This document presents a detailed professional profile of an Industrial Engineer with over 13 years of experience in planning and project control within various EPC projects. The summary highlights key responsibilities such as preparing and maintaining project schedules using Primavera P6, conducting critical path analysis, and preparing project status reports. The engineer's experience includes working on combined cycle power plant projects, cement factory projects, and other industrial projects, demonstrating proficiency in all phases from design to commissioning. The profile also showcases expertise in managing project budgets, resource allocation, and stakeholder communication, with a strong emphasis on achieving project milestones and delivering projects on time and within budget. The engineer's skills include PMBOK methodologies, contract management, and excellent communication abilities, making this a valuable example of project management expertise.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
NAME
Mobile: E-mail:
Address:
CAREER PROFESSIONAL
A professional Industrial Engineer with more than 13 years of progressive experience in
Planning and Project Control of various EPC projects as the consultant and client. Strong
working knowledge of project management methodologies, tools, and techniques (PMBOK)
Familiar with contract concepts, engineering documents, and drawings. Highly motivated and
comprehensive mind, high ability of team working and good communication skills.
EDUCATIONAL QUALIFICATION
Bachelor of Science in Industrial Engineering
Shahid Bahonar Kerman University [2001]
WORK EXPERIENCE
MAPNA Group , MAPNA MD1
Project Planner / Scheduler
May, 2016 to Current
Key Responsibilities:
Prepare EPC Level 3 Schedule in the Combined cycle power plant Industries
Prepare Proposal schedule
Analysis of modifications to the to the project schedule
Monitor and document monthly progress for assigned projects including critical path
analysis, and schedule narratives
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Update and close schedules to support month end close and periodic reporting.
Prepare weekly and monthly project schedule status reports for project managers
Prepare, baseline, status, maintain and report project schedule
Deploy standard work breakdown structure, coding, analysis and reports for project
schedules maintained
Analyze detailed plans, development of recovery plans by engaging subcontractors inputs for
materials, resources and tools
Planning, scheduling, status and reporting progress of all site activities from contract award
to contract closeout through engineering, procurement, construction, commissioning.
Afagh Energy Pars Company, Kahnooj combined cycle Power plant, Iran
Planning and project control supervisor
March, 2013 to May, 2016
Key Responsibilities:
Provided/developed resource/cost loaded project time schedule (Oracle Primavera Project
Management Software) including Basic & Detail Design, Tendering, Supply/Manuf.,
Transportation, Construction (Civil/Structural, Mechanical, E&I) & Commissioning
activities and milestones both independently and team environments
Provided/developed project WBS and coding
Prepared project scheduling and progress measurement procedures
Prepared, analyzed and monitored project progress reports based on critical path method
(CPM) including critical activities and milestones to determine the effect of changes in the
schedule and make recommendations for corrective actions and recovery plan, S-Curve
(Plan, Actual & Look ahead Forecast), updated time schedule, performance report, and
Document Page
schedule narratives from contract award to contract closeout through (Monthly, Weekly,
Daily)
Attended progress review meetings with main stakeholders such as client, senior managers,
project team, and subcontractors to present, analyze and propose modifications to the project
schedule, critical path, materials, resources and tools
Reviewed and analyzed of contractor’s delays based on Time Impact Analysis (TIA).
Tosee Siloha Company, Tehran Cement Factory, Iran
Planning and Project Supervisor
December, 2011 to December, 2012
Key Responsibilities:
Preparing Master and Detailed Schedule in form of MSP software for Tehran Cement Plant
project.
Preparing daily, weekly and monthly reports for the client.
Applying Earned Value Technique (EVT) as a tool for controlling and predicting cost and
time of project and appropriate future estimation in the project.
Cooperating with workshop financial assistance for unification of accounting and project
control systems via project WBS. Cooperating with workshop technical and financial office
in cost estimating and also sending quarter reports of income and cost to the headquarters.
Determining performance indexes (past performance indexes and future performance
indexes) for the project.
