MBA642 Project Management: Progress Report on Relocation Project
VerifiedAdded on  2023/04/21
|18
|2259
|277
Report
AI Summary
This report provides a comprehensive overview of a house relocation project's progress, detailing completions, slips, and delays encountered. It addresses changes in the project scenario, including Kelly's illness and logistical challenges, and their implications on resources. The report outlines adjustments made to the schedule to accommodate these unforeseen events, such as hospital admission and temporary hotel stays. It also includes a personal reflection on the project management process, highlighting lessons learned in handling work packages and problem-solving. The revised schedule and resource allocation are presented, with an updated milestone plan in the appendix. Desklib provides access to similar solved assignments for students.

Running Head: PROJECT MANAGEMENT
Project Management
Name of the Student
Name of the University
Project Management
Name of the Student
Name of the University
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1PROJECT MANAGEMENT
Table of Contents
1. Purpose of the Report..................................................................................................................2
2. Project Status including Completions, Slips, and Delays............................................................2
3. Implications of Changes Made on Resources..............................................................................9
4. Details of All Adjustments Made..............................................................................................12
5. Personal Reflection....................................................................................................................13
Bibliography..................................................................................................................................14
Appendix........................................................................................................................................16
Table of Contents
1. Purpose of the Report..................................................................................................................2
2. Project Status including Completions, Slips, and Delays............................................................2
3. Implications of Changes Made on Resources..............................................................................9
4. Details of All Adjustments Made..............................................................................................12
5. Personal Reflection....................................................................................................................13
Bibliography..................................................................................................................................14
Appendix........................................................................................................................................16

2PROJECT MANAGEMENT
1. Purpose of the Report
The purpose of this report is to accommodate a number of changes in the scenario of
house relocation project. As per the initial conditions provided in the scenario, Jeff and Kelly
need to relocate from Sunshine Coast to Perth due to a change in job of Jeff. Accordingly, they
have to let go of the rental in Sunshine Coast and take a new rental apartment in Perth. As per the
initial conditions, the schedule was developed and finalized regarding the entire relocation
process. However, as per the latest update, there are certain constraints added including illness of
Kelly, breakdown of luggage truck, unavailability of hotels in Perth after 27th January and others.
As a result, the overall schedule has to be altered to suit the needs of Jeff and Kelly.
2. Project Status including Completions, Slips, and Delays
Before incorporating the changes in the schedule, the following was the schedule status
for the project.
Task Name Duration Start Finish Resource Names Cost
New schedule with
adjustment for
relocation of the
family
22 days
Wed
1/2/19
Wed
1/23/19
$14,968.00
Initiation 5 days
Wed
1/2/19
Sun
1/6/19
$0.00
Developing the 1 day Wed Wed Kelly & Jeff $0.00
1. Purpose of the Report
The purpose of this report is to accommodate a number of changes in the scenario of
house relocation project. As per the initial conditions provided in the scenario, Jeff and Kelly
need to relocate from Sunshine Coast to Perth due to a change in job of Jeff. Accordingly, they
have to let go of the rental in Sunshine Coast and take a new rental apartment in Perth. As per the
initial conditions, the schedule was developed and finalized regarding the entire relocation
process. However, as per the latest update, there are certain constraints added including illness of
Kelly, breakdown of luggage truck, unavailability of hotels in Perth after 27th January and others.
As a result, the overall schedule has to be altered to suit the needs of Jeff and Kelly.
2. Project Status including Completions, Slips, and Delays
Before incorporating the changes in the schedule, the following was the schedule status
for the project.
