Project Management Report: Family Relocation Schedule and Analysis
VerifiedAdded on  2023/04/22
|17
|3067
|417
Report
AI Summary
This report details a project schedule for the relocation of a family from the Sunshine Coast to Perth. The assignment, based on a real-life scenario, encompasses the application of project management principles, including the development of a Work Breakdown Structure (WBS), milestone plan, task list, and Gantt chart. The report outlines the criteria and assumptions used, and the project is structured into phases such as project initiation, planning, execution, and closure. It includes a breakdown of tasks, responsibilities, and a timeline for completion, considering a budget constraint of $15,000 and a deadline aligned with the start of the new job and school sessions. Adjustments made to the schedule and the justification for these changes are also documented. The report concludes with a personal reflection on the project management process, emphasizing critical knowledge areas such as communication, risk, procurement, and logistic management, the importance of project phases, and the need for resource allocation based on skills, and concludes with the significance of appropriate tools and technologies.

Running head: PROJECT MANAGEMENT
Project Management: Relocation of Family
Name of the student:
Name of the university:
Project Management: Relocation of Family
Name of the student:
Name of the university:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1PROJECT MANAGEMENT
Table of Contents
1. An overview of the scenario........................................................................................................2
2. The criteria and assumptions used to prepare the milestone plan and task list (WBS)...............3
2.1 Criteria...................................................................................................................................3
2.2 Assumptions..........................................................................................................................3
2.3 Work Breakdown Structure (WBS).......................................................................................4
3. Milestone plan (refer to appendix 1)...........................................................................................5
4. List of the tasks and who is responsible for each task (refer to appendix 2)...............................6
5. Gantt chart indicating the flow of tasks (refer to appendix 3).....................................................7
6. Details of all adjustments made to the schedule..........................................................................8
Justification for the adjustments......................................................................................................8
7. A personal reflection on the process............................................................................................9
References......................................................................................................................................11
Appendices....................................................................................................................................13
Appendix 1: Milestone plan.......................................................................................................13
Appendix 2: A list of tasks........................................................................................................13
Appendix 3: A Gantt chart.........................................................................................................15
Table of Contents
1. An overview of the scenario........................................................................................................2
2. The criteria and assumptions used to prepare the milestone plan and task list (WBS)...............3
2.1 Criteria...................................................................................................................................3
2.2 Assumptions..........................................................................................................................3
2.3 Work Breakdown Structure (WBS).......................................................................................4
3. Milestone plan (refer to appendix 1)...........................................................................................5
4. List of the tasks and who is responsible for each task (refer to appendix 2)...............................6
5. Gantt chart indicating the flow of tasks (refer to appendix 3).....................................................7
6. Details of all adjustments made to the schedule..........................................................................8
Justification for the adjustments......................................................................................................8
7. A personal reflection on the process............................................................................................9
References......................................................................................................................................11
Appendices....................................................................................................................................13
Appendix 1: Milestone plan.......................................................................................................13
Appendix 2: A list of tasks........................................................................................................13
Appendix 3: A Gantt chart.........................................................................................................15

2PROJECT MANAGEMENT
1. An overview of the scenario
This project report reflects the role of professional project management practices that are
needed to be widely followed by the project manager and project team members to ensure its
success. The case scenario is about relocation of a family of a two adults Jeff and Kelly along
with their 2 children Will aged 7 & Lexie aged 12, a car and their dog named as Buddy. Jeff has
recently secured designation of a marketing director interstate and currently mainly for the job
purposes the family is interested to shift to Perth from their current location the Sunshine Coast,
Qld. Currently the rental apartment where they are living is two bedroom in Maroochydore and
the new apartment which they have already rented is a four bedroom suburban house in Perth.
The new job of Jeff will be started on 5the February, 2018 and the school session of their
children is going to commence on Wednesday 31th January, 2019. However, they have to vacate
their house on 20th January, 2018 in middle the one year they have to rent anther small house
nearby on the Sunshine Coast, Qld due to their children school. They have no relatives living in
on the Sunshine Coast, Qld therefore, rent is the only option left for them. Their expected budget
is $15,000 within which they have to accomplish the project. A details project WBS, including
milestone and activities are elaborated in this report to make the project must transparent and
visible.
