Project Management Report

Verified

Added on  2020/02/03

|22
|7415
|52
Report
AI Summary
This report provides a detailed analysis of a project management case study involving the development of a six-story hotel and swimming pool. It covers various aspects of project management, including background and principles, investment viability assessment (using NPV and payback period calculations), organizational structure, resource allocation, project scheduling (using PERT and Gantt charts), performance measurement methods, and change control procedures. The report also includes a detailed project plan, outlining tasks, durations, and dependencies. The analysis demonstrates the application of project management tools and techniques to minimize time and costs, manage risks, and ensure successful project completion. The report concludes with a post-project appraisal, highlighting lessons learned and areas for improvement.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
TABLE OF CONTENTS
INTRODUCTION................................................................................................................................4
TASK 1.................................................................................................................................................4
1.1 Describing the background and principles of project management...........................................4
1.2 Appraising the viability of the investment in the hotel and swimming pool and develop a
success and failure criteria...............................................................................................................6
1.3 Principles behind project management systems and procedures...............................................7
d. Key elements involved in terminating projects and conducting post-project appraisals.............8
TASK 2.................................................................................................................................................9
2.1 Identification of the most appropriate organizational structure, roles and responsibilities of
participants of the project................................................................................................................9
2.2 Explaining how the structure identified above would help in control and co-ordinate the
project............................................................................................................................................10
2.3 Assessing the leadership style and qualities required to manage the above project
successfully....................................................................................................................................11
2.4 Planning and specifying human resources requirements for the proposed project..................12
TASK 3...............................................................................................................................................13
3.1 Preparing a detailed project plan for the proposed project......................................................13
3.2 Applying the appropriate project scheduling tools to plan the project activities so as to
minimise the time and costs of the project....................................................................................14
3.3 Analysing the methods used to measure project performance.................................................15
3.4 Explaining the change control procedure for evaluating project at its completion.................15
CONCLUSION..................................................................................................................................15
REFERENCES...................................................................................................................................17
1
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
LIST OF FIGURES
Figure 1 Project Management Timeline...............................................................................................5
2
Document Page
INTRODUCTION
The past several decades have been stated by rapid growth in the use of project management
as a means by which organizations achieve their objectives. Building a new skyscraper, designing a
commercial ad campaign, launching a rocket etc are some examples of this concept. The present
research is based on project management and to understand this, a case study is taking into the
consideration. As per the given case scenario, Alan, Joy, Shab and Sudjat are four partners who are
running a restaurant in Borehamwood, near London from last 5 years. Organization has made 2
million profits in previous year and on the basis of this, the capital base of partners have become 3
million. According to long term strategy, it has planned by the owners of restaurant to build a 6
storey hotel which will contain a swimming pool in Borehamwood. This will serve both community
and business customers from overseas locations. In this regards, the 4 managers have already talked
with the bank manager for grant a loan of £1.5 million pounds on 10% interest rate. Before starting
the project, Joy has disused it about a management consultant who is specialising in hotels.
According to him, it will not worth full for the company if they will hold it after the development.
So, management consultant has advice the owners to make money by selling the new 6 start hotel
and reinvest the amount in new opportunities.
TASK 1
1.1 Describing the background and principles of project management
Background
At the time of Second World War, the concept of project management has developed. In the
late of 50’s and early of 60’s, project management was applied by civil sector for various
developments. This was the time frame where diverse tools and techniques related to project
management like CPM, PERT etc. Along with this development, integrated computer systems have
evolved (Harpham, 2003). These were able to deliver the quality work under the set time, costs and
other limitations. On the other hand, in 1980-1994, a revolutionary development in the Information
management has taken place with the introduction of Personal Computer (PC) and other network
facilities. These were highly efficient in managing and controlling of complex project schedules
(Kerzner, 2013). From 1995 to present, development related to the internet has changed business
practices. The result of this is many of the project management related software have directly
connected with internet and it has provided interactive, fast and customized mode to manage simple
to complex projects in easier manner.
3
Document Page
Figure 1 Project Management Timeline
(Source: Harpham, 2003)
Principles of Project Management:
Vision and mission: For a successful execution of a project, vision and mission of plan
should be clear for all members of project team. It assists in clarify the expected results and
develops strategies to attain them. Moreover, it gives a proper path to be followed for achieving
results.
