manual
reporting system to a smart one the Abu Dhabi Food Control Authority require to implement
Information System and data warehouse for food security, safety and quality improvement.
1.5 Requirements
After analyzing the business case in details data warehouse or a business Intelligence can
be developed for successful programs. The data warehouse can be developed successfully on
solid business requirements. It helps to demonstrate the solution requirements in business terms.
Some steps are there required to be followed by the project managers of Abu Dhabi Food
Control Authority while developing data house system. The detail steps are as follows:
Determining the business objectives
Collecting and analyzing Information details
Identification of core business processes
Construction of conceptual data model
Locating data sources and planning for data transformation
Set tracking duration
Implementation of the plan
1.6 Preliminary project scope
Data warehousing business requirement demonstrate the needed solution in the business
terms. It helps to gather and manage all business requirements that include the following steps-

6PROJECT MANAGEMENT
business mission and operation, enterprise goals and objective setting, identification of user
groups, requirements interview, requirement workshops and sizing. The Rapid data warehouse
requirement can include increased productivity, improved solution quality, rapid resultant, longer
development cost and enhanced team work and productivity. The scope of the project is to
develop a data model with database layout, data strategy and roadmaps. The scope of the project
is to identify discrete data sources to gather needful information those are helpful for developing
smart reporting. The system will be used to merge multiple numbers of data from theses sources
to provide one common data model. The design data model can integrate, enhance and preserve
key accurate information throughout the organization. It has been assumed that with successful
design and development of a data warehouse the decision making process of Abu Dhabi Food
Control Authority will be improved and it can also successfully provide data quality analysis
report, dashboard and performance cards.
business mission and operation, enterprise goals and objective setting, identification of user
groups, requirements interview, requirement workshops and sizing. The Rapid data warehouse
requirement can include increased productivity, improved solution quality, rapid resultant, longer
development cost and enhanced team work and productivity. The scope of the project is to
develop a data model with database layout, data strategy and roadmaps. The scope of the project
is to identify discrete data sources to gather needful information those are helpful for developing
smart reporting. The system will be used to merge multiple numbers of data from theses sources
to provide one common data model. The design data model can integrate, enhance and preserve
key accurate information throughout the organization. It has been assumed that with successful
design and development of a data warehouse the decision making process of Abu Dhabi Food
Control Authority will be improved and it can also successfully provide data quality analysis
report, dashboard and performance cards.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT MANAGEMENT
1.7 Work breakdown structure
Scheduling smart
reporting system for Abu
Dhab Food Control
Authority
Project initiation
Identification of
problems in Abu
Dhabi Food Control
Authority
Developing project
scope statement
SRS
Resource
identification
Resource gathering
and analysis
Project planning
Feasibility analysis
Time/ schedule and
cost estimation
Risk and quality
management plan
Contingency and
procurement
management plan
Project design and
execution
Hardware and
software
specifications
UML diagram
presentation
ETL design and code
review
Naming standard
checking
Checking business
logic
Checking mapping
sources to target
System prototype
design
Oracle database
connectivity
Testing
Unit testing
Functionality testing
Performance and
user acceptance
testing
Project implementation
and closure phase
Post system
maintenance plan
Stakeholder’s
signoff
Figure 1: Work Breakdown Structure developed for the project
(Sources: Created by author)
1.7 Work breakdown structure
Scheduling smart
reporting system for Abu
Dhab Food Control
Authority
Project initiation
Identification of
problems in Abu
Dhabi Food Control
Authority
Developing project
scope statement
SRS
Resource
identification
Resource gathering
and analysis
Project planning
Feasibility analysis
Time/ schedule and
cost estimation
Risk and quality
management plan
Contingency and
procurement
management plan
Project design and
execution
Hardware and
software
specifications
UML diagram
presentation
ETL design and code
review
Naming standard
checking
Checking business
logic
Checking mapping
sources to target
System prototype
design
Oracle database
connectivity
Testing
Unit testing
Functionality testing
Performance and
user acceptance
testing
Project implementation
and closure phase
Post system
maintenance plan
Stakeholder’s
signoff
Figure 1: Work Breakdown Structure developed for the project
(Sources: Created by author)