1. An overview of the scenario
This project report reflects the role of professional project management practices that are
needed to be widely followed by the project manager and project team members to ensure its
success. The case scenario is about relocation of a family of a two adults Jeff and Kelly along
with their 2 children Will aged 7 & Lexie aged 12, a car and their dog named as Buddy. Jeff has
recently secured designation of a marketing director interstate and currently mainly for the job
purposes the family is interested to shift to Perth from their current location the Sunshine Coast,
Qld. Currently the rental apartment where they are living is two bedroom in Maroochydore and
the new apartment which they have already rented is a four bedroom suburban house in Perth.
The new job of Jeff will be started on 5the February, 2018 and the school session of their
children is going to commence on Wednesday 31th January, 2019. However, they have to vacate
their house on 20th January, 2018 in middle the one year they have to rent anther small house
nearby on the Sunshine Coast, Qld due to their children school. They have no relatives living in
on the Sunshine Coast, Qld therefore, rent is the only option left for them. Their expected budget
is $15,000 within which they have to accomplish the project. A details project WBS, including
milestone and activities are elaborated in this report to make the project must transparent and
visible.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3PROJECT MANAGEMENT
2. The criteria and assumptions used to prepare the milestone plan and task
list (WBS)
2.1 Criteria
The list of criteria must be maintained while implementing this project includes the
following:
 The time between leaving the current location and final shift to Perth Jeff and
Kelly should rent a house nearby Sunshine Coast, Qld
 The newly rented apartment should have good location with adequate transport
communications
 The neighbours are needed to be enough friendly
 There should have availability of healthcare units for both human and pets with
medical stores
 The project is required to be completed within the estimated budget of $15,000
 The total time within which the project must be accomplished is estimated as 20th
January, 2018 and 31st January, 2018
2.2 Assumptions
As soon as the family relocation case scenario is analyzed it has been determined for
accomplishing the transfer a successful project the project associates are required to play serious
attention on each and every undertaken activity. For this specific project triple project constraints
have been chosen in terms of time, cost and scope. It is the responsibility of the project manager
to ensure that its scope is meeting the goals and objectives within one year of estimated time
2. The criteria and assumptions used to prepare the milestone plan and task
list (WBS)
2.1 Criteria
The list of criteria must be maintained while implementing this project includes the
following:
 The time between leaving the current location and final shift to Perth Jeff and
Kelly should rent a house nearby Sunshine Coast, Qld
 The newly rented apartment should have good location with adequate transport
communications
 The neighbours are needed to be enough friendly
 There should have availability of healthcare units for both human and pets with
medical stores
 The project is required to be completed within the estimated budget of $15,000
 The total time within which the project must be accomplished is estimated as 20th
January, 2018 and 31st January, 2018
2.2 Assumptions
As soon as the family relocation case scenario is analyzed it has been determined for
accomplishing the transfer a successful project the project associates are required to play serious
attention on each and every undertaken activity. For this specific project triple project constraints
have been chosen in terms of time, cost and scope. It is the responsibility of the project manager
to ensure that its scope is meeting the goals and objectives within one year of estimated time
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4PROJECT MANAGEMENT
period (20th January, 2018 and 31st January, 2018). The project is required to be accomplished
before 31st January because the school sessions of the children are going to be started on that day.
2.3 Work Breakdown Structure (WBS)
In order to reduce work pressure from the project resources (human and physical) and
implement an error free relocation project the activities the project manager must be divided into
small segments. The prepared WBS for the family relation project is elaborated in the below
section. The Work Breakdown Structure (WBS) is comprises of four work packages such as
project starting phase, planning phase, execution phase and project closure phase.
Family relocation project
schedule to Perth
Project starting phase
Project feasibility
study
Preparing the
project schedule
Reason of relocation
should be explained
to the children
Contact to current
school for getting
transfer certificate
Taking admission in
new school
Searching for a new
apartment for the
middle time
Milestone 1:
Completion of
project inititiaon
phase
Planning phase
Procurement
planning
Risk management
planning
Taking medical
records of all
including the pet
Packaging
Milestone 2:
Completing planning
phase
Project execution phase
Booking cars for
shifting
Travelling
arrangement
securing
Gathering food
products
Final move or transfer
undertaken
Booking trucks for
taking furniture
Settling furniture in
the new location
Milestone 3:
Completion of
project execution
phase
Project closure phase
Final project signoff
Successful
accomplishment of
the project
Milestone 4:
Completing project
closure phase
Figure 1: The WBS for the project
(Source: created by author)
period (20th January, 2018 and 31st January, 2018). The project is required to be accomplished
before 31st January because the school sessions of the children are going to be started on that day.
