Detailed Project Management Plan: Demolition Project Overview

Verified

Added on  2020/05/04

|39
|6587
|235
Project
AI Summary
This project management plan outlines the key components necessary for the successful execution of a demolition project. It begins with an introduction and organizational plan, detailing the structure of the construction company and the roles of various departments like HR, finance, and engineering. The plan then proceeds to cover staffing, resource allocation, and project programming. A significant portion is dedicated to essential aspects like budgeting, communication, work health and safety, and stakeholder management. Quality management is addressed through a detailed plan, followed by procurement and logistics strategies. Furthermore, the plan includes a comprehensive risk management plan, contract management guidelines, and a construction environmental management plan, along with temporary traffic management measures. The conclusion summarizes the key takeaways and overall project management strategy for the demolition project.
Document Page
PROJECT MANAGEMENT
PLAN
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Table of Contents
1. Introduction.................................................................................................................................3
2. Organisational Plan.....................................................................................................................3
3. Staffing Plan.................................................................................................................................5
4. Resource Plan...............................................................................................................................5
5. Program........................................................................................................................................6
6. Budget...........................................................................................................................................6
7. Communication Plan...................................................................................................................6
8. Work health Safety Plan.............................................................................................................7
9. Stakeholder Management...........................................................................................................7
10. Quality Management Plan......................................................................................................9
11. A Procurement and Logistics Plan.......................................................................................10
12. Risk Management Plan.........................................................................................................11
13. Contract Management Plan..................................................................................................11
14. Construction Environmental Management Plan.................................................................12
15. Temporary Traffic Management Measures.........................................................................12
16. Project Management Plan.....................................................................................................13
17. Conclusion..............................................................................................................................40
Document Page
1. Introduction
Main scope of the project is to construct the project management system plan for
demolition project. This project management include several types of planning’s used to
demolition the building. These are includes the organisational plan, staffing plan,
communication plan, stakeholder plan, work health and safety plan, quality management plan
,construction plan and risk management plan. In this project management system consist of
various planning systems. In this construction project will be demolition, so we are providing
some demolition process buildings to the organisation. The demolition process is nothing but
the removal of equipment, cleaning up all the unwanted things around the building area and
also removal process of portable bathroom.
2. Organisational Plan
The construction company generally contains the basic functions of units. These are
including by project, financial department, human resources, marketing and purchasing
department. In this organisational plan include various roles in construction management. In
this organisational charts are having the different types of graphical representations (Kerzner,
2017).
Document Page
The basic responsibilities for each and every department in the construction Management
Company is shown in below.
Human resources department
In this HR department is most responsible for the staff training and staff recruitment
processes. It also keeps and maintains the record details, benefits, Insurance and also
responsible for the employee relations.
Project department
The project department is responsible for managing the each project and also
scheduling the each project. The project manager duties are need to assign employees and
their duties. The project manager also needs to decide the financial status of the project. It
also needs to complete the job and overview the workers safety.
Purchasing department
In this purchasing department play main roles in purchasing materials used for the
projects and also supplies the company daily needs.
Financial department
The financial department having the responsibilities to managing the company’s cash
flow and also update the available to meet the everyday payments details.
Engineering department
It responsible for the construction planning go the project work. The engineering
department also needs to surveys, analysing the results, construction planning and also
supporting to the all technical problems during the project work.
3. Staffing Plan
Staff planning is the process for selecting the right people to hiring the organisation or
the constructional process management. In this staffing plan to ensure with the fulfil business
needs to the employee. We must take into the internal and external changes with the company
business plan. The staffing plan needs the process of analysing and identifying staffing plans
and surpluses. In this staffing process is part of the Human resources management planning.
The function of staffing strategic is to perform the employees with your company’s
overall goals to achieve. And also it prepared status for developing and keeping the
employees. The workforce planning is a continuous process used for aligning the needs of the
organizations. The models of staffing process are related to set of reports, it used to determine
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
how many employers are needed and analysing the employee time spent and calculates the
costs (Halpin, Lucko & Senior, n.d.).
4. Resource Plan
In demolition Project, the resource allocations are listed below.
Resource Name Type Initials Max.
Units Std. Rate Accrue
At
Base
Calendar
Project Engineer Work P 100% $250.00/hr Prorated Standard
Site Foreman Work S 100% $250.00/hr Prorated Standard
Plant operator Work P 100% $300.00/hr Prorated Standard
General labourer Work G 100% $450.00/hr Prorated Standard
Principal Surveyor (Registered) Work P 100% $250.00/hr Prorated Standard
Senior Surveyor Work S 100% $300.00/hr Prorated Standard
Surveyor Work S 100% $350.00/hr Prorated Standard
Survey Draftsperson Work S 100% $350.00/hr Prorated Standard
Survey Assistant Work S 100% $400.00/hr Prorated Standard
Arborist Work A 100% $350.00/hr Prorated Standard
Hygienist Work H 100% $250.00/hr Prorated Standard
Asbestos Removalist Supervisor Work A 100% $350.00/hr Prorated Standard
Asbestos Removalist Labourer Work A 100% $300.00/hr Prorated Standard
Senior Environmental
Consultant Work S 100% $350.00/hr Prorated Standard
Environmental Consultant Work E 100% $200.00/hr Prorated Standard
Structural Engineer Work S 100% $400.00/hr Prorated Standard
Contractor Work C 100% $500.00/hr Prorated Standard
Contractor Assistant Work C 100% $400.00/hr Prorated Standard
5. Program
In a programme for the constructional project work is related to maintain the dates
and duration allocated to the tasks. Tasks which can only carried out after the other one tasks
Document Page
have been completed. In this task work carried out simultaneously. To preparing the
programme should not be in the simple paper form. It must be a record formation.