8PROJECT MANAGEMENT
Assignment 2
2.1 Detail Work Breakdown Structure for the project
The Abu Dhabi Food Control Authority established a clear view to evaluate discrete data
those can be used in real field of application. In order to maintain the safety and quality of food,
UAE government body has started keeping their focus on each protection entities. The mission
of UAE is to achieve sustainability for effective improvement of each research activities.
Statistical database collection, research activities and government services are the sectors that are
improving continuously for long term agricultural sustainability and food safety. In order prepare
the database warehouse system/Oracle based ERP system Agile project development lifecycle
should be used by the system developers and project managers. The details of the Work
Breakdown Structure (WBS) and details work packages used are elaborated in the below section:
Project initiation: The project initiation plan stars with problem analysis, project scope
statement development and identification of resources. For this data house development project it
is identified that the Abu Dhabi Food control Authority used to apply manual data management.
Discrete data are available in different sectors of Abu Dhabi food. Though, application of these
data are very essential but due to lack of management and operational processes the Abu Dhabi
Food control Authority failed to use these data while required. After identification f this
problem, the project scope statement is designed. In order to implement the project scope
considering its goals and objectives it becomes necessary for the assigned project manager to
identify and analyze resources in this phase. Basically this project phase initiates the data
warehouse development project.
Assignment 2
2.1 Detail Work Breakdown Structure for the project
The Abu Dhabi Food Control Authority established a clear view to evaluate discrete data
those can be used in real field of application. In order to maintain the safety and quality of food,
UAE government body has started keeping their focus on each protection entities. The mission
of UAE is to achieve sustainability for effective improvement of each research activities.
Statistical database collection, research activities and government services are the sectors that are
improving continuously for long term agricultural sustainability and food safety. In order prepare
the database warehouse system/Oracle based ERP system Agile project development lifecycle
should be used by the system developers and project managers. The details of the Work
Breakdown Structure (WBS) and details work packages used are elaborated in the below section:
Project initiation: The project initiation plan stars with problem analysis, project scope
statement development and identification of resources. For this data house development project it
is identified that the Abu Dhabi Food control Authority used to apply manual data management.
Discrete data are available in different sectors of Abu Dhabi food. Though, application of these
data are very essential but due to lack of management and operational processes the Abu Dhabi
Food control Authority failed to use these data while required. After identification f this
problem, the project scope statement is designed. In order to implement the project scope
considering its goals and objectives it becomes necessary for the assigned project manager to
identify and analyze resources in this phase. Basically this project phase initiates the data
warehouse development project.

9PROJECT MANAGEMENT
Project planning: In this phase different project knowledge management areas come
under consideration. The project manager and other associates need to develop risk quality,
procurement, communication, time, cost and schedule management plan in this project
development phase.
Project design and execution: In this phase the project prototype will be designed and
the warehouse will be connected to the Oracle database. This warehouse will be able to store and
manage large set of data. The authorized users and employees of Abu Dhabi Food control
Authority will be able to access those while required regardless of time and budget by running
queries.
Project testing: Whether the project design is successful from the business and
consumers perspectives or not is checked through project testing phases. The three sequential
testing processes will be used for this project are respectively unit testing, integration testing and
user acceptance testing. The user accepting testing will ensure that whether the project will be
beneficial or not.
Project implementation and closure: After successful acceptance testing the project is
finally implemented in this phase. Tough, post project maintenance is a very important activity
should e followed by the project team associates. In this phase the post system maintenance plan
is developed and the project is gets finally closed with stakeholders signoff.
Project planning: In this phase different project knowledge management areas come
under consideration. The project manager and other associates need to develop risk quality,
procurement, communication, time, cost and schedule management plan in this project
development phase.
Project design and execution: In this phase the project prototype will be designed and
the warehouse will be connected to the Oracle database. This warehouse will be able to store and
manage large set of data. The authorized users and employees of Abu Dhabi Food control
Authority will be able to access those while required regardless of time and budget by running
queries.
Project testing: Whether the project design is successful from the business and
consumers perspectives or not is checked through project testing phases. The three sequential
testing processes will be used for this project are respectively unit testing, integration testing and
user acceptance testing. The user accepting testing will ensure that whether the project will be
beneficial or not.
Project implementation and closure: After successful acceptance testing the project is
finally implemented in this phase. Tough, post project maintenance is a very important activity
should e followed by the project team associates. In this phase the post system maintenance plan
is developed and the project is gets finally closed with stakeholders signoff.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

10PROJECT MANAGEMENT
2.2 Formulation of the project team
Project team
members
Roles Responsibilities
Project Manager Internal The responsibility of the project manager is to control and
monitor the project progress so that it can meet the expectation
of the customers. In addition to this, another responsibility of
the project manager is to accomplish the project within assigned
timeline and budget
Research Analyzer Externa
l
Responsibility is to analyze current business situation and
possible information analysis to make the data warehouse
implementation successful
senior Data Design
Engineer
Internal To design and integrate all data accurately
Representatives
AMS, AIRS &
VMS
Externa
l
To represent AMS, AIRS & VMS
Representatives
HR, FIN, CP &
INV
Externa
l
To represent HR, FIN, CP & INV
Technical support Internal To identify technical and non technical requirements so that it
can support the automated data management (data warehouse
system)
2.2 Formulation of the project team
Project team
members
Roles Responsibilities
Project Manager Internal The responsibility of the project manager is to control and
monitor the project progress so that it can meet the expectation
of the customers. In addition to this, another responsibility of
the project manager is to accomplish the project within assigned
timeline and budget
Research Analyzer Externa
l
Responsibility is to analyze current business situation and
possible information analysis to make the data warehouse
implementation successful
senior Data Design
Engineer
Internal To design and integrate all data accurately
Representatives
AMS, AIRS &
VMS
Externa
l
To represent AMS, AIRS & VMS
Representatives
HR, FIN, CP &
INV
Externa
l
To represent HR, FIN, CP & INV
Technical support Internal To identify technical and non technical requirements so that it
can support the automated data management (data warehouse
system)