2.3 Work Breakdown Structure (WBS)
In order to reduce work pressure from the project resources (human and physical) and
implement an error free relocation project the activities the project manager must be divided into
small segments. The prepared WBS for the family relation project is elaborated in the below
section. The Work Breakdown Structure (WBS) is comprises of four work packages such as
project starting phase, planning phase, execution phase and project closure phase.
Family relocation project
schedule to Perth
Project starting phase
Project feasibility
study
Preparing the
project schedule
Reason of relocation
should be explained
to the children
Contact to current
school for getting
transfer certificate
Taking admission in
new school
Searching for a new
apartment for the
middle time
Milestone 1:
Completion of
project inititiaon
phase
Planning phase
Procurement
planning
Risk management
planning
Taking medical
records of all
including the pet
Packaging
Milestone 2:
Completing planning
phase
Project execution phase
Booking cars for
shifting
Travelling
arrangement
securing
Gathering food
products
Final move or transfer
undertaken
Booking trucks for
taking furniture
Settling furniture in
the new location
Milestone 3:
Completion of
project execution
phase
Project closure phase
Final project signoff
Successful
accomplishment of
the project
Milestone 4:
Completing project
closure phase
Figure 1: The WBS for the project
(Source: created by author)

5PROJECT MANAGEMENT
WBS Task Name
0 Family relocation project schedule to Perth
1 Project starting phase
1.1 Project feasibility study
1.2 Preparing the project schedule
1.3 Reason of relocation should be explained to the children
1.4 Contact to current school for getting transfer certificate
1.5 Taking admission in new school
1.6 Searching for a new apartment for the middle time
1.7 Milestone 1: Completion of project initiation phase
2 Planning phase
2.1 Procurement planning
2.2 Risk management planning
2.3 Taking medical records of all including the pet
2.4 Packaging
2.5 Milestone 2: Completing planning phase
3 Project execution phase
3.1 Booking cars for shifting
3.2 Travelling arrangement securing
3.3 Gathering food products
3.4 Final move or transfer undertaken
3.5 Booking trucks for taking furniture
3.6 Settling furniture in the new location
3.7 Milestone 3: Completion of project execution phase
4 Project closure phase
4.1 Final project signoff
4.2 Successful accomplishment of the project
4.3 Milestone 4: Completing project closure phase
3. Milestone plan (refer to appendix 1)
In order to implement this project five major milestones are highlighted and under each
of the work package more than two activities are presented. It is assumed that if all these
activities are properly assigned and arranged then implementation of the project will become
must easier and error free. For this specific project two project timelines are prepared. For the
WBS Task Name
0 Family relocation project schedule to Perth
1 Project starting phase
1.1 Project feasibility study
1.2 Preparing the project schedule
1.3 Reason of relocation should be explained to the children
1.4 Contact to current school for getting transfer certificate
1.5 Taking admission in new school
1.6 Searching for a new apartment for the middle time
1.7 Milestone 1: Completion of project initiation phase
2 Planning phase
2.1 Procurement planning
2.2 Risk management planning
2.3 Taking medical records of all including the pet
2.4 Packaging
2.5 Milestone 2: Completing planning phase
3 Project execution phase
3.1 Booking cars for shifting
3.2 Travelling arrangement securing
3.3 Gathering food products
3.4 Final move or transfer undertaken
3.5 Booking trucks for taking furniture
3.6 Settling furniture in the new location
3.7 Milestone 3: Completion of project execution phase
4 Project closure phase
4.1 Final project signoff
4.2 Successful accomplishment of the project
4.3 Milestone 4: Completing project closure phase
3. Milestone plan (refer to appendix 1)
In order to implement this project five major milestones are highlighted and under each
of the work package more than two activities are presented. It is assumed that if all these
activities are properly assigned and arranged then implementation of the project will become
must easier and error free. For this specific project two project timelines are prepared. For the
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6PROJECT MANAGEMENT
first project the estimated cost is 14,240 and for the revised relocation project the budget that has
been developed costs 13,640. The four milestones for this specific project are also elaborated in
this report.