6. Budget
Overall demolition project budget is shown in below.
Name % Complete Cost Baseline
Cost
Cost Variance
DEMOLITION
PROJECT
0% $2,699,600.00 $0.00 $2,699,600.00
7. Communication Plan
In communication plan, essential thinks is to any project management. In this
communication process including the project topic, project delivery date, delivery mechanism
and it also handles the sensitive issues, communicator and finally the expected result also.
8. Work health Safety Plan
In this field is very important to construct the management. This field is addresses to
the application process and enforcement of the government safety and health regulation
before constructing process. The one the safety act is the occupational safety and health act
(OSHA) is addresses to many safety issues to associates with the construction process. The
major two safety hazards are falls from height on a working site and construction vehicles,
but it also the more problems are done to reduce.
Some of the main hazards to health, the solvents, manual handling activities and noise
problems to create the health hazards to the employers. Before starting the constructional
work to must properly collect the samples of the dust, vapours, gases and other toxic
materials to ensure the personal safety and test results. To reduce this type of hazards the
professions in this field to routinely check the safety measurements. These are including by:
The home inspector and the safety director.
Mainly the construction inspector should there the site of the construction building.
Building inspectors and environmental health and safety manager
Regulatory compliance manager.
Document Page
The demolition process include the health and safety plans, during the demolition
process the cable lines are placed so to ensure that the cable line will not be cut or any
damage. Must use the goggles and cutting shields shall be used to protect the eye, and to
prevent the flash burns from the welding machine. When the cutting process will be
stated must protect the non-combustible proofs. During the cutting process the proper
ventilation will be provided for the heating process performed (Du & Li, 2011).
9. Stakeholder Management
The stakeholder management is anybody can affect or affected by the organisation or
project. The people who are external or internal and senior or junior levels, it power to
respond and change the strategic future of the company.
Stake holder lists are followed include by:
Wood machinist
Labourer
Ceiling fixer
Roofer
Plant mechanic
Plant operator
General construction
Shop fitter
Bricklayers
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
The stakeholders are two different types. These are internal stakeholders and external
stakeholders. The internal stake holders who are affect or affected by within the
organisations is known as internal stakeholders. In this internal stakeholders include the
management,marketing,designers,sales,assembly,experts,purchasing,manufacturing,and
designers (Ganapathi & Nandi, n.d.).
The external stakeholders are determining who are affected by the individual or
outside a business or project. It includes the vendors, consultants, celebrities, citizen’s action
groups, government regulators, trade unions and associations.
10.Quality Management Plan
In this quality management specifies the 8 essentials to control the quality plan management.
The 8 essentials are followed by
Project personnel
In project should have the designed quality manager, the one person is manage the
quality control. The quality management plan along with the person’s qualification to holding
this position.
Quality assurance surveillance
In this quality assurance surveillance will be monitoring the project quality on a
weekly or monthly basis.
Quality communications
Document Page
The quality communication should include the quality plan that includes expecting the
touch points to your clients.
Inspections and tests
The inspection process includes some procedures.
Monitoring the work processes
Handle the construction materials to receiving and inspections
Make sure that the construction work is ready to begin
Verifying that the project work completed.
Project quality specifications
Sometimes the customers do not specifying the building codes or industrial standards
are apply to your scope of the project. You will list the work; so there’s no confusion to the
quality work specifications.
Subcontractors and suppliers
To always include the good plan to construct the project work, the following plans are
there,
Listing the subcontractors and project suppliers
The subcontractor qualification and suppliers records
The qualifying suppliers and subcontractors should follow the procedures
Project completion inspections
The project completion inspections are including the final things of the project work.
The contracted work is completed to specifications.
Control of non-conformances
It includes the corrective actions of the project work. It also preventing cover-ups the
work and it also keep the record incident (Oakland, 2016).
11.A Procurement and Logistics Plan
Document Page
The procurement logistics are to ensure the economic supplies of the company.it will
not self-produced raw materials. In this logistics also supplies the good and buying parts. In
particularly the large companies and medium sized are easy to reached a high level
complexity. In this logistics are occurs due to the diverse and heterogeneous tasks and targets,
it includes in the department of purchasing and materials (Heerkens, 2015).
A procurement and logistics plan are also include the numerous to optimised the
materials management and production. It increases the cost pressure, customer’s demand. In
also addition the logistics needs to design, it can be flexibly adapted to changing the
environmental conditions.
12.Risk Management Plan
Basically risk is a condition that occurs in positive or negative effects on the projects.
In this risk management include a strategy. In this strategies are avoid the risk, control the
risk, to accept risk and transfer the risk. The SARA is abbreviated as Share, Avoid, Reduce,
and Accept. In this risk management system to track the documenting reports (Pellicer,
2014).
The risk management has two types of risk tools. These are the capital asset pricing
model and another one is probabilistic risk assessment. The capital asset pricing model is
used for economic statistics or market to determine the required asset of risk. The
probabilistic risk assessment application is used to generating and identifying the metrics.
In this risk management system having lot of risks to demolition the building. In this
section the risk management system includes the various types of the problems. During risk
process, it has the two risk assessment such as qualitative risk assessment and quantitative
risk assessment. In this risk processes include the various hazards. These are individual risk
of injury, individual risk of fatality and biophysical risk.