11PROJECT MANAGEMENT
2.3 Development of time management plan (schedule) using CPM based on resource
pool and resource allocation
WBS Task Name Duratio
n Start Finish
0 Scheduling smart reporting system for Abu Dhabi
Food Control Authority 121 days Mon
4/15/19
Fri
9/27/19
1 Project initiation 23 days Mon
4/15/19
Wed
5/15/19
1.1 Identification of problems in Abu Dhabi Food Control
Authority 5 days Mon
4/15/19 Fri 4/19/19
1.2 Developing project scope statement 6 days Mon
4/22/19
Mon
4/29/19
1.3 SRS 12 days Tue
4/30/19
Wed
5/15/19
1.3.1 Resource identification 5 days Tue
4/30/19 Fri 5/3/19
1.3.2 Resource gathering and analysis 8 days Mon
5/6/19
Wed
5/15/19
2 Project planning 19 days Thu
5/16/19
Tue
6/11/19
2.1 Feasibility analysis 5 days Thu
5/16/19
Wed
5/22/19
2.2 Time/ schedule and cost estimation 6 days Thu
5/16/19
Thu
5/23/19
2.3 Risk and quality management plan 5 days Fri 5/24/19 Thu
5/30/19
2.4 Contingency and procurement management plan 8 days Fri 5/31/19 Tue
6/11/19
3 Project design and execution 38 days Wed
6/12/19 Fri 8/2/19
3.1 Hardware and software specifications 9 days Wed
6/12/19
Mon
6/24/19
3.2 UML diagram presentation 5 days Tue
6/25/19
Mon
7/1/19
3.3 ETL design and code review 13 days Tue 7/2/19 Thu
7/18/19
3.3.1 Naming standard checking 5 days Tue 7/2/19 Mon
7/8/19
3.3.2 Checking business logic 8 days Tue 7/9/19 Thu
7/18/19
3.3.3 Checking mapping sources to target 7 days Tue 7/9/19 Wed
2.3 Development of time management plan (schedule) using CPM based on resource
pool and resource allocation
WBS Task Name Duratio
n Start Finish
0 Scheduling smart reporting system for Abu Dhabi
Food Control Authority 121 days Mon
4/15/19
Fri
9/27/19
1 Project initiation 23 days Mon
4/15/19
Wed
5/15/19
1.1 Identification of problems in Abu Dhabi Food Control
Authority 5 days Mon
4/15/19 Fri 4/19/19
1.2 Developing project scope statement 6 days Mon
4/22/19
Mon
4/29/19
1.3 SRS 12 days Tue
4/30/19
Wed
5/15/19
1.3.1 Resource identification 5 days Tue
4/30/19 Fri 5/3/19
1.3.2 Resource gathering and analysis 8 days Mon
5/6/19
Wed
5/15/19
2 Project planning 19 days Thu
5/16/19
Tue
6/11/19
2.1 Feasibility analysis 5 days Thu
5/16/19
Wed
5/22/19
2.2 Time/ schedule and cost estimation 6 days Thu
5/16/19
Thu
5/23/19
2.3 Risk and quality management plan 5 days Fri 5/24/19 Thu
5/30/19
2.4 Contingency and procurement management plan 8 days Fri 5/31/19 Tue
6/11/19
3 Project design and execution 38 days Wed
6/12/19 Fri 8/2/19
3.1 Hardware and software specifications 9 days Wed
6/12/19
Mon
6/24/19
3.2 UML diagram presentation 5 days Tue
6/25/19
Mon
7/1/19
3.3 ETL design and code review 13 days Tue 7/2/19 Thu
7/18/19
3.3.1 Naming standard checking 5 days Tue 7/2/19 Mon
7/8/19
3.3.2 Checking business logic 8 days Tue 7/9/19 Thu
7/18/19
3.3.3 Checking mapping sources to target 7 days Tue 7/9/19 Wed

12PROJECT MANAGEMENT
7/17/19
3.4 System prototype design 6 days Fri 7/19/19 Fri 7/26/19
3.5 Oracle database connectivity 5 days Mon
7/29/19 Fri 8/2/19
4 Testing 23 days Mon
8/5/19
Wed
9/4/19
4.1 Unit testing 5 days Mon
8/5/19 Fri 8/9/19
4.2 Functionality testing 8 days Mon
8/12/19
Wed
8/21/19
4.3 Performance and user acceptance testing 10 days Thu
8/22/19
Wed
9/4/19
5 Project implementation and closure phase 17 days Thu
9/5/19
Fri
9/27/19
5.1 Post system maintenance plan 15 days Thu 9/5/19 Wed
9/25/19
5.2 Stakeholder’s signoff 2 days Thu
9/26/19 Fri 9/27/19
7/17/19
3.4 System prototype design 6 days Fri 7/19/19 Fri 7/26/19
3.5 Oracle database connectivity 5 days Mon
7/29/19 Fri 8/2/19
4 Testing 23 days Mon
8/5/19
Wed
9/4/19
4.1 Unit testing 5 days Mon
8/5/19 Fri 8/9/19
4.2 Functionality testing 8 days Mon
8/12/19
Wed
8/21/19
4.3 Performance and user acceptance testing 10 days Thu
8/22/19
Wed
9/4/19
5 Project implementation and closure phase 17 days Thu
9/5/19
Fri
9/27/19
5.1 Post system maintenance plan 15 days Thu 9/5/19 Wed
9/25/19
5.2 Stakeholder’s signoff 2 days Thu
9/26/19 Fri 9/27/19
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

