This project management assignment analyzes the construction of two units for Reasonable Builders, focusing on systematic project planning and scheduling. It utilizes MS Project to create a detailed timeline and cost analysis, incorporating techniques such as the waterfall model, Gantt charts, and network diagrams. The project is broken down into phases, including planning, site design, lock-up, and fit-out, with estimated costs and durations for each task. The assignment emphasizes optimizing time and resources, managing costs, and determining the critical path. The analysis includes detailed resource allocation, variance analysis, and a comprehensive cost breakdown, aiming to provide the company with the necessary information for effective project management and negotiation. The report covers the project's planning, execution, and control phases, offering insights into managing project duration and cost, and demonstrating the application of key project management principles.
Document Page
Running head: PROJECT MANAGEMENT KNOWLEDGE
PROJECT MANAGEMENT KNOWLEDGE
Name of the Student
Name of the University
Author Note
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1PROJECT MANAGEMENT KNOWLEDGE
Executive summary
The aim of the assessment is to determine the basic concept that is related with a systematic
project planning and scheduling. While executing a project it is considered to be essential to
ensure that project management techniques are used for the purpose of managing the project
duration and overall cost. The paper will focus on analyzing and applying the principles that are
associated with cash flow planning and cost control. Thus it can be concluded that with an
enhanced project management principles it will become easy to manage the performance. The
paper will focus on analyzing the project management techniques in respect to the case study of
Reasonable builders. It is expected that by the end of this paper sufficient knowledge will be
provided towards the company about the time line and cost.
Document Page
2PROJECT MANAGEMENT KNOWLEDGE
Table of Contents
Introduction......................................................................................................................................3
Project management techniques and tools.......................................................................................3
Optimizing time and resources........................................................................................................4
Cost for developing the project....................................................................................................6
Variance and time........................................................................................................................7
Gantt chart...................................................................................................................................9
Resources for project.................................................................................................................10
Network diagram...........................................................................................................................13
Critical path...................................................................................................................................14
Conclusion.....................................................................................................................................15
References......................................................................................................................................16
Document Page
3PROJECT MANAGEMENT KNOWLEDGE
Introduction
The main perspective of the assessment is to improve a time line and cost for
understanding contract components well. With proper assistance and knowledge of project it
becomes easy to negotiate the price with client. The project will include developing an effective
schedule for offering better support towards the organization. This assessment will focus on
evaluating the different components associated with developing the schedule. The report will
focus on planning the time, cost and resources that will be used for successfully executing a
project in addition to this the critical path will also be determined within the MS project. Thus it
can be stated that with the help of this assessment it will become easy to manage the
performance of the project.
Project management techniques and tools
Project management techniques are used for the aim of offering better support towards
the development of a project. With the growing technologies it has been identified that with the
evolution of project management methodologies it becomes easy to provide effective support
towards the successful execution of the project (Chavez 2018). The best project management
technique that will help in developing the project is waterfall technique. The main focus behind
selecting waterfall model is that it uses clear structure so that it becomes easy to define the
different steps and information can be transformed properly. Hence it can be concluded that
with the effective use of PM methodologies it will become easy to define the objectives.
MS project is the project management tool that is used for developing an effective
schedule of a project, helps in assigning the resources towards a task so that it becomes easy to
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4PROJECT MANAGEMENT KNOWLEDGE
manage the project. In order to understand the different components associated with the project it
is important to use Microsoft project (Jamali and Oveisi 2016). The key benefits that are offered
with the use of Microsoft project includes simplifying the IT management, offers effective
presentation and also ensures that a better way of communicating with the key stakeholders are
identified.
Optimizing time and resources
Before developing a project it becomes necessary to ensure that the resources and time
frame are being planned properly so that the project can be developed effectively. The project
needs to be expected within a schedule time and budget so that it becomes easy to manage the
performance of the project. In order to optimizing the time, the tasks will be carried out in
minimum time frames (Joslin 2019). This will ensure that the resources and overall time needed
for executing the project is reduced. The key phases that are going to be included within the
project are described below:
Phase 1: Planning and Site designing
This phase will focus on creating site plans for the purpose of easy development of the
project. The site needs to be preparing properly so that it can be used successfully for managing
the different materials. A foundation needs to be lay down properly so that it becomes easy to
organize the materials. The time needed for completing the phase is estimated to be around 30
days. It is expected that within the estimated time period it will become easy to execute the
process. There is a need to ensure that the tasks are managed effectively together so that it can
offer better support.
Document Page
5PROJECT MANAGEMENT KNOWLEDGE
Phase 2: To Lock up
This phase is considered as an important phase as this involves internal development of
the site. This phase will focus on erect framing, preparing the lay roofing, brick walls
development and fitting the windows and doors for completing the site. For the purpose of
optimizing the time frame it is important to complete the internal design together. This involves
preparing the brick walls and fitting the doors and windows for the completion of the site. With
reduced time frame it will become easy to manage the project development process. Moreover it
is expected that the reduced time frame will attract attention of customers.
Phase 3: Fit Out
This includes developing the interior works that includes performing the electrical works,
internal plumbing, and plastering the walls. This installation of kitchen and bathroom can be
done on similar days. This will lead to reduce in overall time frame and there resources that are
needed for managing the business activities. The final fittings need to be done effectively for
developing the project successfully.
The main reason behind optimizing the resources and time is that it helps in increasing
the revenue and also ensures that the conflicts are resolved effectively. The project performance
also gets developed effectively with cost reduction. Thus it can be stated that with the use of
proper resource management it will become efficient to manage the customer expectations.