13. Contract Management Plan
In this section of contract management plan to identifies the guidelines for the
successful management. It also identifies the critical process of the contract management. In
this contract management process explain, how the team members to resolve the contract
management issues. It used to keeping the relationship between the team members in long
way, to effectively resolve the problem of contract management. Contract communication
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
protocol address explained how the formal informal and outside communication are includes
in this process (Cicala & Cicala, 2013).
The formal communication with the contractor used to tracking the system and also it
correspondence to control the systems. The informal communication address can arises from
the members of the CMT and IPT. In this type of communication is non-binding
communication process. The outside communication protocol include the state and central
government responsibilities and work scope it is one of the critical communication compare
to other communication process. In this section the construct management plan also
including the demolition process. The contractor of the building must prepare the approval of
the site, and also explain the project report.
14. Construction Environmental Management Plan
The construction environmental management planning is the purpose of to outline the
construction project to minimise on the environment and the surrounding areas. In this
environmental policy requirements conditions are followed by the section 106 agreement.
Purpose
The purpose of this environmental planning is classified into:
Stakeholder
Environmental management system
Environmental statement
Method statements
Environmental legislation(Happy, 2010)
Scope
The basics of construction environmental management plan are applicable for
individual project of subject areas.
Water quality and drainage should be properly
Soils and geology area should be applicable for the construction
Air quality
The vibration and noise
To must have a nature conservation
In this section the environmental status of the management plan in demolition process
occur in environmental related problems. The management will be establishing the
construction process you must prepare the environmental management plan during the
Document Page
demolition works. It also includes the soil sedimentation, erosion control, dust mitigation
and contamination management planning. The site engineering must produce the full
environmental report. In this demolition work include in environmental protection
agreement with the EPA in respect to all the activities (O'Brien & Plotnick, n.d.).
15. Temporary Traffic Management Measures
The temporary traffic management is responsible for the safety of the workforce
management. In this management process does not disturb for peoples, and the users can
travel safely around the work sites. In this section the requirements are needed to start the
environmental management system (Halpin, Lucko & Senior, n.d.).
It should be an approval to use a closed road
Temporary public road to closure
It must having the traffic control devices plan authorisation
Temporary traffic management plan authorisation
The work will be executed by map or plan
In this section the traffic management system to control the traffic problems during
the demolition process. During this process of demolition in traffic management has the
traffic congestion problems. In this management must approval to use a closed road for
the demolition process. And it also not disturb to any other problems for the public. In
this management do not disturb in any other illegal activities.
16. Project Management Plan
Open MS Project.
Set Start date and End date.
After, set as the Non- Working Date. It is shown in below.
Document Page
The Demolition Project Task is shown in below.
Task Name
DEMOLITION PROJECT
PRELIMINARIES
Site establishment & maintenance site office and amenities
Survey Control
Preparation and submission and approval of PQP, ITPs, Project
WHS Plan, Environmental and Waste Management Plan
Preparation of Project Plans
Preparation of Construction and Environmental Management
Plan
Liaison and Approvals from all Authorities
Liaison and Coordination with adjoining work sites /
residential / business dwellings
Environmental Reporting and Approvals including Liaison and
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Coordination with the Principal’s Environmental Consultant
Approvals and Fees for Required Technical Support
Compliance and Audit Testing as Directed by the Principal's
Authorised Person PS
Additional Work as Directed by the Principals Authorised Person
(PAP) PS
Workasexecuted Information
Provision for traffic
EARTHWORKS
Protection of the Works
Clearing and grubbing
Removal of Tree
Removal of Pavement
Extra over Pay Item for Saw Cutting Pavement
Removal of Concrete Kerbs
Removal of Paths and Driveways
Removal and Stockpiling topsoil
Removal and Stockpiling topsoil on site
General Earthworks
Disposal of Spoil Material Off Site
Imported Fill
Removal of hazardous materials and remediation of areas of
environmental concern and providing clearance
UNDERGROUND SERVICES
Excavation & Backfilling
Backfilling Under Roads, Paths and Driveways
Existing Services Location
Sewer
Storm water
Gas
Electricity
Document Page
Water
Telecommunication
Sewerage
Works by the Sewer Authority (ICON)
Works by the Sewer Authority to existing sewer services
Works by the Contractor on existing sewer services, excluding
works by the Sewer Authority
Removal of all internal in ground sewer services
Storm water Drainage
Removal of all internal in ground storm water services
Water Supply Mains
Works by the Water Authority (ICON)
Works by the Water Authority to existing sewer services
(ICON)
Works by the Contractor on existing water services, excluding
works by the Sewer Authority
Removal of all internal in ground water services
INCIDENTALS
Fencing
Fence Type T
Removal of Existing Fences
Power Supply Disconnection
Works by ActewAGL
Works by the Contractor
Common Supply Disconnection
Works by Telstra
Works by the Contractor
Gas Supply Disconnection
Works by ActewAGL
Works by the Contractor
Site Establishment
Supply, install, and maintain hoardings and temporary fences
Document Page
Undertake a full dilapidation survey of the site
Install and maintain clearly signposted and safe site access gates.
Approvals and Documentation
Prepare and submit a Building Application and engage Building
Certifier for works
The Contractor shall prepare and submit a TTM plan
The Contractor is to provide program and methodology
Submit for approval a demolition method statement
Provide worksasexecuted drawings per current ACT
Government reference documents recording all works, including
service terminations.