13PROJECT MANAGEMENT
Figure 2: Gantt chart for the data warehouse development project
(Source: Created by Author)
Figure 2: Gantt chart for the data warehouse development project
(Source: Created by Author)

14PROJECT MANAGEMENT
Figure 3: Schedule for the data warehouse development project (using CPM method)
(Source: Created by Author)
Figure 3: Schedule for the data warehouse development project (using CPM method)
(Source: Created by Author)

Running head: PROJECT MANAGEMENT
2.4 Estimate cost and budget
The net cost estimated for the project is $70,000. It is the responsibility of the project
manager to accomplish the project within this estimated timeline and budget.
WBS Task Name Duratio
n Resource Names Cost
0 Scheduling smart reporting system for
Abu Dhabi Food Control Authority 121 days $64,992.00
1 Project initiation 23 days $5,248.00
1.1 Identification of problems in Abu
Dhabi Food Control Authority 5 days Project Manager $800.00
1.2 Developing project scope statement 6 days Project Manager $960.00
1.3 SRS 12 days $3,488.00
1.3.1 Resource identification 4 days resource manager $480.00
1.3.2 Resource gathering and analysis 8 days Representative Group
(2),resource manager $3,008.00
2 Project planning 19 days $4,200.00
2.1 Feasibility analysis 5 days Finance manager $600.00
2.2 Time/ schedule and cost estimation 6 days Project Manager $960.00
2.3 Risk and quality management plan 5 days senior Data Design
Engineer $720.00
2.4 Contingency and procurement
management plan 8 days Representative group (1) $1,920.00
3 Project design and execution 38 days $50,008.00
3.1 Hardware and software specifications 9 days Hardware cost[1],software
cost[1] $45,000.00
3.2 UML diagram presentation 5 days senior Data Design
Engineer $720.00
3.3 ETL design and code review 13 days $2,592.00
3.3.1 Naming standard checking 5 days system developer $680.00
3.3.2 Checking business logic 8 days application programmer $960.00
3.3.3 Checking mapping sources to target 7 days system developer $952.00
3.4 System prototype design 6 days system developer $816.00
3.5 Oracle database connectivity 5 days DBA $880.00
4 Testing 23 days $2,576.00
4.1 Unit testing 5 days tester $560.00
4.2 Functionality testing 8 days tester $896.00
4.3 Performance and user acceptance
testing 10 days tester $1,120.00
2.4 Estimate cost and budget
The net cost estimated for the project is $70,000. It is the responsibility of the project
manager to accomplish the project within this estimated timeline and budget.
WBS Task Name Duratio
n Resource Names Cost
0 Scheduling smart reporting system for
Abu Dhabi Food Control Authority 121 days $64,992.00
1 Project initiation 23 days $5,248.00
1.1 Identification of problems in Abu
Dhabi Food Control Authority 5 days Project Manager $800.00
1.2 Developing project scope statement 6 days Project Manager $960.00
1.3 SRS 12 days $3,488.00
1.3.1 Resource identification 4 days resource manager $480.00
1.3.2 Resource gathering and analysis 8 days Representative Group
(2),resource manager $3,008.00
2 Project planning 19 days $4,200.00
2.1 Feasibility analysis 5 days Finance manager $600.00
2.2 Time/ schedule and cost estimation 6 days Project Manager $960.00
2.3 Risk and quality management plan 5 days senior Data Design
Engineer $720.00
2.4 Contingency and procurement
management plan 8 days Representative group (1) $1,920.00
3 Project design and execution 38 days $50,008.00
3.1 Hardware and software specifications 9 days Hardware cost[1],software
cost[1] $45,000.00
3.2 UML diagram presentation 5 days senior Data Design
Engineer $720.00
3.3 ETL design and code review 13 days $2,592.00
3.3.1 Naming standard checking 5 days system developer $680.00
3.3.2 Checking business logic 8 days application programmer $960.00
3.3.3 Checking mapping sources to target 7 days system developer $952.00
3.4 System prototype design 6 days system developer $816.00
3.5 Oracle database connectivity 5 days DBA $880.00
4 Testing 23 days $2,576.00
4.1 Unit testing 5 days tester $560.00
4.2 Functionality testing 8 days tester $896.00
4.3 Performance and user acceptance
testing 10 days tester $1,120.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