Task Name Duration Start Finish Resource Names Cost
New schedule with
adjustment for
relocation of the
family
22 days
Wed
1/2/19
Wed
1/23/19
$14,968.00
Initiation 5 days
Wed
1/2/19
Sun
1/6/19
$0.00
Developing the 1 day Wed Wed Kelly & Jeff $0.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3PROJECT MANAGEMENT
initial plan for
relocation
1/2/19 1/2/19
Identifying
proper date for re-
location
1 day
Thu
1/3/19
Thu
1/3/19
Kelly & Jeff $0.00
Consult about
relocation with the
planner
1 day Fri 1/4/19 Fri 1/4/19 Kelly & Jeff $0.00
Date
confirmation
2 days
Sat
1/5/19
Sun
1/6/19
Kelly & Jeff $0.00
Milestone 1:
Completing the
initial plan
0 days
Sun
1/6/19
Sun
1/6/19
$0.00
Planning 4 days
Mon
1/7/19
Thu
1/10/19
$3,840.00
Identifying the
project activities
1 day
Mon
1/7/19
Mon
1/7/19
Event Planner $960.00
initial plan for
relocation
1/2/19 1/2/19
Identifying
proper date for re-
location
1 day
Thu
1/3/19
Thu
1/3/19
Kelly & Jeff $0.00
Consult about
relocation with the
planner
1 day Fri 1/4/19 Fri 1/4/19 Kelly & Jeff $0.00
Date
confirmation
2 days
Sat
1/5/19
Sun
1/6/19
Kelly & Jeff $0.00
Milestone 1:
Completing the
initial plan
0 days
Sun
1/6/19
Sun
1/6/19
$0.00
Planning 4 days
Mon
1/7/19
Thu
1/10/19
$3,840.00
Identifying the
project activities
1 day
Mon
1/7/19
Mon
1/7/19
Event Planner $960.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4PROJECT MANAGEMENT
Making
schedule for
relocation
1 day
Tue
1/8/19
Tue
1/8/19
Event Planner $960.00
Planning for the
contingency
1 day
Wed
1/9/19
Wed
1/9/19
Event Planner $960.00
Allocating the
required resources
1 day
Thu
1/10/19
Thu
1/10/19
Event Planner $960.00
Milestone
2:Getting approval
0 days
Thu
1/10/19
Thu
1/10/19
$0.00
Pre-relocation
activities
8.5 days
Fri
1/11/19
Sat
1/19/19
$7,140.00
Hiring packers
and movers
1 day
Fri
1/11/19
Fri
1/11/19
Kelly & Jeff $0.00
Packing the
necessary
belongings
1 day
Sat
1/12/19
Sun
1/13/19
Packers[200%],Packaging
Cost[1]
$2,700.00
Selling the
items that are not
needed
1.5 days
Sat
1/12/19
Sun
1/13/19
Event Planner[200%] $2,880.00
Getting pre- 2 days Sun Tue Kelly & Jeff, Mortgage $1,560.00
Making
schedule for
relocation
1 day
Tue
1/8/19
Tue
1/8/19
Event Planner $960.00
Planning for the
contingency
1 day
Wed
1/9/19
Wed
1/9/19
Event Planner $960.00
Allocating the
required resources
1 day
Thu
1/10/19
Thu
1/10/19
Event Planner $960.00
Milestone
2:Getting approval
0 days
Thu
1/10/19
Thu
1/10/19
$0.00
Pre-relocation
activities
8.5 days
Fri
1/11/19
Sat
1/19/19
$7,140.00
Hiring packers
and movers
1 day
Fri
1/11/19
Fri
1/11/19
Kelly & Jeff $0.00
Packing the
necessary
belongings
1 day
Sat
1/12/19
Sun
1/13/19
Packers[200%],Packaging
Cost[1]
$2,700.00
Selling the
items that are not
needed
1.5 days
Sat