Business objectives: Here, some objectives related to project develops by responsible
project team members. It is significantly gives the contribution in the direction of success of the
plan (Burke, 2013). The SMART and concrete objectives help in achieving desired results with
better efficiency.
Standards of engagement: This is means setting of standards related to how will become a
part of the project team. There are several parameters and protocols designing to clarify objectives
of the project (Kshama, 2012). These parameters act as a factor according to which quality of work
can be enhanced.
Intervention and execution: With the help of various methods and techniques, gaps in the
expected and actual deliverables determine. This assists in minimize or resolving the issues that
may affect the final outcomes of the plan (Burke, 2013). This step helps in making corrective
actions as well to reduce the chances of errors.
Organizational alignment: By ongoing communication concept such as meetings, mails
etc, different and important information easily communicates with the team members. This ensures
4
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
the success of the project by engaging the teams.
Measurement and accountability: This is the important principles of project management
in which various methods use to measure the success of the plan on different criteria and aspects. It
reflects over the areas where improvement must be needs to attain the objectives of project
(Schwalbe, 2015).
1.2 Appraising the viability of the investment in the hotel and swimming pool and develop a success
and failure criteria
As per the given case study, it has found that Alan, Joy, Shab and Sudjat have run a
restaurant in Borehamwood, London from last five years ago. They have made 2 million profits
from the business in previous year. Now, the managers have planned to open a 6 star hotel and it
will contain a swimming pool. The initial investment for hotel has £4m and swimming pool has
£1.5m. In this context, it has become important to appraise the viability of the investment in the
hotel and swimming pool to decide success and failure criteria of the plan.
Hotel
Years Cash flow in
£m
PV factor at
10%
Present value
(in £m)
1 600 0.9091 545460
2 600 0.8264 495840
3 600 0.7513 450780
4 600 0.6830 409800
5 950 0.6209 589855
Total 2491735
Initial investment 4
NPV -1508265
Swimming pool
Years Cash flow in
£m
PV factor at
10%
Present value
(in £m)
1 300 0.9091 272730
2 300 0.8264 247920
3 300 0.7513 225390
4 300 0.6830 204900
5 1300 0.6209 807170
5
Document Page
Total 1758110
Initial investment 1.5
NPV +258110
Payback period for Hotel
Year Cash inflow in £m
1 600
2 600
3 600
4 600
5 950
Total 3350
Analysis No Money Back after five years
Payback period for Hotel
Year Cash inflow in £m
1 300
2 300
3 300
4 300
5 1300
Total 2,500
300 x 12 = 36
1300
36
13 =2.7
Analysis Money back after 4 years and 2.7 months
Success and failure criteria
From the above both of the tables of NPV for hotel and swimming pool, it has tried to
determine the viability of the investment in both of the project. NPV value of hotel has showed after
the 5 years, new present value of the investment at 10% interest rate has become negative. It has
demonstrated that restaurant will not recover the invested amount after 5 years. While in the case of
6
Document Page
swimming pool project, initial investment will cover after completion of 5 years and it will give
positive net present value of funds. So on the basis of the above discussion, it can be said that value
of NPV will work as both success and failure criteria for hotel and swimming pool project.
The major criteria on which the project's success and failure can be decided is its timely
delivery. The technical requirements which are necessary for making this project successful should
be arranged after making a check for all the sources that are required for it in advance manner. In
addition to this, it is necessary to give a due consideration to the stakeholders without which the
project's success cannot be attained. It has been noticed that risk assessment aspects also being
discussed effectively so that better outcomes can be attained. Insufficient regards in context to cash
flow might be affected so management need to consider it effectively. Stakeholders involvement in
the project is also significant because it allows to improve the overall performance.
1.3 Principles behind project management systems and procedures
Systems for allocating time and cost
Resources levelling: Under this method, the adjustment in start and finish dates of tasks
have based on the resources constraints with the aim of maintain the balance between the demands
of resources with the availability of supplies. With the help of resource levelling system, it will
become easy to make changes in beginning and ending duration of project plan of opening of 6
storey hotel as per the accessibility of resources within the particular time duration. It is considering
as the most effective technology in terms of both time and costing (Wysocki, 2011).