LANDSCAPE
Topsoil
Site topsoil to grass areas
Top soiling (Type C)
Grassing
Dry land Grass
Bitumen and Straw Mulching
DEMOLITION
Hazardous Materials Removal
Hazardous materials, lead paint, PCBs, SMFs & ODS
Asbestos Containing Materials (ACM’s)
Removal and disposal of all hazardous materials as identified in
'Hazardous Material Survey & Management Plan’ Robson
Intrusive report
Air Monitoring
Environmental Clearances to proceed with the demolition works.
Underground Fuel Storage Tank (UST)
Establish and maintain environmental controls in accordance
with RAP
Excavate and stockpile spoil at AEC (UST)
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Remove and dispose of pipes, valves and vent lines associated
with UST
Remove and dispose of UST
Validation sampling of stockpile (1 round)
Removal and disposal of stockpile spoil including all fees
Additional validation sampling
Additional spoil disposal
Unexpected Finds
Demolition Works
Demolition of Buildings
Demolition of Minor Structures
Retaining Walls (Brick)
Courtyard Walls (Brick)
Concrete Stairs
Light Poles, Light Bollards, log barriers & Signs etc.
Gas Meter Brick Enclosure
Overall Project management plan is shown in below.
Task
Mode Task Name Duration Start Finish Predecessors Resource
Names
Auto
Scheduled
DEMOLITION
PROJECT 287 days Thu
1/1/15
Tue
2/23/16
Auto
Scheduled PRELIMINARIES 65 days Thu
1/1/15
Wed
4/1/15
Auto
Scheduled
Site establishment
& maintenance site
office and amenities
3 days Thu
1/1/15
Mon
1/5/15
Project
Engineer ,Site
Foreman
Auto
Scheduled Survey Control 3 days Tue
1/6/15
Thu
1/8/15 3
Survey
Assistant ,Surv
eyorr, Senior
Surveyor
Document Page
Auto
Scheduled
Preparation and
submission and
approval of PQP, ITPs,
Project WHS Plan,
Environmental and
Waste Management
Plan
4 days Fri
1/9/15
Wed
1/14/15 4
Principal
Surveyor
(Registered) ,P
roject Engineer
Auto
Scheduled
Preparation of
Project Plans 10 days Thu
1/15/15
Wed
1/28/15 5
Project
Engineer ,Cont
ractor,
Contractor
Assistant
Auto
Scheduled
Preparation of
Construction and
Environmental
Management Plan
6 days Thu
1/29/15
Thu
2/5/15 6
Contractor,
Contractor
Assistant,
Project
Engineer
Auto
Scheduled
Liaison and
Approvals from all
Authorities
5 days Fri
2/6/15
Thu
2/12/15 7
Principal
Surveyor
(Registered) ,S
enior
Environmental
Consultant ,Se
nior Surveyor
Auto
Scheduled
Liaison and Co
ordination with
adjoining work sites /
residential / business
dwellings
5 days Fri
2/13/15
Thu
2/19/15 8
Senior
Environmental
Consultant ,Se
nior Surveyor
Auto
Scheduled
Environmental
Reporting and
Approvals including
Liaison and Co
6 days Fri
2/20/15
Fri
2/27/15
9 Principal
Surveyor
(Registered) ,S
enior
Document Page
ordination with the
Principal’s
Environmental
Consultant
Environmental
Consultant
Auto
Scheduled
Approvals and Fees
for Required Technical
Support
4 days Mon
3/2/15
Thu
3/5/15 10
Contractor,
Project
Engineer
Auto
Scheduled
Compliance and
Audit Testing as
Directed by the
Principal's Authorised
Person PS
4 days Fri
3/6/15
Wed
3/11/15 11
Senior
Surveyor ,Surv
ey
Draftsperson ,
Surveyorr
Auto
Scheduled
Additional Work as
Directed by the
Principals Authorised
Person (PAP) PS
5 days Thu
3/12/15
Wed
3/18/15 12
Principal
Surveyor
(Registered)
Auto
Scheduled
Workasexecuted
Information 5 days Thu
3/19/15
Wed
3/25/15 13
Project
Engineer ,Stru
ctural Engineer
Auto
Scheduled Provision for traffic 5 days Thu
3/26/15
Wed
4/1/15 14
General
labourer ,Senio
r
Environmental
Consultant
Auto
Scheduled EARTHWORKS 53 days Thu
4/2/15
Mon
6/15/15 2
Auto
Scheduled
Protection of the
Works 3 days Thu
4/2/15
Mon
4/6/15
Project
Engineer ,Stru
ctural Engineer
Auto
Scheduled
Clearing and
grubbing 15 days Tue
4/7/15
Mon
4/27/15 17
Auto
Scheduled
Removal of Tree 15 days Tue
4/7/15
Mon
4/27/15
General
labourer ,Plant
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
operator
Auto
Scheduled
Removal of
Pavement 6 days Tue
4/28/15
Tue
5/5/15 18
Auto
Scheduled
Extra over Pay
Item for Saw Cutting
Pavement
6 days Tue
4/28/15
Tue
5/5/15
Environmental
Consultant ,Ge
neral
labourer ,Plant
operator
Auto
Scheduled
Removal of
Concrete Kerbs 8 days Wed
5/6/15
Fri
5/15/15 20
Plant
operator ,Gene
ral
labourer ,Senio
r
Environmental
Consultant
Auto
Scheduled
Removal of Paths
and Driveways 7 days Mon
5/18/15
Tue
5/26/15 22
Plant
operator ,Gene
ral labourer
Auto
Scheduled
Removal and
Stockpiling topsoil 3 days Wed
5/27/15