1/12/19
Sun
1/13/19
Event Planner[200%] $2,880.00
Getting pre- 2 days Sun Tue Kelly & Jeff, Mortgage $1,560.00

5PROJECT MANAGEMENT
mortgage 1/13/19 1/15/19 Cost[1]
Keeping
Copious Notes
1 day
Tue
1/15/19
Wed
1/16/19
Kelly & Jeff $0.00
Applying for
the school
2 days
Wed
1/16/19
Fri
1/18/19
Kelly & Jeff $0.00
Relocation to
the old apartment
1 day
Fri
1/18/19
Sat
1/19/19
$0.00
Milestone
3:Vaacting the old
house
0 days
Sat
1/19/19
Sat
1/19/19
$0.00
Post Relocation 4.5 days
Sat
1/19/19
Wed
1/23/19
$3,988.00
Moving to hotel
until
commencement of
new house
0 days
Sat
1/19/19
Sat
1/19/19
$0.00
Arriving to the
new house
1 day
Sat
1/19/19
Sun
1/20/19
Kelly & Jeff $0.00
mortgage 1/13/19 1/15/19 Cost[1]
Keeping
Copious Notes
1 day
Tue
1/15/19
Wed
1/16/19
Kelly & Jeff $0.00
Applying for
the school
2 days
Wed
1/16/19
Fri
1/18/19
Kelly & Jeff $0.00
Relocation to
the old apartment
1 day
Fri
1/18/19
Sat
1/19/19
$0.00
Milestone
3:Vaacting the old
house
0 days
Sat
1/19/19
Sat
1/19/19
$0.00
Post Relocation 4.5 days
Sat
1/19/19
Wed
1/23/19
$3,988.00
Moving to hotel
until
commencement of
new house
0 days
Sat
1/19/19
Sat
1/19/19
$0.00
Arriving to the
new house
1 day
Sat
1/19/19
Sun
1/20/19
Kelly & Jeff $0.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6PROJECT MANAGEMENT
Receiving items
that are needed
0.5 days
Sun
1/20/19
Sun
1/20/19
Movers, Transportation
Cost[1]
$3,388.00
Unpacking and
shifting
commodities
1 day
Mon
1/21/19
Mon
1/21/19
Packers $600.00
Aligning day-
to-day activities
2 days
Tue
1/22/19
Wed
1/23/19
$0.00
Milestone 4:
Project closure
0 days
Mon
1/21/19
Mon
1/21/19
$0.00
However, there are certain changes in the scenario due to some unforeseen incidents like
flu of Kelly, breakdown of luggage truck en route, Australia Day celebration at Perth and others.
As a result, certain changes had to be made in the overall scenario that are shown in the
following table.
Task Name Duration Start Finish
Revised Schedule for the Relocation 30.5 days Wed 1/2/19 Fri 2/1/19
Initiation 5 days Wed 1/2/19 Sun 1/6/19
Developing the initial plan for
relocation
1 day Wed 1/2/19 Wed 1/2/19
Receiving items
that are needed
0.5 days
Sun
1/20/19
Sun
1/20/19
Movers, Transportation
Cost[1]
$3,388.00
Unpacking and
shifting
commodities
1 day
Mon
1/21/19
Mon
1/21/19
Packers $600.00
Aligning day-
to-day activities
2 days
Tue
1/22/19
Wed
1/23/19
$0.00
Milestone 4:
Project closure
0 days
Mon
1/21/19
Mon
1/21/19
$0.00
However, there are certain changes in the scenario due to some unforeseen incidents like
flu of Kelly, breakdown of luggage truck en route, Australia Day celebration at Perth and others.
As a result, certain changes had to be made in the overall scenario that are shown in the
following table.