Activity based costing: In this, the cost for each activity assigns along with all resources as
per the real consumption of each one. It will assist the opening of 6 storey of hotel and swimming
pool project to effectively utilize the funds and resources by minimizing the spending over the
unnecessary expenses (Walker, 2015).
Process of integrate material and human resources
To allocate material and human resources in more effective manner, a systematic process can
be used by opening of 6 storey hotel project which is as follows:
1. By finding the real requirements and needs of material and human resources for the planned
project (De Bakker, Boonstra and Wortmann, 2010).
2. Preparing resource allocation plan as per the determine supplies needs.
3. By arranging human and material resources with the aim of meeting the objectives and
deliverables of project.
4. Resource plan implementation process carry out by considering the different factors such as
abilities and skills of the team members, priorities of the activities etc (Jun, Qiuzhen and
7
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Qingguo, 2011).
5. By regular meetings and other techniques, monitoring and control process related to
performance improvement of plan, human resources and optimal utilization of materials can
be done.
6. Changes in current plan to attain the objective of opening of 6 storey hotel project (Jun,
Qiuzhen and Qingguo, 2011).
7. Analyze the outcomes of the work can be carried out by assessing resources allocation plan.
Objectives
The objecticves to be set for the project should be based on SMART criteria. This will help
in proiper allocation of tasks among concerned workers and clarifying their roles. Besides this,
expectation of company will be also clear for them according to which they will work on the
project.
Adaptability
The project should be planned in a proper way with a scope of making changes in easier way
so that in condition of changes, the plan can be adjusted accordingly.
Integration
The integration is a process in which various activities are incorporated in a proper way so
that all tasks can be accomplished with a better link.
Input and output
The input and output of materials is a necessary process in which it is necessary to arrange
the resources in appropriate way as per the need. Thus, it will help in accomplishment of work on
time with less number of flaws.
d. Key elements involved in terminating projects and conducting post-project appraisals
Key elements of project termination process
In project management, Project termination is a very important section that can be taken at
any stage of the plan by a project team. Most common reasons of take this type of decisions are less
profitability, technical issues, delay from supplies sides, finance issues etc. There are four types of
project termination: integration, starvation, addition and extinction. These are the most essential
sections where it assists to terminate the project at any stage. The major elements of project
termination are cost, time, legal requirements, audits logs, payments of bills, closing the different
contracts, transferring of software, reports and data to the firm, etc (Artto, Kulvik, Poskela and
Turkulainen, 2011). In cost factor, project manager has to compare actual and expected costing of
the plan and then terminate the contract. Along with this, all legal requirements related to
8
Document Page
cancelation of contracts with complete formalities also require to carry out. Apart from this,
transfer of rights and releasing of resources also takes place. These all have needed to be considered
in the case of closing or termination of opening of 6 storey of hotel and swimming pool project.
Post project appraisal
The reason of using post project appraisal is to assess the outcomes of the plan by
considering various factors. The post project appraisal is important as it is a strong way to have a
continuous improvement in project. This gives greater opportunities for entire project team to have
a discussion on what went good and things which went wrong. All this discussion helps in making
good decision and plans which will be an advantage for the next projects which would be made on
the basis of improved skills. In the case of opening of 6 storey hotel project, process of post project
appraisal is as follows:ï‚· Conduct variance analysis: It assists in find the variations between expected and actual
results related to opening of 6 storey of hotel and swimming pool project (Wu and Low,
2010).ï‚· Cost benefit analysis: The initial costing of opening of 6 storey of hotel and swimming pool
project will be high but in the future, it will deliver various benefits to restaurant. So, with
the help of cost benefit analysis, the owners of the organization will predict the profits of
future.ï‚· Risk analysis and its review: Under this, risk analysis process will carry out to minimize the
impact of uncertainties over opening of 6 storey of hotel and swimming pool project
(Bredillet, Yatim and Ruiz, 2010).
ï‚· Recognising achievements of the project: Here, the achievements of project team members
will recognize with effective methods. This will highlight the learning and skills of team
members in terms of experience (Mantel, 2011).
ï‚· Identification of things which performed well- The appraisal of project can be done by
making an analysis on things which went well so that this can be used as a factor in next
projects for making it better.