4. List of the tasks and who is responsible for each task (refer to appendix 2)
The responsibilities given to each of those activities are elaborated in the below section:
Resource Name Description
Project manager
The project manager is responsible to
accomplish the project activities within the
estimated budget of $15,000 and time of 1 year.
However, in between the responsibilities of
taking another apartment as rent is also
responsibility of the project manager.
Travelling cost
The cost of travel is an external cost that is also
the responsibility for the project manager and
finance manager.
Agent cost As the family is going to shift to Perth therefore
the agent is hires to accomplish the other needs
Food cost The cost of food is elaborated by the project
manager
Logistics cost The logistic cost is undertaken by the project
manager
Admission cost This cost is not included to the relocation cost
directly
rental cost The cost assigned for room rent
medical cost Medical cost assigned for the pet and family
Packing cost
first project the estimated cost is 14,240 and for the revised relocation project the budget that has
been developed costs 13,640. The four milestones for this specific project are also elaborated in
this report.
4. List of the tasks and who is responsible for each task (refer to appendix 2)
The responsibilities given to each of those activities are elaborated in the below section:
Resource Name Description
Project manager
The project manager is responsible to
accomplish the project activities within the
estimated budget of $15,000 and time of 1 year.
However, in between the responsibilities of
taking another apartment as rent is also
responsibility of the project manager.
Travelling cost
The cost of travel is an external cost that is also
the responsibility for the project manager and
finance manager.
Agent cost As the family is going to shift to Perth therefore
the agent is hires to accomplish the other needs
Food cost The cost of food is elaborated by the project
manager
Logistics cost The logistic cost is undertaken by the project
manager
Admission cost This cost is not included to the relocation cost
directly
rental cost The cost assigned for room rent
medical cost Medical cost assigned for the pet and family
Packing cost
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT MANAGEMENT
5. Gantt chart indicating the flow of tasks (refer to appendix 3)
Figure 2: Initial project schedule
(Source: created by author)
5. Gantt chart indicating the flow of tasks (refer to appendix 3)
Figure 2: Initial project schedule
(Source: created by author)

8PROJECT MANAGEMENT
Figure 3: Updated project schedule
(Source: created by author)
6. Details of all adjustments made to the schedule
At the initial project the assigned cost is 14,240 and after making all the adjustments the
cost has become 13,640. The numbers of days assigned for some of the activities are reduced to
diminish the overall cost of the project and to keep it within the estimation of $15,000.
Justification for the adjustments
As, initially the cost estimated for this project is 14,240 which is little high therefore, the
cost needed to be reduced to a smaller amount. The final amounted is estimated at 13,640. It is
assumed that the reduced cost will increase the project feasibility. The numbers of days are for
Figure 3: Updated project schedule
(Source: created by author)
6. Details of all adjustments made to the schedule
At the initial project the assigned cost is 14,240 and after making all the adjustments the
cost has become 13,640. The numbers of days assigned for some of the activities are reduced to
diminish the overall cost of the project and to keep it within the estimation of $15,000.
Justification for the adjustments
As, initially the cost estimated for this project is 14,240 which is little high therefore, the
cost needed to be reduced to a smaller amount. The final amounted is estimated at 13,640. It is
assumed that the reduced cost will increase the project feasibility. The numbers of days are for
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9PROJECT MANAGEMENT
the project is reduced to diminish the overall cost. As a whole the project must not exceed the
overall cost of $15,000.
7. A personal reflection on the process
During the implementation of the project I have realized that in order to accomplish any
project successfully there are certain knowledge areas which requires major focus. The project
management practices include communication management, risk management, procurement
management, and logistic management. For this specific project these are the specific
components must be deeply analyzed to avoid overrunning cost and over allocation of budget. In
order to implement this project the project manager requires to follow basic five project
implementation phases in terms of project initiation, planning, execution, control and monitoring
and project closure. The output of one phase is used as the input to the very next phase In other
words the project management phases are all inter related to each other. Therefore, each of these
phase are required to be scrutinized during its design and implementation period. As the budget
estimated for the project is $15,000 therefore, the activities should be arranged such that it can
never exceed the estimation. As this project is not about any kind of Return on Investment (ROI),
thus the resources or each of the activities should have to be selected wisely.