Task Name Duration Start Finish
Revised Schedule for the Relocation 30.5 days Wed 1/2/19 Fri 2/1/19
Initiation 5 days Wed 1/2/19 Sun 1/6/19
Developing the initial plan for
relocation
1 day Wed 1/2/19 Wed 1/2/19
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT MANAGEMENT
Identifying proper date for re-
location
1 day Thu 1/3/19 Thu 1/3/19
Consult about relocation with the
planner
1 day Fri 1/4/19 Fri 1/4/19
Date confirmation 2 days Sat 1/5/19 Sun 1/6/19
Milestone 1: Completing the initial
plan
0 days Sun 1/6/19 Sun 1/6/19
Planning 4 days Mon 1/7/19 Thu 1/10/19
Identifying the project activities 1 day Mon 1/7/19 Mon 1/7/19
Making schedule for relocation 1 day Tue 1/8/19 Tue 1/8/19
Planning for the contingency 1 day Wed 1/9/19 Wed 1/9/19
Allocating the required resources 1 day Thu 1/10/19 Thu 1/10/19
Milestone 2:Getting approval 0 days Thu 1/10/19 Thu 1/10/19
Pre-relocation activities 18 days Fri 1/11/19 Mon 1/28/19
Hiring packers and movers 1 day Fri 1/11/19 Fri 1/11/19
Packing the necessary belongings 1 day Sat 1/12/19 Sun 1/13/19
Selling the items that are not needed 1.5 days Sat 1/12/19 Sun 1/13/19
Identifying proper date for re-
location
1 day Thu 1/3/19 Thu 1/3/19
Consult about relocation with the
planner
1 day Fri 1/4/19 Fri 1/4/19
Date confirmation 2 days Sat 1/5/19 Sun 1/6/19
Milestone 1: Completing the initial
plan
0 days Sun 1/6/19 Sun 1/6/19
Planning 4 days Mon 1/7/19 Thu 1/10/19
Identifying the project activities 1 day Mon 1/7/19 Mon 1/7/19
Making schedule for relocation 1 day Tue 1/8/19 Tue 1/8/19
Planning for the contingency 1 day Wed 1/9/19 Wed 1/9/19
Allocating the required resources 1 day Thu 1/10/19 Thu 1/10/19
Milestone 2:Getting approval 0 days Thu 1/10/19 Thu 1/10/19
Pre-relocation activities 18 days Fri 1/11/19 Mon 1/28/19
Hiring packers and movers 1 day Fri 1/11/19 Fri 1/11/19
Packing the necessary belongings 1 day Sat 1/12/19 Sun 1/13/19
Selling the items that are not needed 1.5 days Sat 1/12/19 Sun 1/13/19

8PROJECT MANAGEMENT
Getting pre-mortgage 2 days Sun 1/13/19 Tue 1/15/19
Keeping Copious Notes 1 day Tue 1/15/19 Wed 1/16/19
Admit Kelly in Hospital 0 days Tue 1/15/19 Tue 1/15/19
Bed Rest for Kelly in Hospital 14 days Tue 1/15/19 Mon 1/28/19
Applying for the school 2 days Wed 1/16/19 Fri 1/18/19
Relocation to the old apartment 1 day Fri 1/18/19 Sat 1/19/19
Milestone 3:Vaacting the old house 0 days Sat 1/19/19 Sat 1/19/19
Relocation 13 days Sat 1/19/19 Fri 2/1/19
Moving to hotel until Kelly is fit 9 days Sat 1/19/19 Mon 1/28/19
Arriving at Perth 0 days Mon 1/28/19 Mon 1/28/19
Receiving items that are needed 0.5 days Tue 1/29/19 Tue 1/29/19
Unpacking and shifting
commodities
1 day Tue 1/29/19 Wed 1/30/19
Aligning day-to-day activities 2 days Wed 1/30/19 Fri 2/1/19
Milestone 4: Project closure 0 days Wed 1/30/19 Wed 1/30/19
Getting pre-mortgage 2 days Sun 1/13/19 Tue 1/15/19
Keeping Copious Notes 1 day Tue 1/15/19 Wed 1/16/19
Admit Kelly in Hospital 0 days Tue 1/15/19 Tue 1/15/19
Bed Rest for Kelly in Hospital 14 days Tue 1/15/19 Mon 1/28/19
Applying for the school 2 days Wed 1/16/19 Fri 1/18/19
Relocation to the old apartment 1 day Fri 1/18/19 Sat 1/19/19
Milestone 3:Vaacting the old house 0 days Sat 1/19/19 Sat 1/19/19
Relocation 13 days Sat 1/19/19 Fri 2/1/19
Moving to hotel until Kelly is fit 9 days Sat 1/19/19 Mon 1/28/19
Arriving at Perth 0 days Mon 1/28/19 Mon 1/28/19
Receiving items that are needed 0.5 days Tue 1/29/19 Tue 1/29/19
Unpacking and shifting
commodities
1 day Tue 1/29/19 Wed 1/30/19
Aligning day-to-day activities 2 days Wed 1/30/19 Fri 2/1/19
Milestone 4: Project closure 0 days Wed 1/30/19 Wed 1/30/19
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9PROJECT MANAGEMENT
The revised table shows four activities have been modified / added in order incorporate
the changes in the scenario. These activities include hospital admission for Kelly, moving of Jeff
and rest of the family to the hotel until Kelly is fit and relocation to Perth on a different date.
