The assignment is a project charter created for PRM701 Project Management Principles. The charter outlines the project's purpose, which is to upgrade a coastal pathway and holiday park, including details like project scope, objectives (increased seating capacity and new amenities), assumptions (profit increase), constraints (budget, timeline, and specific upgrade requirements), and budget and timeline. The project aims to enhance public facilities and is expected to be completed within a specified budget and timeframe. The charter serves as a foundational document for the project, defining key aspects and providing a roadmap for successful completion. The assignment also requires short answer questions which are not included in the provided text.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: PRM701 PROJECT MANAGEMENT PRINCIPLES
PRM701 PROJECT MANAGEMENT PRINCIPLES
Name of the Student
Name of the University
Author note
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1
PRM701 PROJECT MANAGEMENT PRINCIPLES
Part 1: Project charter
Project Project Management
Principles
Start Date
Name 1 July 2019
Project Prioritization
Manager
Owner(s) Scheduled
Sunshine Coast Council Completion 30 November 2019
Date:
Purpose The purpose of the project is to upgrade the
coastal pathway between the Arthur Parkyn peak
and the boardwalk. In addition to this, the project
will also include upgrading the holiday park for
providing better facilities to words the people of
that area.
Scope The scope associated with the project includes
developing a proper up-gradation with coastal
pathway and holiday park so that the services
provided towards the public can be enhanced. The
contract is going to be lump sum contract.
Objective The main reason behind upgrading the coastal
path way is to increase the seating capacity within
the two beaches so that maximum people can be
Document Page
2
PRM701 PROJECT MANAGEMENT PRINCIPLES
accommodated. This will also include
implementing proper fencing for providing better
support throughout the coastal area. The
upgradation for holiday park will include new
amenities, office and residences for the people.
This will ensure better way of living.
Assumptions It is expected that with the help of up-gradation
the profit obtained will be double as compared to
the funds that is going to be used for renovation.
Constraints The major constraints for this projects are:
Needs to be completed within the time and budget
The holiday park needs to be upgraded with the
recent demands
Access area for beaches needs to be upgraded
Budget It is expected that the project will be completed
within $20000.
Timeline
The project will get started at 1st July 2019 and
will be completed within 30th November 2019.
After this, the park will be available for the
people.
chevron_up_icon
1 out of 3
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]