1PROJECT MANAGEMENT
5 Project implementation and closure
phase 17 days $2,960.00
5.1 Post system maintenance plan 15 days Research Analyzer $2,640.00
5.2 Stakeholder’s signoff 2 days Project Manager $320.00
5 Project implementation and closure
phase 17 days $2,960.00
5.1 Post system maintenance plan 15 days Research Analyzer $2,640.00
5.2 Stakeholder’s signoff 2 days Project Manager $320.00

2PROJECT MANAGEMENT
Assignment 3
3.1 Development of a Human Resource Plan
In order to manage the human resource for the project there are certain basic steps those
are needed to be followed by the assigned project associates. The Human resource knowledge
area is comprises of four processes in terms of development of human resource plan, acquiring
project team, developing project team and project team management. The process needs to cover
organizational behavior, psychology and human resource theories. The main purpose of the
human resource management team is to motivate and lead their project team members. Every
one of the project associate requires playing respective roles, responsibilities in the project
development plan. Individual’s contribution will help to meet the project goal and objectives.
Activity resource requirements: For each project activity what resource is actually
required identified in this phase. In order to complete theses activities the planning processes are
to be carried out.
Analysis of environmental factor: In this phase the organizational structure, values,
norms and ethics need to be followed by the project associates are elaborated.
Organizational process assets: This particular process deals with different aspects in
terms of resource project plan, social corporate of competencies, organizational guidelines,
policies and procedures.
Development of human resource plan: The human Resource management plan is about
assigning roles and responsibilities to each team members, giving title to them and finally
describing their level of authorities, skills and competency level.
Assignment 3
3.1 Development of a Human Resource Plan
In order to manage the human resource for the project there are certain basic steps those
are needed to be followed by the assigned project associates. The Human resource knowledge
area is comprises of four processes in terms of development of human resource plan, acquiring
project team, developing project team and project team management. The process needs to cover
organizational behavior, psychology and human resource theories. The main purpose of the
human resource management team is to motivate and lead their project team members. Every
one of the project associate requires playing respective roles, responsibilities in the project
development plan. Individual’s contribution will help to meet the project goal and objectives.
Activity resource requirements: For each project activity what resource is actually
required identified in this phase. In order to complete theses activities the planning processes are
to be carried out.
Analysis of environmental factor: In this phase the organizational structure, values,
norms and ethics need to be followed by the project associates are elaborated.
Organizational process assets: This particular process deals with different aspects in
terms of resource project plan, social corporate of competencies, organizational guidelines,
policies and procedures.
Development of human resource plan: The human Resource management plan is about
assigning roles and responsibilities to each team members, giving title to them and finally
describing their level of authorities, skills and competency level.

3PROJECT MANAGEMENT
Designing resource histogram: The resource histogram estimates the actual time spent
by each resource. The graph shows the actual schedule spent by an assigned resource for a
particular time phase. In order to detect the problems and fix them at the very early stage of
development the histogram, design is very essential.
Organizational chart and position description: Organizational chart is a hierarchy
which starts with a top sponsor and end with project manager at the extreme lower level
explaining regarding the project details.
Design of RACI chart/ RACI matrix: The RACI matrix, also known as responsibility
assignment matrix identified the responsibility assigned for each project associates at each
activity.
Organizational theory: The assigned project manager should ensure that each project
team members are following the norms and regulations complete professionally.
3.2 Development of Quality plan
In order to deliver a quality project to clients, the project manager should gather input
information in terms of scope statement, stakeholder management, risk register and project
implementation schedule. The scope statement defines the project boundaries, project
assumptions and project deliverables. The products scope identifies the function and features of
the Information System. The project manager should develop a risk register to identify the
potential risks, their possibilities, impact and respective mitigation strategies. In order to
accomplish the project within estimated timeline and budget the project manager must develop a
timeframe also.
Designing resource histogram: The resource histogram estimates the actual time spent
by each resource. The graph shows the actual schedule spent by an assigned resource for a
particular time phase. In order to detect the problems and fix them at the very early stage of
development the histogram, design is very essential.
Organizational chart and position description: Organizational chart is a hierarchy
which starts with a top sponsor and end with project manager at the extreme lower level
explaining regarding the project details.
Design of RACI chart/ RACI matrix: The RACI matrix, also known as responsibility
assignment matrix identified the responsibility assigned for each project associates at each
activity.
Organizational theory: The assigned project manager should ensure that each project
team members are following the norms and regulations complete professionally.
3.2 Development of Quality plan
In order to deliver a quality project to clients, the project manager should gather input
information in terms of scope statement, stakeholder management, risk register and project
implementation schedule. The scope statement defines the project boundaries, project
assumptions and project deliverables. The products scope identifies the function and features of
the Information System. The project manager should develop a risk register to identify the
potential risks, their possibilities, impact and respective mitigation strategies. In order to
accomplish the project within estimated timeline and budget the project manager must develop a
timeframe also.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4PROJECT MANAGEMENT
Data analysis: Each data collected for successful implementation of the (IS) project data
analysis is very essential. As soon as input information is received by planning team they must
conduct a cost benefit analysis to ensure the project success. The project manager should develop
a quality management plan with taking support from the other project team members.
Setting quality matrix: The Abu Dhabi Food Corporation Authority should develop a
quality matrix plan where the team requires selecting the service details they are going to deliver
to the clients. In order to assure project quality and control activities quality matrix must be
prepared.
Design of the improvement plan: This is the final step of developing a quality
management plan. This improvement plan used to analyze the performance quality, product
values, project boundaries, process matrices and objectives. The designed document is required
to be approved by project manager.
3.3 Development of communication plan
Purpose of communication Frequency Time Who Medium
To demonstrate the objectives
of the project to the project
team members
Weekly 2
hours
Project manager
and project team
members
Face to face
meeting,
presentation and
video conference
Develop the project scope
statement
Weekly 3
hours
Project manager
and project
sponsor
Face to face
meeting,
presentation and
video conference
Data analysis: Each data collected for successful implementation of the (IS) project data
analysis is very essential. As soon as input information is received by planning team they must
conduct a cost benefit analysis to ensure the project success. The project manager should develop
a quality management plan with taking support from the other project team members.
Setting quality matrix: The Abu Dhabi Food Corporation Authority should develop a
quality matrix plan where the team requires selecting the service details they are going to deliver
to the clients. In order to assure project quality and control activities quality matrix must be
prepared.
Design of the improvement plan: This is the final step of developing a quality
management plan. This improvement plan used to analyze the performance quality, product
values, project boundaries, process matrices and objectives. The designed document is required
to be approved by project manager.
3.3 Development of communication plan
Purpose of communication Frequency Time Who Medium
To demonstrate the objectives
of the project to the project
team members
Weekly 2
hours
Project manager
and project team
members
Face to face
meeting,
presentation and
video conference
Develop the project scope
statement
Weekly 3
hours
Project manager
and project
sponsor
Face to face
meeting,
presentation and
video conference