ï‚· Identifying things that can be improved: Another requirement which can be applied for post
project appraisal is identifying those points which have a scope of improvements. So, some
extra efforts can be made to make some improvements which can help in improving the
quality of project.
The project's post appraisal is necessary so that the work can be checked and it can be
determined that the tasks have been accomplished in a better way. The
9
Document Page
TASK 2
2.1 Identification of the most appropriate organizational structure, roles and responsibilities of
participants of the project
Organizational structure
The organizational structure of opening of 6 storey of hotel and swimming pool project will
be Project based structure. The reason of selecting the following one is to allocate the roles and
responsibilities to the team members as per their skills and capabilities. It will create a good
communication channel between the team personnel (Patanakul, Iewwongcharoen and Milosevic,
2010). In addition to this, the project based structure is best suitable for those businesses that need
to make frequent changes and innovations in their working practice. This structure provides enough
scope for flexibility and also gives opportunity to execute diverse works as quickly as possible.
Therefore, in current strategy of opening a hotel, the project based structure will be best suitable so
that firm can make suitable changes as and when needed. Matrix type of organisational structure is
not suitable as it creates the dual reporting reponsibility of workers whcih may create the
confusions.
Roles and responsibilities of participants of the project
For opening of 6 storey of hotel and swimming pool project, human resources will require
which will contain various skills and capabilities to attain the expected outcomes of the plan. The
major personal needed for the plan are project manager, project board, management consultant,
architecture, quality analyst, risk analyzer and other supportive team members. These all will give
contribution in planned work to accomplish the objectives (Bredillet, 2010).
Participants Roles and responsibilities in the form of job description
Project manager Manage project tasks.
Assigning roles and responsibilities to team members
Formulation and implementation of plan
Arrange and allocating different resources (Lee and Yu, 2012).
Architecture Developing a architect of building and its other related components
Quality analyst Accountable for the quality of the project.
Ensure the quality of new 6 storey of hotel and swimming pool project
Management
consultant
Responsible for advising the project board related to construction of
planned project.
10
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Assist the suggestions where to invest or not to invest the funds (Hwang
and Tan, 2012).
Project board Analyse the issues and changes in project plan, finalize the project plan,
approve resource allocation etc.
Risk analyzer Assess the risks at different stages of the project plan and develop the
strategies to minimize the impacts of these on the final outcomes.
Other supportive team
members
Transform the ideas into the actions, determine the needs of client etc
(Portny, 2010).
2.2 Explaining how the structure identified above would help in control and co-ordinate the project
Control and co-ordination, these two are most essential things in project management. Both
have helped assess and monitor the performance of project plan. With the application of this, project
manager and its team members can manage the whole work in an effective manner at all stages. In
the case of opening of 6 storey of hotel and swimming pool project, the selected organizational
structure has project management design. This has assisted in keeping the control over progress of
proposed plan and has established the co-ordination between different activities. Along with this, it
has aided in scheduling as well as allocation of resources to project stages. To establish control and
co-ordinate with project management organizational structure, several techniques have used by
project manager. These are Work Breakdown structured, Product Breakdown structured and Gantt
chart. By using WBS technique, the whole project plan of 6 storey of hotel and swimming pool
project has divided into the manageable section in the form of small sections (Patanakul and
Shenhar, 2012). It has also focused over the right and optimal utilization of the resources. While,
Gantt chart has assisted the project manager to measure the growth of proposed plan to ensure that
work is going as per the set procedure and schedule or not. Along with this, to establish control and
co-ordinate the 6 storey of hotel and swimming pool project, roles and responsibilities of project
team members have played an essential role. The tasks perform by project manager and other
members have demonstrated their skills and abilities. From the above discussion, it has been clear
that project organizational structure has helped in establish in control and co-ordinate the proposed
project (Morris, 2010).
11
Document Page
2.3 Assessing the leadership style and qualities required to manage the above project successfully
The project manager of 6 storey of hotel and swimming pool project has needed some
leadership qualities and style to manage the planned project in successful manner. In this context,
assessments of these superiorities are as follows:
Problem solver: Project manager of 6 storey of hotel and swimming pool project should
having the sense of solving the problem. This assists him or her to find the solutions of issues in the
plan and select the best one to resolve them (Barry, 2015).