Fri
5/29/15 23
Auto
Scheduled
Removal and
Stockpiling topsoil on
site
3 days Wed
5/27/15
Fri
5/29/15
Asbestos
Removalist
Labourer ,Asb
estos
Removalist
Supervisor
Auto
Scheduled
General Earthworks 3 days Mon
6/1/15
Wed
6/3/15
24 Asbestos
Removalist
Labourer ,Asb
estos
Removalist
Supervisor,
Environmental
Document Page
Consultant
Auto
Scheduled
Disposal of Spoil
Material Off Site 3 days Thu
6/4/15
Mon
6/8/15 26 General
labourer
Auto
Scheduled Imported Fill 3 days Tue
6/9/15
Thu
6/11/15 27 Senior
Surveyor
Auto
Scheduled
Removal of
hazardous materials
and remediation of
areas of environmental
concern and providing
clearance
2 days Fri
6/12/15
Mon
6/15/15 28
General
labourer ,Proje
ct Engineer
Auto
Scheduled
UNDERGROUND
SERVICES 49 days Tue
6/16/15
Fri
8/21/15 16
Auto
Scheduled
Excavation &
Backfilling 25 days Tue
6/16/15
Mon
7/20/15
Auto
Scheduled
Backfilling Under
Roads, Paths and
Driveways
4 days Tue
6/16/15
Fri
6/19/15
Contractor,
Contractor
Assistant,
Environmental
Consultant ,Sit
e Foreman
Auto
Scheduled
Existing Services
Location 3 days Mon
6/22/15
Wed
6/24/15 32 Site Foreman
Auto
Scheduled Sewer 3 days Thu
6/25/15
Mon
6/29/15 33
Project
Engineer ,Stru
ctural Engineer
Auto
Scheduled Stormwater 3 days Tue
6/30/15
Thu
7/2/15 34
Contractor,
Contractor
Assistant,
Project
Engineer ,Stru
ctural Engineer
Auto Gas 3 days Fri Tue 35 Contractor,
Document Page
Scheduled 7/3/15 7/7/15
Contractor
Assistant,
Project
Engineer ,Stru
ctural Engineer
Auto
Scheduled Electricity 3 days Wed
7/8/15
Fri
7/10/15 36
Contractor,
Contractor
Assistant,
General
labourer ,Proje
ct
Engineer ,Stru
ctural Engineer
Auto
Scheduled Water 3 days Mon
7/13/15
Wed
7/15/15 37
General
labourer ,Senio
r
Environmental
Consultant ,Str
uctural
Engineer
Auto
Scheduled Telecommunication 3 days Thu
7/16/15
Mon
7/20/15 38
Site
Foreman ,Surv
ey
Assistant ,Surv
ey
Draftsperson
Auto
Scheduled Sewerage 10 days Tue
7/21/15
Mon
8/3/15 31
Auto
Scheduled
Works by the
Sewer Authority
(ICON)
2 days Tue
7/21/15
Wed
7/22/15
Survey
Assistant ,Surv
ey
Draftsperson ,
Surveyor
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Auto
Scheduled
Works by the
Sewer Authority to
existing sewer services
2 days Thu
7/23/15
Fri
7/24/15 41
Senior
Surveyor ,Surv
ey
Assistant ,Surv
ey
Draftsperson ,
Surveyor
Auto
Scheduled
Works by the
Contractor on existing
sewer services,
excluding works by the
Sewer Authority
3 days Mon
7/27/15
Wed
7/29/15 42
Senior
Surveyor ,Surv
ey
Assistant ,Surv
ey
Draftsperson ,
Surveyor
Auto
Scheduled
Removal of all
internal in ground
sewer services
3 days Thu
7/30/15
Mon
8/3/15 43
Senior
Environmental
Consultant ,Se
nior
Surveyor ,Stru
ctural
Engineer,
Survey
Assistant
Auto
Scheduled
Stormwater
Drainage 3 days Tue
8/4/15
Thu
8/6/15 40
Auto
Scheduled
Removal of all
internal in ground
stormwater services
3 days Tue
8/4/15
Thu
8/6/15
Principal
Surveyor
(Registered) ,P
roject Engineer
,Structural
Engineer
Auto
Scheduled
Water Supply
Mains 11 days Fri
8/7/15
Fri
8/21/15 45
Document Page
Auto
Scheduled
Works by the
Water Authority
(ICON)
2 days Fri
8/7/15
Mon
8/10/15
Senior
Surveyor ,Site
Foreman ,Surv
ey Assistant
Auto
Scheduled
Works by the
Water Authority to
existing sewer services
(ICON)
3 days Tue
8/11/15
Thu
8/13/15 48
Site
Foreman ,Stru
ctural
Engineer,
Survey
Draftsperson ,
Surveyor
Auto
Scheduled
Works by the
Contractor on existing
water services,
excluding works by the
Sewer Authority
3 days Fri
8/14/15
Tue
8/18/15 49
Senior
Surveyor ,Stru
ctural
Engineer,
Survey
Assistant ,Surv
ey
Draftsperson
Auto
Scheduled
Removal of all
internal in ground
water services
3 days Wed
8/19/15
Fri
8/21/15 50
Principal
Surveyor
(Registered) ,P
roject Engineer
,Survey
Assistant ,Surv
ey
Draftsperson
Auto
Scheduled INCIDENTALS 23 days Mon
8/24/15
Wed
9/23/15 30
Auto
Scheduled Fencing 3 days Mon
8/24/15
Wed
8/26/15
Auto
Scheduled
Fence Type T 3 days Mon
8/24/15
Wed
8/26/15
Survey
Assistant ,Surv
Document Page
ey
Draftsperson ,
Surveyor
Auto
Scheduled
Removal of
Existing Fences 3 days Thu
8/27/15
Mon
8/31/15 53
Project
Engineer ,Stru
ctural
Engineer,
Survey
Assistant
Auto
Scheduled
Power Supply
Disconnection 5 days Tue
9/1/15
Mon
9/7/15 55
Auto
Scheduled
Works by
ActewAGL 3 days Tue
9/1/15
Thu
9/3/15
Survey
Assistant ,Surv
ey
Draftsperson
Auto
Scheduled
Works by the
Contractor 2 days Fri
9/4/15
Mon
9/7/15 57
Project
Engineer ,Stru
ctural
Engineer,
Survey