5PROJECT MANAGEMENT
To identify the possible risks
that may interrupt the project
success
Weekly 2
hours
Project manager
and resource
manager
Face to face
meeting,
presentation and
video conference
Discussion on current project
status
Monthly 1
hour
Project team
members and
manager
Presentation and
video conference
To discuss details of IS
implementation project
procurement plan for Abu
Dhabi Food control Authority
Monthly 2
hours
Project manager,
procurement
manager
Face to face
meeting,
presentation
3.4 Risk plan
Risk
Id
Risk name Description of the
risks
Likelihoo
d
Consequ
ences
Score Mitigation
strategy
R0 Interconnecti
on and
integration
risks
If proper technical
specifications are
not designed and
considered then
lack of integrity
and
interconnection
among the data
Rare (1) Catastrop
hic (5)
Low (5) Proper tools
and
techniques are
needed to be
used by the
system
developers of
Abu Dhabi
To identify the possible risks
that may interrupt the project
success
Weekly 2
hours
Project manager
and resource
manager
Face to face
meeting,
presentation and
video conference
Discussion on current project
status
Monthly 1
hour
Project team
members and
manager
Presentation and
video conference
To discuss details of IS
implementation project
procurement plan for Abu
Dhabi Food control Authority
Monthly 2
hours
Project manager,
procurement
manager
Face to face
meeting,
presentation
3.4 Risk plan
Risk
Id
Risk name Description of the
risks
Likelihoo
d
Consequ
ences
Score Mitigation
strategy
R0 Interconnecti
on and
integration
risks
If proper technical
specifications are
not designed and
considered then
lack of integrity
and
interconnection
among the data
Rare (1) Catastrop
hic (5)
Low (5) Proper tools
and
techniques are
needed to be
used by the
system
developers of
Abu Dhabi

6PROJECT MANAGEMENT
will occur. It will
impact the overall
process flow of the
data warehouse
and Oracle ERP
system
Food control
Authority to
make
interconnectio
n among the
stored
information.
R1 Technical
risks
If the project
manager fails to
identify the
technical
specification that
is required to
design and develop
the IS for UAE
food control
authority then the
all the available
discrete data may
not be stored and
fetched
successfully
Likely (4) Major (4) High
(16)
The project
manager
should
consider each
technical
specifications
at the project
initiation
phase to make
sure that no
issues are
arising.
R2 Lack of If it is found that Possible Moderate Moderat The owner
will occur. It will
impact the overall
process flow of the
data warehouse
and Oracle ERP
system
Food control
Authority to
make
interconnectio
n among the
stored
information.
R1 Technical
risks
If the project
manager fails to
identify the
technical
specification that
is required to
design and develop
the IS for UAE
food control
authority then the
all the available
discrete data may
not be stored and
fetched
successfully
Likely (4) Major (4) High
(16)
The project
manager
should
consider each
technical
specifications
at the project
initiation
phase to make
sure that no
issues are
arising.
R2 Lack of If it is found that Possible Moderate Moderat The owner
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