Time management style: Project manager of proposed plan should able to manage the time.
The reason to have such quality in him or her because this plan is complex and lengthy in nature.
So, to complete the assign work within the given timeframe, project manager need to manage the
time.
Team building skills: In 6 storey of hotel and swimming pool project, project manager
should capable to develop a good team of professions who can attain the objectives of the plan. For
this, he or she can build up team by using right leadership skills.
Work under pressure: The project manager of 6 storey of hotel and swimming pool project
should know how to manage the work under the pressure. The reason of this is sometimes, there
may be some activities which require being complete within in the small duration and it may create
a pressure over him(Killen and Hunt, 2010).
Good communicator: A project manager of 6 storey of hotel and swimming pool project
should be a good communicator. By establishing a clear and right communication with the team
members, vision and mission of the plan can be stated to team personnel in right way.
Integrity: Project leader of 6 storey of hotel and swimming pool project should honest and
loyal. This will create a best example in front of the team members (Morris and Pinto, 2010).
Empathy: Project leader of planned project should understand the requirements of team
members. In this context, he or she has to give proper attention towards various needs of personnel
in team by establishing personal relationship with them.
2.4 Planning and specifying human resources requirements for the proposed project
In the context of 6 storey of hotel and swimming pool project, there will be some and major
human resources requirements. For this, planning and specifications related to this is as follows:
12
Document Page
Human
resources
Time Working pattern Number of
human
resources
Sourcing Retirement
planning
Project manager Till the
completion of
project
As a leader to
lead the team
1 On contract
basis
No
Project board Till the
completion of
project
Team member 3 On contract
basis
No
Management
consultant
Till the
completion of
project
Team member 2 On contract
basis
No
Architecture Till the
completion of
project
Team member 2 On contract
basis
No
Quality analyst Till the
completion of
project
Team member 2 On contract
basis
No
Risk analyzer Till the
completion of
project
Team member 3 On contract
basis
No
Other supportive
team members
Till the
completion of
project
Team member 8 On contract
basis
No
From the above table it is necessary that about 21 people are required for a successful
execution of the tasks. As per this requirement, different people have allotted with various roles and
responsibilities. This quantity has been decided after proper planning of tasks according to which
the roles of staff has been allocated. 21 employees are enough to conduct this project as the
estimation entails this number clearly for performing the work. 1 project manager will be
responsible for supervising the entire project while 3 persons will be required in project
13
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
management board who will be required for executing the work properly as ordered. 2 members
will be needed as a management consultant who can give their advices and suggestions in context of
carrying out the project. Similarly, 2 architects will be there for designing the hotel and pool
structure. 2 members of quality analyst will be crucial in the project as they will analyse the quality
of work and project. 3 members in the risk analysing team will be there to have a check on various
risks that can be raised while conducting the project. They will also develop plans and procedures
through which risks can be minimised. In addition, there will be 8 members who will be responsible
for carrying out different functions and tasks which is required by the project. Due to this these
reasons 21 employees are selected.