Presenting Cash Flow chart to project management.
Preparing required documents for company’s future claims.
Document Page
MAPNA Gropu, Mapna MD2, Jandar combined cycle Power plant, Syria
Planning and Project Control expert
June, 2010 to December, 2011
Key Responsibilities:
Attended progress review meetings with client and senior managers to review project
variance report and project progress S-curves on monthly bases
Supported Project Managers and Project Controls team in their daily activities and managed
associate planner issues
Produced and reviewed project master Work Breakdown Structure (WBS) & Critical Path
Method (CPM) based planning with an emphasis on accuracy of scope, time, and cost
Organized and reviewed integrated baseline schedules to ensure all packages have realistic
and logically linked schedules for tracking and reporting during FEED and EPC execution
(using Oracle PrimaveraP6, network diagram and Gantt chart view)
Identified and monitored critical pathways in the schedule (package and master level) and
prepare Critical Action Item Report for monthly progress review meetings
Established Master Time schedule to monitor interfaces, contract and payment milestones
Prepared earn value analysis reports and calculating cost performance index (CPI) and
schedule performance index (SPI) for all WBS packages and entire program
Identified any deviations from baseline plan, prepared recovery action plan, highlighted
milestones in project lifecycle and updated all Contract Deliverables (CDRLs) throughout the
life of the project.
Mapna MD2 Company, Damavand combined cycle Power plant, Iran
Project Planner / Scheduler
June, 2009 to June, 2010
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Key Responsibilities:
Prepared level three (3) Master ( Baseline) time schedules: Conceptual, Basic & Detail
Design, Tendering, Supply/Manufacturing, Transportation, Civil, Erection& Commissioning
Activities
Managed junior level planners within organization
Developed project budgets, administered bidding process, verified contract expenditures and
compliance
Established and monitored performance metrics relevant to project planning
Determined resources requirements and supervised progress
Approved WBS a level 4 time schedule for subcontractors (including weight percent).
Tosee Siloha Company, Damavand combined cycle Power plant, Iran
Project Planner / Scheduler Lead
April, 2007 to June, 2009
Key Responsibilities:
Presented progress reports including S-Curve (Plan, Actual & Forecast) and critical activities
to the senior management team and clients
Conducted site visits and meet with subcontractors to monitor the project progress
Prepared and maintained overall timing plan for project, resource assignment, estimating and
preparation of progress measurement system (PMS)
Revised Work Breakdown Structures (WBS) for project phases (EPC) according to the
contract
Maintenance and analysis of schedule (Basic & Detail Design, Tendering, Supply, Civil,
Erection & Commissioning)
Document Page
Reviewed schedules and cost estimates prepared by contractor.
Norahan Sanaye Company, Yazd combined cycle Power plant, Iran
Planning and Project Control expert
January, 2005 to April, 2007
Key Responsibilities:
Managing the planning and controls functions for projects
Responsible for tracking and monitoring progress of project office as well as coordinate
delivery date
Prepared development and maintenance of project plans including Civil, mechanical,
Electrical, piping, works
Liaised with clients to obtain information for project controls, planning, scheduling, and
project management support.
Defense Industries Organization, Tehran, Iran
Production Line Planner
October, 2003 to January, 2005
AWARDS AND ACCOMPLISHMENTS
Top student of Industrial Engineering during college years
Receiving commendation from manager of Jandar Power plant as one of the five
effective experts in the project
Document Page
Receiving commendation in Yazd Power Plant cooling system project for impressive and
creative activities and teamwork.
Key Skills
PMBOK 2016
Presentation and teaching
Public Speaking
Ability for strong management
and teamwork
Excellent interpersonal skills
Bilingual (English – Persian)
Adobe Photoshop
Familiar with standards of quality assurance
management system
Computer and Internet Literate
Primavera 3.1 & 6
Microsoft Project
Microsoft Office Proficiency
Management Skills
chevron_up_icon
1 out of 7
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]