This project management plan outlines the steps and timeline for an ERP implementation project. It includes a detailed task breakdown, duration, start and finish dates, and predecessors for each activity. The plan covers various phases, from project initiation and preparation, including choosing a theme, defining the project scope, and identifying stakeholders, to the application step of development, technical infrastructure preparation, and quality assurance. The plan also includes business blueprint analysis, process mapping, system configuration, and unit testing. The document incorporates Gantt charts and a network diagram to visualize the project's schedule and dependencies, providing a comprehensive view of the project's lifecycle. The project culminates in the portrayal of valid assumptions, effective endorsements, project certification, and final project submission.
Document Page
Project management plan
Task Name Duration Start Finish Predecessors
Research Project 3 days Wed 6/6/18 Fri 6/8/18
Preparation phase of
ERP plan 3 days Wed 6/6/18 Fri 6/8/18
Choosing a theme or
subject 2 days Wed 6/6/18 Thu 6/7/18
Defining project scope and
objectives 1 day Wed 6/6/18 Wed 6/6/18
Select subject or
problematic in carrying
out installation
1 day Mon 6/11/18 Mon 6/11/18 1
Stakeholders 1 day Wed 6/6/18 Wed 6/6/18
Location period 1 day Mon 6/11/18 Mon 6/11/18 1,2
Price examining 1 day Fri 6/8/18 Fri 6/8/18 3
Distribution of reserve 1 day Thu 6/7/18 Thu 6/7/18 4
Application step of
development 3 days Wed 6/6/18 Fri 6/8/18
Technical infrastructure
preparation 4 days Tue 6/12/18 Fri 6/15/18 5
Identifying development
environment 4 days Tue 6/12/18 Fri 6/15/18 5
Quality assurance
environment 2 days Tue 6/12/18 Wed 6/13/18 6,7
Training environment 2 days Mon 6/11/18 Tue 6/12/18 8
Business blueprint 1 day Fri 6/8/18 Fri 6/8/18 9
AS-IS business process
analysis 1 day Wed 6/6/18 Wed 6/6/18
Identifying end to end
current business process 3 days Mon 6/11/18 Wed 6/13/18 10
Identify process
integration point 1 day Mon 6/18/18 Mon 6/18/18 11
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Mapping ERP process to
business 3 days Mon 6/18/18 Wed 6/20/18 12,13
Defining TO-BE process 1 day Wed 6/13/18 Wed 6/13/18 14
Configuration of system
according to design from
business blueprint.
3 days Wed 6/13/18 Fri 6/15/18 14,15
Configure solution 1 day Thu 6/7/18 Thu 6/7/18 16
Write units test script 2 days Thu 6/14/18 Fri 6/15/18 17
Configure solution 2 days Tue 6/19/18 Wed 6/20/18 17,18
Unit test configuration 4 days Thu 6/21/18 Tue 6/26/18 18,19
Concluding point of ERP
project 1 day Tue 6/19/18 Tue 6/19/18 18
Portrayal the valid
assumption 5 days Thu 6/21/18 Wed 6/27/18 19,20
Providing effective
endorsements 4 days Thu 6/14/18 Tue 6/19/18 20
Certification of assignment 4 days Thu 6/14/18 Tue 6/19/18 20
Submission the ready
project 4 days Mon 6/18/18 Thu 6/21/18 21
Document Page
Figure 1: Gantt chart
Figure 2: Gantt chart
Document Page
Figure 3: Network Diagram
[Source: The Project Management Plan (PMP), 2018]