TASK 3
3.1 Preparing a detailed project plan for the proposed project
Task Name Duration Start Finish Predecessors
6 storey of hotel and swimming pool
project 254 days Mon 2/13/17 Thu 2/1/18
Planning 20 days Mon 2/13/17 Fri 3/10/17
Gather information 11 days Mon 2/13/17 Mon 2/27/17
Develop wish list of client 4 days Tue 2/28/17 Fri 3/3/17 3
Approval of list from client 5 days Mon 3/6/17 Fri 3/10/17 4
Contracts 25 days Mon 3/13/17 Fri 4/14/17
Supply agreement 8 days Mon 3/13/17 Wed 3/22/17 5
Supply plans 9 days Thu 3/23/17 Tue 4/4/17 7
Supply specification 8 days Wed 4/5/17 Fri 4/14/17 8
Plan development 50 days Mon 3/13/17 Fri 5/19/17
Develop designs 7 days Mon 3/13/17 Tue 3/21/17 8
Reviews and final plans 6 days Wed 3/22/17 Wed 3/29/17 11
Review and final the specifications of
ground and rest floors rooms 9 days Thu 3/30/17 Tue 4/11/17 12
Review and final site plan 6 days Wed 4/12/17 Wed 4/19/17 13
Getting approval for the designs 7 days Thu 4/20/17 Fri 4/28/17 14
Approve the specifications of ground,
first and second floors rooms 9 days Mon 5/1/17 Thu 5/11/17 15
Print the designs 6 days Fri 5/12/17 Fri 5/19/17 16
Bids and contracts 72 days Wed 3/22/17 Thu 6/29/17
Prepare the copies of plans 7 days Wed 3/22/17 Thu 3/30/17 17
Prepare the copies of specifications 6 days Mon 5/22/17 Mon 5/29/17 19
Distribution of specifications and plans 6 days Mon 4/17/17 Mon 4/24/17 20
Invite the bids 5 days Tue 5/30/17 Mon 6/5/17 21
Receive the bids 6 days Tue 6/6/17 Tue 6/13/17 22
Finalize the suppliers 5 days Wed 6/14/17 Tue 6/20/17 23
Make the contract 7 days Wed 6/21/17 Thu 6/29/17 24
14
Document Page
Implementation of plan according to the
specifications 97 days Fri 6/30/17 Mon
11/13/17
Draw ground floor rooms 19 days Fri 6/30/17 Wed 7/26/17 25
Draw first floor rooms 13 days Thu 7/27/17 Mon 8/14/17 27
Draw second floor rooms 13 days Tue 8/15/17 Thu 8/31/17 28
Draw third floor rooms 13 days Fri 9/1/17 Tue 9/19/17 29
Draw four floor rooms 13 days Wed 9/20/17 Fri 10/6/17 30
Draw fifth floor rooms 13 days Mon 10/9/17 Wed 10/25/17 31
Draw sixth floor rooms 13 days Thu 10/26/17 Mon 11/13/17 32
Finishing of building 29 days Tue 11/14/17 Fri 12/22/17
Interior finishing in all rooms 4 days Tue 11/14/17 Fri 11/17/17 33
Plumbing 5 days Mon 11/20/17 Fri 11/24/17 35
Exterior finishing 6 days Mon 11/27/17 Mon 12/4/17 36
Fire and smoke detector devices
installation 5 days Tue 12/5/17 Mon 12/11/17 37
Floors finishing 3 days Tue 12/12/17 Thu 12/14/17 38
Final coat of paint on building 2 days Fri 12/15/17 Mon
12/18/17 39
Hardware installation 2 days Tue 12/19/17 Wed 12/20/17 40
Cleaning 2 days Thu 12/21/17 Fri 12/22/17 41
Monitoring 14 days Mon 12/25/17 Thu 1/11/18
Inspection 3 days Mon 12/25/17 Wed 12/27/17 42
Check the actual work with the given
specifications 2 days Thu 12/28/17 Fri 12/29/17 44
Identify the defects 4 days Mon 1/1/18 Thu 1/4/18 45
Corrective actions 5 days Fri 1/5/18 Thu 1/11/18 46
Project closure 15 days Fri 1/12/18 Thu 2/1/18
Developing project report 5 days Fri 1/12/18 Thu 1/18/18 47
Post implementation review 3 days Fri 1/19/18 Tue 1/23/18 49
Termination of various contracts 3 days Wed 1/24/18 Fri 1/26/18 50
Reassign resources 2 days Mon 1/29/18 Tue 1/30/18 51
Project hand over 2 days Wed 1/31/18 Thu 2/1/18 52
3.2 Applying the appropriate project scheduling tools to plan the project activities so as to minimise
the time and costs of the project
With the aim of scheduling of the proposed project plan for restaurant, there is different
tools used by the project manager. These are PERT and Gantt chart which is as follows:
PERT: Program Evaluation and Review Techniques has helped represented the lists of activities of
6 storey of hotel and swimming pool project with the respect of the time duration. It has used to
determine the major milestones and its subtasks along with their sequence. This has assisted in total
time estimation to complete the plan within the allocated time frame. It has facilitated the project
15
Document Page
manage to keep records of time of every tasks and compare it with the expected outcomes
(Kerzner, 2013).
Illustration 1: Network diagram
Gantt chart: It is used to show the activities against the time frame in project management. In the
case of 6 storey of hotel and swimming pool project, scheduling of the plan have presented in the
form of graphical. This has helped the project manager to plan, coordinate and control over the
project plan. It has defined the complete illustration of the status of plan without showing the
dependencies between activities (Nishadha, 2012).