Assistant ,Surv
ey
Draftsperson
Auto
Scheduled
Comms Supply
Disconnection 4 days Tue
9/8/15
Fri
9/11/15 56
Auto
Scheduled Works by Telstra 2 days Tue
9/8/15
Wed
9/9/15
Project
Engineer ,Surv
ey
Assistant ,Surv
ey
Draftsperson
Auto
Scheduled
Works by the
Contractor
2 days Thu
9/10/15
Fri
9/11/15
60 Contractor,
Contractor
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Assistant
Auto
Scheduled
Gas Supply
Disconnection 4 days Mon
9/14/15
Thu
9/17/15 59
Auto
Scheduled
Works by
ActewAGL 2 days Mon
9/14/15
Tue
9/15/15
Asbestos
Removalist
Labourer ,Asb
estos
Removalist
Supervisor
Auto
Scheduled
Works by the
Contractor 2 days Wed
9/16/15
Thu
9/17/15 63 Contractor
Auto
Scheduled Site Establishment 9 days Mon
8/24/15
Thu
9/3/15
Auto
Scheduled
Supply, install,
and maintain hoardings
and temporary fences
3 days Mon
8/24/15
Wed
8/26/15
Site
Foreman ,Surv
ey
Assistant ,Surv
ey
Draftsperson
Auto
Scheduled
Undertake a full
dilapidation survey of
the site
3 days Thu
8/27/15
Mon
8/31/15 66
Contractor,
Contractor
Assistant,
General
labourer ,Proje
ct Engineer
Auto
Scheduled
Install and
maintain clearly
signposted and safe site
access gates.
3 days Tue
9/1/15
Thu
9/3/15 67
Contractor,
Contractor
Assistant,
General
labourer ,Proje
ct
Engineer ,Stru
ctural Engineer
Document Page
Auto
Scheduled
Approvals and
Documentation 14 days Fri
9/4/15
Wed
9/23/15 65
Auto
Scheduled
Prepare and
submit a Building
Application and engage
Building Certifier for
works
2 days Fri
9/4/15
Mon
9/7/15
Contractor,
Project
Engineer ,Stru
ctural Engineer
Auto
Scheduled
The Contractor
shall prepare and
submit a TTM plan
3 days Tue
9/8/15
Thu
9/10/15 70
Contractor,
Contractor
Assistant
Auto
Scheduled
The Contractor is
to provide program and
methodology
3 days Fri
9/11/15
Tue
9/15/15 71
Contractor,
Contractor
Assistant,
Project
Engineer
Auto
Scheduled
Submit for
approval a demolition
method statement
3 days Wed
9/16/15
Fri
9/18/15 72
Contractor,
Contractor
Assistant,
Project
Engineer ,Seni
or
Environmental
Consultant ,Str
uctural
Engineer
Auto
Scheduled
Provide worksas
executed drawings per
current ACT
Government reference
documents recording
all works, including
service terminations.
3 days Mon
9/21/15
Wed
9/23/15 73
Contractor,
Project
Engineer ,Stru
ctural Engineer
Auto LANDSCAPE 12 days Thu Fri 69
Document Page
Scheduled 9/24/15 10/9/15
Auto
Scheduled Topsoil 2 days Thu
9/24/15
Fri
9/25/15
Contractor,
Environmental
Consultant ,Pr
oject
Engineer ,Seni
or
Environmental
Consultant
Auto
Scheduled
Site topsoil to grass
areas 2 days Mon
9/28/15
Tue
9/29/15 76
Contractor,
Environmental
Consultant ,Pr
oject Engineer
Auto
Scheduled
Topsoiling (Type
C) 2 days Wed
9/30/15
Thu
10/1/15 77
Contractor,
Environmental
Consultant ,Se
nior
Environmental
Consultant
Auto
Scheduled Grassing 2 days Fri
10/2/15
Mon
10/5/15 78
Contractor,
Environmental
Consultant ,Pr
oject
Engineer ,Seni
or
Environmental
Consultant ,Str
uctural
Engineer
Auto
Scheduled
Dryland Grass 2 days Tue
10/6/15
Wed
10/7/15
79 Contractor,
Environmental
Consultant ,Pr
oject
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Engineer ,Seni
or
Environmental
Consultant
Auto
Scheduled
Bitumen and Straw
Mulching 2 days Thu
10/8/15
Fri
10/9/15 80
Contractor,
Contractor
Assistant,
Principal
Surveyor
(Registered) ,S
enior
Environmental
Consultant
Auto
Scheduled DEMOLITION 85 days Mon
10/12/15
Tue
2/23/16 75
Auto
Scheduled
Hazardous
Materials Removal 2 days Mon
10/12/15
Tue
10/13/15
Asbestos
Removalist
Labourer ,Asb
estos
Removalist
Supervisor,
Contractor,
Project
Engineer
Auto
Scheduled
Hazardous
materials, lead paint,
PCBs, SMFs & ODS
3 days Wed
10/14/15
Fri
10/16/15 83
Asbestos
Removalist
Labourer ,Asb
estos
Removalist
Supervisor,
Contractor,
Project
Engineer
Document Page
Auto
Scheduled
Asbestos
Containing Materials
(ACM’s)
3 days Mon
10/19/15
Wed
10/21/15 84
Arborist ,Asbe
stos
Removalist
Labourer ,Cont
ractor, Project
Engineer
Auto
Scheduled
Removal and
disposal of all
hazardous materials as
identified in 'Hazardous
Material Survey &
Management Plan’
Robson Intrusive report
4 days Thu
10/22/15
Tue
10/27/15 85
Arborist ,Contr
actor, Project
Engineer ,Stru
ctural Engineer
Auto
Scheduled Air Monitoring 2 days Wed
10/28/15
Thu
10/29/15 86
Environmental
Consultant ,Pr
oject
Engineer ,Seni
or
Environmental
Consultant
Auto
Scheduled
Environmental
Clearances to proceed
with the demolition
works.