3. Implications of Changes Made on Resources
As new activities have been added to the overall schedule, there are also changes in the
resources. The changed resources are shown in the following table.
Task Name Duration Resource Names Cost
Revised Schedule for
the Relocation
30.5 days $16,468.00
Initiation 5 days $0.00
Developing the
initial plan for
relocation
1 day Jeff $0.00
Identifying proper
date for re-location
1 day Jeff $0.00
Consult about
relocation with the
planner
1 day Jeff $0.00
Date confirmation 2 days Jeff $0.00
The revised table shows four activities have been modified / added in order incorporate
the changes in the scenario. These activities include hospital admission for Kelly, moving of Jeff
and rest of the family to the hotel until Kelly is fit and relocation to Perth on a different date.
3. Implications of Changes Made on Resources
As new activities have been added to the overall schedule, there are also changes in the
resources. The changed resources are shown in the following table.
Task Name Duration Resource Names Cost
Revised Schedule for
the Relocation
30.5 days $16,468.00
Initiation 5 days $0.00
Developing the
initial plan for
relocation
1 day Jeff $0.00
Identifying proper
date for re-location
1 day Jeff $0.00
Consult about
relocation with the
planner
1 day Jeff $0.00
Date confirmation 2 days Jeff $0.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10PROJECT MANAGEMENT
Milestone 1:
Completing the initial
plan
0 days $0.00
Planning 4 days $3,840.00
Identifying the
project activities
1 day Event Planner $960.00
Making schedule
for relocation
1 day Event Planner $960.00
Planning for the
contingency
1 day Event Planner $960.00
Allocating the
required resources
1 day Event Planner $960.00
Milestone
2:Getting approval
0 days $0.00
Pre-relocation
activities
18 days $8,640.00
Hiring packers and
movers
1 day Jeff $0.00
Packing the 1 day Packers[200%],Packagin $2,700.00
Milestone 1:
Completing the initial
plan
0 days $0.00
Planning 4 days $3,840.00
Identifying the
project activities
1 day Event Planner $960.00
Making schedule
for relocation
1 day Event Planner $960.00
Planning for the
contingency
1 day Event Planner $960.00
Allocating the
required resources
1 day Event Planner $960.00
Milestone
2:Getting approval
0 days $0.00
Pre-relocation
activities
18 days $8,640.00
Hiring packers and
movers
1 day Jeff $0.00
Packing the 1 day Packers[200%],Packagin $2,700.00

11PROJECT MANAGEMENT
necessary belongings g Cost[1]
Selling the items
that are not needed
1.5 days Event Planner[200%] $2,880.00
Getting pre-
mortgage
2 days Jeff, Mortgage Cost[1] $1,560.00
Keeping Copious
Notes
1 day Jeff $0.00
Admit Kelly in
Hospital
0 days $0.00
Bed Rest for Kelly
in Hospital
14 days $1,500.00
Applying for the
school
2 days Jeff $0.00
Relocation to the
old apartment
1 day $0.00
Milestone
3:Vaacting the old
house
0 days $0.00
Relocation 13 days $3,988.00
necessary belongings g Cost[1]
Selling the items
that are not needed
1.5 days Event Planner[200%] $2,880.00
Getting pre-
mortgage
2 days Jeff, Mortgage Cost[1] $1,560.00
Keeping Copious
Notes
1 day Jeff $0.00
Admit Kelly in
Hospital
0 days $0.00
Bed Rest for Kelly
in Hospital
14 days $1,500.00
Applying for the
school
2 days Jeff $0.00
Relocation to the
old apartment
1 day $0.00
Milestone
3:Vaacting the old
house
0 days $0.00
Relocation 13 days $3,988.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 18
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.