In the case of 6 storey of hotel and swimming pool project, MS project tool has used to
determine the costing of whole project. On the basis of this, it has found that the entire plan has
completed within 50002.56 pounds. Along with this, critical path of proposed project has shown the
time duration of complete. It has finished in 284 days.
16
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Illustration 2: Gantt chart
17
Document Page
3.3 Analysing the methods used to measure project performance
To measure the project performance of 6 storey of hotel and swimming pool project, project
manager has set some key performance indicators. With the help of this, it becomes easy to compare
outcomes with the expected results. In this context, analysis of some methods used to assess
proposed project is as follows:ï‚· Budgeted cost for work scheduled: This has helped to evaluate the overall costing of 6
storey of hotel and swimming pool project. Here, the actual and estimated budget for the
each task has compared with the buddgetted to determine the variance(Burke, 2013).ï‚· Budgeted cost for work performed: This defines the actual costing incurred in proposed
project activities. It has stated the performance gap to ensure the success or failure rate of
project.
ï‚· Earned value analysis: It has assisted the project manager to forecast time and costing of 6
storey of hotel and swimming pool project in an effective manner (Meredith and Mantel Jr,
2011).
ï‚· Periodic monitoring-There should be a system through which the quality of project can be
monitored at each step so that any relevant and better way of doing the project can be
implemented at priority.
ï‚· The qualitative measures can be used to analyse the performances
ï‚· There are possibilities that alterations may occur as a result of the modifications that are
made at last moment. Besides this, there may be changes which have risen as a result of the
corrections made in mistakes done before.
ï‚· The qualitative measures for checking the performance of project is measuring the
performance time. If the project is completed as per the set time, it means it is successful.
Besides this, the satsifaction of clioent from the project must be checked so that it can be
assured that project is right and of right quality.
In addition to this, it can be stated that qualitative measures are need to be considered as critical
aspect. Customers technical specifications are need to be referred effectively so that objectives
designed under project can be accomplished effectively. If technical support is not appropriate as
per standards then it will impact the overall outcome. If comparison with standards is appropriate
then it will impact the overall performance in positive manner. With an assistance of qualitative
18
Document Page
measures the key aspects can be accomplished in desired way.
Activities Time scale
Budgeted cost for work scheduled 3 days
Budgeted cost for work performed 5 days
Earned value analysis 10 days
Periodic monitoring 50 days
Qualitative analysis 150 days
3.4 Explaining the change control procedure for evaluating project at its completion
To make the required changes in 6 storey of hotel and swimming pool project, project
manager has used Change control process. This has carried out after the completion of the project.
In this context, the following procedure with the respect of planned work has as follows:
ï‚· First step has determining the requirements of modifications in the project plan in various
stages of plan (Manage changes in your project, 2012).
ï‚· Here, a change request has generated by the project manager by using change request form.
ï‚· Now, change request from has sent to project change control board to evaluated their
effectiveness by considering all aspects.
ï‚· After this, change control board has rejects or accepts the change in 6 storey of hotel and
swimming pool project plan. If the request has rejected than it sends to the client otherwise
it pass to the project manager to make modifications in the plan (Schwalbe, 2015).
ï‚· The changes can occur at different stages which must be addressed properly with the help of
project assessment at each and every stage. There should be enough flexibility in the project
so that any change that are demanded by stake holder or customer can be made easily.
ï‚· There should be a proper control over the project so that they no change can be made by
anyone without informing. Moreover, a contingency plan should be also applied with a
proper communication so that the sudden change can be acceptable by all concerned people.
ï‚· Finally, it should be documented
CONCLUSION
From the above report, it has been analyzed that project management has an important tool 6
storey of hotel and swimming pool project. With the help of various tools and techniques, project
manager has completed the work within the 284 days with 50002.56 pounds costing. There have
several human resource and other materials have utilized. As per the capabilities and skills of team
members, the roles and responsibilities have given to them. On the other hand, by using key
19
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
performance methods, project manager has tried to assess the progress and performance of the
proposed project.