3 days Fri
10/30/15
Tue
11/3/15 87
Contractor,
Environmental
Consultant ,Pr
oject
Engineer ,Seni
or
Environmental
Consultant
Auto
Scheduled
Underground Fuel
Storage Tank (UST)
3 days Wed
11/4/15
Fri
11/6/15
88 Contractor,
Environmental
Consultant ,Pr
oject
Engineer ,Seni
Document Page
or
Environmental
Consultant
Auto
Scheduled
Establish and
maintain environmental
controls in accordance
with RAP
2 days Mon
11/9/15
Tue
11/10/15 89
Contractor,
Environmental
Consultant ,Se
nior
Environmental
Consultant ,Se
nior Surveyor
Auto
Scheduled
Excavate and
stockpile spoil at AEC
(UST)
2 days Wed
11/11/15
Thu
11/12/15 90
Contractor,
Environmental
Consultant ,Pr
oject
Engineer ,Seni
or
Environmental
Consultant ,Su
rveyor
Auto
Scheduled
Remove and
dispose of pipes, valves
and vent lines
associated with UST
3 days Fri
11/13/15
Tue
11/17/15 91
General
labourer ,Contr
actor Assistant
Auto
Scheduled
Remove and
dispose of UST 3 days Wed
11/18/15
Fri
11/20/15 92
Asbestos
Removalist
Labourer ,Gen
eral labourer
Auto
Scheduled
Validation
sampling of stockpile
(1 round)
3 days Mon
11/23/15
Wed
11/25/15
93 Contractor,
Contractor
Assistant,
General
labourer ,Proje
ct
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Engineer ,Stru
ctural Engineer
Auto
Scheduled
Removal and
disposal of stockpile
spoil including all fees
3 days Thu
11/26/15
Mon
11/30/15 94
Contractor
Assistant,
Environmental
Consultant ,Pr
oject Engineer
Auto
Scheduled
Additional
validation sampling 4 days Tue
12/1/15
Fri
12/4/15 95
Asbestos
Removalist
Supervisor,
Contractor,
Contractor
Assistant,
Project
Engineer ,Stru
ctural Engineer
Auto
Scheduled
Additional spoil
disposal 5 days Mon
12/7/15
Fri
12/11/15 96
General
labourer ,Proje
ct
Engineer ,Stru
ctural Engineer
Auto
Scheduled Unexpected Finds 1 day Mon
12/14/15
Mon
12/14/15 97
General
labourer ,Proje
ct
Engineer ,Stru
ctural Engineer
Auto
Scheduled
Demolition Works 4 days Tue
12/15/15
Fri
12/18/15
98 Asbestos
Removalist
Labourer ,Cont
ractor,
Environmental
Consultant ,Pla
nt
Document Page
operator ,Proje
ct
Engineer ,Seni
or
Environmental
Consultant ,Str
uctural
Engineer
Auto
Scheduled
Demolition of
Buildings 11 days Mon
12/21/15
Wed
1/20/16 99
Contractor,
Contractor
Assistant,
General
labourer ,Proje
ct
Engineer ,Stru
ctural Engineer
Auto
Scheduled
Demolition of
Minor Structures 9 days Thu
1/21/16
Tue
2/2/16 100
Contractor,
Project
Engineer ,Stru
ctural Engineer
Auto
Scheduled
Retaining Walls
(Brick) 3 days Wed
2/3/16
Fri
2/5/16 101
Contractor
Assistant,
Project
Engineer ,Stru
ctural Engineer
Auto
Scheduled
Courtyard Walls
(Brick) 3 days Mon
2/8/16
Wed
2/10/16 102
Project
Engineer ,Stru
ctural Engineer
Auto
Scheduled Concrete Stairs 3 days Thu
2/11/16
Mon
2/15/16 103
Contractor,
Project
Engineer ,Stru
ctural Engineer
Auto Light Poles, Light 3 days Tue Thu 104 Contractor,
Document Page
Scheduled Bollards, log barriers &
Signs etc. 2/16/16 2/18/16
Contractor
Assistant,
Project
Engineer ,Stru
ctural Engineer
Auto
Scheduled
Gas Meter Brick
Enclosure 3 days Fri
2/19/16
Tue
2/23/16 105
Contractor,
Contractor
Assistant,
Project
Engineer ,Stru
ctural Engineer
Resource allocation Status
Project Engineer
Site Foreman
Plant operator
General labourer
Principal Surveyor (Registered)
Senior Surveyor
Surveyorr
Survey Draftsperson
Survey Assistant
Arborist
Hygienist
Asbestos Removalist Supervisor
Asbestos Removalist Labourer
Senior Environmental Consultant
Environmental Consultant
Structural Engineer
Contractor
Contractor Assistant
0 hrs
200 hrs
400 hrs
600 hrs
800 hrs
1,000 hrs
1,200 hrs
1,400 hrs
Actual Work Remaining Work Baseline Work
Name Start Finish Remaining Work
Project Engineer Thu 1/1/15 Tue 2/23/16 1,312 hrs
Site Foreman Thu 1/1/15 Wed 8/26/15 168 hrs
Plant operator Tue 4/7/15 Fri 12/18/15 320 hrs
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