Hence there arises a need to manage the resources and time effectively so that it can provide
better benefits towards the clients (Westney 2017). Every component needs to be organized
properly so that it becomes easy to manage the resources effectively. The project has been
developed after analyzing all the key phase effectively.
Document Page
6PROJECT MANAGEMENT KNOWLEDGE
Cost for developing the project
The overall estimated cost is $22,296 and will be executed within 51 days. An optimized
budget and schedule will help in offering better support towards the development process. This
also ensures that all the necessary resources are managed effectively for the purpose of
organizing the project objectives (Nicholas and Steyn 2017). Cost management is considered as
an important aspect associated with the project. This helps in setting the baseline for the
estimated cost of the project. Before executing a project it is essential to estimate the costs for
ensuring that proper profit margin is obtained while developing the project.
Task Name Cost
Project development phase $22,296.00
phase 1: Plans and site $9,456.00
creating site plans $480.00
arrange council permit $480.00
Prepare site and organize materials $5,040.00
Lay foundations $2,304.00
plumbing for sewerage $768.00
pour slab $384.00
Foundations comp $0.00
Phase 2: To lock up $4,032.00
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7PROJECT MANAGEMENT KNOWLEDGE
Erect framing $360.00
lay roofing $2,048.00
brick walls and fitting door $1,624.00
lockup $0.00
Phase 3: Fit out $8,808.00
electrical cables and internal plumbing $480.00
plaster walls and internal plumbing $1,800.00
internal doors and trim $480.00
install kitchen and bathroom $1,600.00
Final fitting (electrical, plumbing) $3,968.00
paint $480.00
Construction complete $0.00
Variance and time
It is important to determine the start and finish date for completing a project. The
predecessors are also determined so that it becomes easy to interlink between the tasks (Soe and
Htike 2018). The time period is estimated in the given below table.
Document Page
8PROJECT MANAGEMENT KNOWLEDGE
Task Name Duration Start Finish Predecessors
phase 1: Plans and site 22 days Mon 2/24/20 Tue 3/24/20
Project development phase 51 days Mon 2/24/20 Mon 5/4/20
creating site plans 2 days Mon 2/24/20 Tue 2/25/20
arrange council permit 2 days Wed 2/26/20 Thu 2/27/20 3
Prepare site and organize
materials
10 days Wed 2/26/20 Tue 3/10/20 3
Lay foundations 6 days Wed 3/11/20 Wed 3/18/20 5
plumbing for sewerage 3 days Thu 3/19/20 Mon 3/23/20 6
pour slab 1 day Tue 3/24/20 Tue 3/24/20 7
Foundations comp 0 days Tue 3/24/20 Tue 3/24/20 8
Phase 2: To lock up 11 days Wed 3/25/20 Wed 4/8/20
Erect framing 3 days Wed 3/25/20 Fri 3/27/20 8
lay roofing 8 days Mon 3/30/20 Wed 4/8/20 11
brick walls and fitting door 7 days Mon 3/30/20 Tue 4/7/20 11
lockup 0 days Tue 4/7/20 Tue 4/7/20 13
Phase 3: Fit out 19 days Wed 4/8/20 Mon 5/4/20
Document Page
9PROJECT MANAGEMENT KNOWLEDGE
electrical cables and internal
plumbing
2 days Wed 4/8/20 Thu 4/9/20 13
plaster walls and internal
plumbing
5 days Fri 4/10/20 Thu 4/16/20 16
internal doors and trim 4 days Fri 4/17/20 Wed 4/22/20 17
install kitchen and bathroom 4 days Fri 4/17/20 Wed 4/22/20 17
Final fitting (electrical,
plumbing)
8 days Thu 4/23/20 Mon 5/4/20 19
paint 5 days Thu 4/23/20 Wed 4/29/20 19
Construction complete 0 days Wed 4/29/20 Wed 4/29/20 21
Gantt chart
Gantt charts are considered as an important component for project management. This
helps in scheduling the tasks effectively and also provides a clear visual representation of the
different time frames. This also offers easy accessibilities towards the users by allowing them to
easily add dependencies and predecessors (Sharon and Dori 2017). The below Gantt chart is
provided for the purpose of managing the key phases for developing the project. The flow of
phases is displayed within the Gantt chart. With the help of this Gantt chart it becomes easy to
improve the communication and also the team cohesion also reduces.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10PROJECT MANAGEMENT KNOWLEDGE
Resources for project
The below table is used for the purpose of explaining the overall resources that are
needed for managing the project development phases. In order to optimize the overall project
development cost, the rates of resources are modified. This has the potential to enhance the
project performance (Radujković and Sjekavica 2017). The main resources that are needed for
successfully developing the project are draftsperson, electrician, plumber, concreter, carpenter,
labourer, painter, supervisor, carpenter, cabinet maker, roof tiler, brick layer and plasterer. Every
member plays a crucial role in the successful development of the project. This ensures that the
projects are executed successfully without any impacts from cost and time.
Resource Name Std. Rate
draftsperson $30.00/hr
Document Page
11PROJECT MANAGEMENT KNOWLEDGE
electrician $30.00/hr
plumber $32.00/hr
concreter $15.00/hr
carpenter $15.00/hr
labourer $18.00/hr
painter $12.00/hr
supervisor $30.00/hr
cabinet maker $18.00/hr
roof tiler $14.00/hr
bricklayer $14.00/hr
plasterer $13.00/hr
The below given list is the number of resources that are needed for executing the project
effectively. With the help of these resources it will become easy to execute the project. The
project developed has the potential to meet the key needs of the client (Pollard 2019). Thus it can
be stated that with the help of proper resource sheet it becomes easy to manage the activities.
Every phase is crucial for executing the project successfully.
Task Name Resource Names