20
Document Page
REFERENCES
Books and Journals
Artto, K., Kulvik, I., Poskela, J. and Turkulainen, V., 2011. The integrative role of the project
management office in the front end of innovation. International Journal of Project
Management, 29(4), pp.408-421.
Bredillet, C., Yatim, F. and Ruiz, P., 2010. Project management deployment: The role of cultural
factors. International Journal of Project Management,28(2), pp.183-193.
Bredillet, C.N., 2010. Blowing hot and cold on project management. Project Management
Journal, 41(3), pp.4-20.
Burke, R., 2013. Project management: planning and control techniques. New Jersey, USA.
Caniëls, M.C. and Bakens, R.J., 2012. The effects of Project Management Information Systems on
decision making in a multi project environment.International Journal of Project
Management, 30(2), pp.162-175.
De Bakker, K., Boonstra, A. and Wortmann, H., 2010. Does risk management contribute to IT
project success? A meta-analysis of empirical evidence. International Journal of Project
Management, 28(5), pp.493-503.
Heising, W., 2012. The integration of ideation and project portfolio management—A key factor for
sustainable success. International Journal of Project Management, 30(5), pp.582-595.
Hwang, B.G. and Tan, J.S., 2012. Green building project management: obstacles and solutions for
sustainable development. Sustainable development, 20(5), pp.335-349.
Jun, L., Qiuzhen, W. and Qingguo, M., 2011. The effects of project uncertainty and risk
management on IS development project performance: A vendor perspective. International
Journal of Project Management, 29(7), pp.923-933.
Kerzner, H.R., 2013. Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Killen, C.P. and Hunt, R.A., 2010. Dynamic capability through project portfolio management in
service and manufacturing industries. International Journal of Managing Projects in
Business, 3(1), pp.157-169.
Lee, S.K. and Yu, J.H., 2012. Success model of project management information system in
construction. Automation in construction, 25, pp.82-93.
Mantel, S.J., 2011. Project management in practice. Wiley,.
Meredith, J.R. and Mantel Jr, S.J., 2011. Project management: a managerial approach. John Wiley
& Sons.
21
Document Page
Morris, P. and Pinto, J.K. eds., 2010. The Wiley Guide to Project Organization and Project
Management Competencies (Vol. 8). John Wiley & Sons.
Morris, P.W., 2010. Research and the future of project management.International Journal of
Managing Projects in Business, 3(1), pp.139-146.
Patanakul, P. and Shenhar, A.J., 2012. What project strategy really is: The fundamental building
block in strategic project management. Project Management Journal, 43(1), pp.4-20.
Patanakul, P., Iewwongcharoen, B. and Milosevic, D., 2010. An empirical study on the use of
project management tools and techniques across project life-cycle and their impact on
project success. Journal of General Management, 35(3), pp.41-65.
Portny, S.E., 2010. Project management for dummies. John Wiley & Sons.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Walker, A., 2015. Project management in construction. John Wiley & Sons.
Wu, P. and Low, S.P., 2010. Project management and green buildings: lessons from the rating
systems. Journal of Professional Issues in Engineering Education and Practice, 136(2),
pp.64-70.
Wysocki, R.K., 2011. Effective project management: traditional, agile, extreme. John Wiley &
Sons.
Online
Barry, T., 2015. TOP 10 QUALITIES OF A PROJECT MANAGER. [Online]. Available
through:<https://www.projectsmart.co.uk/top-10-qualities-project-manager.php>. [Accessed
on 13th February 2017].
Harpham, A., 2003. Early background of project management. [Online]. Available
through:<http://www.maxwideman.com/guests/thegap/background.htm>. [Accessed on 13th
February 2017].].
Kshama, 2012. Basic Principles Of Project Management. [Online]. Available
through:<http://www.simplilearn.com/project-management-basic-principles-article>.
[Accessed on 13th February 2017].
Manage changes in your project, 2012. [Online]. Available
through:<http://satheespractice.blogspot.in/2012/02/manage-changes-in-your-project.html>.
[Accessed on 13th February 2017].
Nishadha, 2012. 5 Reasons to Use Gantt Charts. [Online]. Available
through:<http://creately.com/blog/diagrams/5-reasons-to-use-gantt-charts/>. [Accessed on
13th February 2017].
22
chevron_up_icon
1 out of 22
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]