7PROJECT MANAGEMENT
special
training
among the
project team
members
the project team
members are
lagging essential
technical skills
then the project
will fail to meet the
objectives.
(3) (3) e (9) authority
should arrange
technical
training and
development
program to
make the
associates
familiar with
the IS
development
technical
knowledge
R3 Operational
risks
If the developed
system fails to
meet all
operational and
functional
requirements
Unlikely
(2)
Major (4) Low (8) The operation
manager is
responsible to
include all
operational
specifications
to make sure
that the
project is
meeting its
special
training
among the
project team
members
the project team
members are
lagging essential
technical skills
then the project
will fail to meet the
objectives.
(3) (3) e (9) authority
should arrange
technical
training and
development
program to
make the
associates
familiar with
the IS
development
technical
knowledge
R3 Operational
risks
If the developed
system fails to
meet all
operational and
functional
requirements
Unlikely
(2)
Major (4) Low (8) The operation
manager is
responsible to
include all
operational
specifications
to make sure
that the
project is
meeting its

8PROJECT MANAGEMENT
requirements
and
objectives.
R4 Improper cost
management
If the project
manager fails to
estimate needful
cost then it will
result issues with
cost management
Almost
likely (5)
Major (3) High
(15)
At the
initiation
phase the
project
finance
manager
should
conduct a
feasibility
study to
ensure
whether the
project will be
successful or
not.
R5 Inaccurate
time
management
Overrunning time
for project
completion is
referred to as a
major risk for this
Possible
(3)
High (4) High
(12)
Based on
complexity of
each project
development
activity
requirements
and
objectives.
R4 Improper cost
management
If the project
manager fails to
estimate needful
cost then it will
result issues with
cost management
Almost
likely (5)
Major (3) High
(15)
At the
initiation
phase the
project
finance
manager
should
conduct a
feasibility
study to
ensure
whether the
project will be
successful or
not.
R5 Inaccurate
time
management
Overrunning time
for project
completion is
referred to as a
major risk for this
Possible
(3)
High (4) High
(12)
Based on
complexity of
each project
development
activity

9PROJECT MANAGEMENT
project that may
interrupt the
project success
accurate
project
schedule must
be prepared by
the project
manager
R6 Inadequate
resource
allocation
Inaccurate
identification of
project resources
Most
likely (5)
High (4) Extreme
(20)
Considering
project
requirements
and objectives
resources
(human and
physical)
should e
identified by
the project
manager.
3.5 Procurement plan
The procurement plan developed for this specific project is comprises of five different
phases such as specification, selection, contracting, control and measurement. The aim of Abu
Dhabi Food control Authority is to use the discrete data available in different departments and
use them successfully to make the reporting format smarter to allow the sponsors make easy
project that may
interrupt the
project success
accurate
project
schedule must
be prepared by
the project
manager
R6 Inadequate
resource
allocation
Inaccurate
identification of
project resources
Most
likely (5)
High (4) Extreme
(20)
Considering
project
requirements
and objectives
resources
(human and
physical)
should e
identified by
the project
manager.
3.5 Procurement plan
The procurement plan developed for this specific project is comprises of five different
phases such as specification, selection, contracting, control and measurement. The aim of Abu
Dhabi Food control Authority is to use the discrete data available in different departments and
use them successfully to make the reporting format smarter to allow the sponsors make easy
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10PROJECT MANAGEMENT
decision making. In order to convert the manual discrete data management system of Abu Dhabi
Food control Authority, to an automated one the phases to be followed to develop the
procurement plan are as follows:
Initial plan the procurement: In order to design, develop and approve the procurement
items the marketing and management department needs to communicate with the project
manager. The marketing and management department needs to specify all approved items to
their external vendors. This allows the project planners to determine if the expectations are found
to be completely realistic. In this phase the procurement objectives will be identified with a detail
scope statement,
Scope of the procurement: In this phase, the project the assigned project manager of
Abu Dhabi Food Control Authority data warehousing project needs to determine whether the
services to be purchased are subject to coordinated procurement arrangements those must be
used. The value of procurement needs to be estimated with a details market research.
Selection of suppliers: In this phase accurate project suppliers and vendors should be
selected. In act if t is found that, bidding is needed then, bidding processes are needed to be
specified counting minimum bidding numbers. In this phase the term that needs to be considered
before the implementation of the project is identified. It helps to check that whether the preferred
vendors are nominated by the project manager for implementing the data warehouse system or
not.
Bidding and acceptance: In this phase the procurement department issues a proposal as
a proposal that is also known as Request for Proposal (RFP) which details the project scope,
objectives and actual needs. The response of the suppliers for the proposals will help to provide
decision making. In order to convert the manual discrete data management system of Abu Dhabi
Food control Authority, to an automated one the phases to be followed to develop the
procurement plan are as follows:
Initial plan the procurement: In order to design, develop and approve the procurement
items the marketing and management department needs to communicate with the project
manager. The marketing and management department needs to specify all approved items to
their external vendors. This allows the project planners to determine if the expectations are found
to be completely realistic. In this phase the procurement objectives will be identified with a detail
scope statement,
Scope of the procurement: In this phase, the project the assigned project manager of
Abu Dhabi Food Control Authority data warehousing project needs to determine whether the
services to be purchased are subject to coordinated procurement arrangements those must be
used. The value of procurement needs to be estimated with a details market research.
Selection of suppliers: In this phase accurate project suppliers and vendors should be
selected. In act if t is found that, bidding is needed then, bidding processes are needed to be
specified counting minimum bidding numbers. In this phase the term that needs to be considered
before the implementation of the project is identified. It helps to check that whether the preferred
vendors are nominated by the project manager for implementing the data warehouse system or
not.
Bidding and acceptance: In this phase the procurement department issues a proposal as
a proposal that is also known as Request for Proposal (RFP) which details the project scope,
objectives and actual needs. The response of the suppliers for the proposals will help to provide