General labourer Thu 3/26/15 Wed 1/20/16 672 hrs
Principal Surveyor
(Registered)
Fri 1/9/15 Fri 10/9/15 224 hrs
Senior Surveyor Tue 1/6/15 Tue 11/10/15 280 hrs
Surveyorr Tue 1/6/15 Thu 11/12/15 176 hrs
Survey Draftsperson Fri 3/6/15 Wed 9/9/15 288 hrs
Survey Assistant Tue 1/6/15 Wed 9/9/15 320 hrs
Arborist Mon 10/19/15 Tue 10/27/15 56 hrs
Hygienist NA NA 0 hrs
Asbestos Removalist
Supervisor
Wed 5/27/15 Fri 12/4/15 136 hrs
Asbestos Removalist Labourer Wed 5/27/15 Fri 12/18/15 184 hrs
Senior Environmental
Consultant
Fri 2/6/15 Fri 12/18/15 512 hrs
Environmental Consultant Tue 4/28/15 Fri 12/18/15 336 hrs
Structural Engineer Thu 3/19/15 Tue 2/23/16 872 hrs
Contractor Thu 1/15/15 Tue 2/23/16 1,048 hrs
Contractor Assistant Thu 1/15/15 Tue 2/23/16 648 hrs
Resource Cost Allocation
Name Actual Work Actual Cost Standard Rate
Project Engineer 0 hrs $0.00 $250.00/hr
Site Foreman 0 hrs $0.00 $250.00/hr
Plant operator 0 hrs $0.00 $300.00/hr
General labourer 0 hrs $0.00 $450.00/hr
Principal Surveyor 0 hrs $0.00 $250.00/hr
Document Page
(Registered)
Senior Surveyor 0 hrs $0.00 $300.00/hr
Surveyorr 0 hrs $0.00 $350.00/hr
Survey Draftsperson 0 hrs $0.00 $350.00/hr
Survey Assistant 0 hrs $0.00 $400.00/hr
Arborist 0 hrs $0.00 $350.00/hr
Hygienist 0 hrs $0.00 $250.00/hr
Asbestos Removalist
Supervisor
0 hrs $0.00 $350.00/hr
Asbestos Removalist
Labourer
0 hrs $0.00 $300.00/hr
Senior Environmental
Consultant
0 hrs $0.00 $350.00/hr
Environmental
Consultant
0 hrs $0.00 $200.00/hr
Structural Engineer 0 hrs $0.00 $400.00/hr
Contractor 0 hrs $0.00 $500.00/hr
Contractor Assistant 0 hrs $0.00 $400.00/hr
Document Page
$0.00
$100,000.00
$200,000.00
$300,000.00
$400,000.00
$500,000.00
$600,000.00
Actual Cost Remaining Cost Baseline Cost
Overall Project Cost Flow
Name Remaining
Cost
Actual
Cost
Cost ACWP BCWP BCWS
DEMOLITION
PROJECT
$2,699,600.00 $0.00 $2,699,600.00 $0.00 $0.00 $0.00
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Overall Resource Cost
Name Cost Baseline
Cost
Cost
Variance
Project Engineer $328,000.00 $0.00 $328,000.00
Site Foreman $42,000.00 $0.00 $42,000.00
Plant operator $96,000.00 $0.00 $96,000.00
General labourer $302,400.00 $0.00 $302,400.00
Principal Surveyor
(Registered)
$56,000.00 $0.00 $56,000.00
Senior Surveyor $84,000.00 $0.00 $84,000.00
Surveyorr $61,600.00 $0.00 $61,600.00
Survey Draftsperson $100,800.00 $0.00 $100,800.00
Survey Assistant $128,000.00 $0.00 $128,000.00
Arborist $19,600.00 $0.00 $19,600.00
Hygienist $0.00 $0.00 $0.00
Asbestos Removalist
Supervisor
$47,600.00 $0.00 $47,600.00
Asbestos Removalist
Labourer
$55,200.00 $0.00 $55,200.00
Senior Environmental
Consultant
$179,200.00 $0.00 $179,200.00
Environmental
Consultant
$67,200.00 $0.00 $67,200.00
Structural Engineer $348,800.00 $0.00 $348,800.00
Contractor $524,000.00 $0.00 $524,000.00
Contractor Assistant $259,200.00 $0.00 $259,200.00
Document Page
The MS Project File is attached here.
17. Conclusion
In this project management system we are discussed, analysed and constructed
the management works. These section covered by how to prepare a safety and health plan to
the organisational work. We are designed the constructional work and also protect the
environmental status and traffic management planning’s. It also covers how to save the
building, during the demolition processes. This project management used to protect the
building around the constructional areas. The activities are associated with demolition
process. the potential for incidents is well understood and the management process of the
demolition activities will be minimized. The hazards and risk assessments of the demolition
works has found and analysed to the biophysical environment and also safe the public,
contractors and working staffs.
References
chevron_up_icon
1 out of 39
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]