11PROJECT MANAGEMENT
the details of cost, time and schedule details related to the project. It is the responsibility of the
project manager and project team members to develop a procurement management plan to
implement the Oracle based ERP system successfully within assumed timeline and budget as
well.
the details of cost, time and schedule details related to the project. It is the responsibility of the
project manager and project team members to develop a procurement management plan to
implement the Oracle based ERP system successfully within assumed timeline and budget as
well.

12PROJECT MANAGEMENT
Bibliography
Ahern, T., Leavy, B., & Byrne, P. J. (2014). Complex project management as complex problem
solving: A distributed knowledge management perspective. International Journal of
Project Management, 32(8), 1371-1381.
Cohen-Vogel, L., Tichnor-Wagner, A., Allen, D., Harrison, C., Kainz, K., Socol, A. R., &
Wang, Q. (2015). Implementing educational innovations at scale: Transforming
researchers into continuous improvement scientists. Educational Policy, 29(1), 257-277.
Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., & de Almeida, L. F. M. (2014). Can
agile project management be adopted by industries other than software
development?. Project Management Journal, 45(3), 21-34.
Conger, S. (2015). Six sigma and business process management. In Handbook on Business
Process Management 1 (pp. 127-146). Springer, Berlin, Heidelberg.
First, M. B. (2016). Adopting a continuous improvement model for future DSM revisions. World
Psychiatry, 15(3), 223-224.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management.
Project Management Institute.
Heldman, K. (2015). PMP project management professional exam deluxe study guide: updated
for the (2015) Exam. John Wiley and Sons.
Bibliography
Ahern, T., Leavy, B., & Byrne, P. J. (2014). Complex project management as complex problem
solving: A distributed knowledge management perspective. International Journal of
Project Management, 32(8), 1371-1381.
Cohen-Vogel, L., Tichnor-Wagner, A., Allen, D., Harrison, C., Kainz, K., Socol, A. R., &
Wang, Q. (2015). Implementing educational innovations at scale: Transforming
researchers into continuous improvement scientists. Educational Policy, 29(1), 257-277.
Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., & de Almeida, L. F. M. (2014). Can
agile project management be adopted by industries other than software
development?. Project Management Journal, 45(3), 21-34.
Conger, S. (2015). Six sigma and business process management. In Handbook on Business
Process Management 1 (pp. 127-146). Springer, Berlin, Heidelberg.
First, M. B. (2016). Adopting a continuous improvement model for future DSM revisions. World
Psychiatry, 15(3), 223-224.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management.
Project Management Institute.
Heldman, K. (2015). PMP project management professional exam deluxe study guide: updated
for the (2015) Exam. John Wiley and Sons.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

13PROJECT MANAGEMENT
Hornstein, H. A. (2015). The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2),
291-298.
Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and
project success in different project governance contexts. International Journal of Project
Management, 33(6), 1377-1392.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A. M. E., & Villanueva, P. (2014). Project
risk management methodology for small firms. International Journal of Project
Management, 32(2), 327-340.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), 202-217.
Sanchez, M. A. (2015). Integrating sustainability issues into project management. Journal of
Cleaner Production, 96, 319-330.
Todorovic, M. L., Petrović, D. Č., Mihic, M. M., Obradovic, V. L., & Bushuyev, S. D. (2015).
Project success analysis framework: A knowledge-based approach in project
management. International Journal of Project Management, 33(4), 772-783.
Hornstein, H. A. (2015). The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2),
291-298.
Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and
project success in different project governance contexts. International Journal of Project
Management, 33(6), 1377-1392.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A. M. E., & Villanueva, P. (2014). Project
risk management methodology for small firms. International Journal of Project
Management, 32(2), 327-340.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), 202-217.
Sanchez, M. A. (2015). Integrating sustainability issues into project management. Journal of
Cleaner Production, 96, 319-330.
Todorovic, M. L., Petrović, D. Č., Mihic, M. M., Obradovic, V. L., & Bushuyev, S. D. (2015).
Project success analysis framework: A knowledge-based approach in project
management. International Journal of Project Management, 33(4), 772-783.

14PROJECT MANAGEMENT
1 out of 30
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.