The other responsibility of the project manager is to ensure that project is not at all facing
any kind of risks during its design and implementation period and even after its closure also. In
order to eliminate wastes from project the project manager is required to assign responsibilities
and roles based on skills and knowledge of the resources. In order to execute the plan proper
tools and technologies are also should be adopted and applied accordingly. In fact appropriate
project management strategies are also needed to be used by the project manager during the
the project is reduced to diminish the overall cost. As a whole the project must not exceed the
overall cost of $15,000.
7. A personal reflection on the process
During the implementation of the project I have realized that in order to accomplish any
project successfully there are certain knowledge areas which requires major focus. The project
management practices include communication management, risk management, procurement
management, and logistic management. For this specific project these are the specific
components must be deeply analyzed to avoid overrunning cost and over allocation of budget. In
order to implement this project the project manager requires to follow basic five project
implementation phases in terms of project initiation, planning, execution, control and monitoring
and project closure. The output of one phase is used as the input to the very next phase In other
words the project management phases are all inter related to each other. Therefore, each of these
phase are required to be scrutinized during its design and implementation period. As the budget
estimated for the project is $15,000 therefore, the activities should be arranged such that it can
never exceed the estimation. As this project is not about any kind of Return on Investment (ROI),
thus the resources or each of the activities should have to be selected wisely.
The other responsibility of the project manager is to ensure that project is not at all facing
any kind of risks during its design and implementation period and even after its closure also. In
order to eliminate wastes from project the project manager is required to assign responsibilities
and roles based on skills and knowledge of the resources. In order to execute the plan proper
tools and technologies are also should be adopted and applied accordingly. In fact appropriate
project management strategies are also needed to be used by the project manager during the
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10PROJECT MANAGEMENT
design and development of the project. In addition to this based on requested changes, whether
changes are implementing or not must be monitored by the project managers. The other major
three actions that are to be taken by the project manager include insertion, upgrade and deletion.
The information board should always keep updated according to changing time period.
design and development of the project. In addition to this based on requested changes, whether
changes are implementing or not must be monitored by the project managers. The other major
three actions that are to be taken by the project manager include insertion, upgrade and deletion.
The information board should always keep updated according to changing time period.

11PROJECT MANAGEMENT
References
Ahern, T., Leavy, B., & Byrne, P. J. 2014. Complex project management as complex problem
solving: A distributed knowledge management perspective. International Journal of
Project Management, 32(8), 1371-1381.
Cohen-Vogel, L., Tichnor-Wagner, A., Allen, D., Harrison, C., Kainz, K., Socol, A. R., &
Wang, Q. (2015). Implementing educational innovations at scale: Transforming
researchers into continuous improvement scientists. Educational Policy, 29(1), 257-277.
Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., & de Almeida, L. F. M. 2014. Can
agile project management be adopted by industries other than software
development?. Project Management Journal, 45(3), 21-34.
Conger, S. (2015). Six sigma & business process management. In H&book on Business Process
Management 1 (pp. 127-146). Springer, Berlin, Heidelberg.
First, M. B. (2016). Adopting a continuous improvement model for future DSM revisions. World
Psychiatry, 15(3), 223-224.
Heldman, K. (2015). PMP project management professional exam deluxe study guide: updated
for the (2015) Exam. John Wiley & Sons.
Hornstein, H. A. (2015). The integration of project management & organizational change
management is now a necessity. International Journal of Project Management, 33(2),
291-298.
References
Ahern, T., Leavy, B., & Byrne, P. J. 2014. Complex project management as complex problem
solving: A distributed knowledge management perspective. International Journal of
Project Management, 32(8), 1371-1381.
Cohen-Vogel, L., Tichnor-Wagner, A., Allen, D., Harrison, C., Kainz, K., Socol, A. R., &
Wang, Q. (2015). Implementing educational innovations at scale: Transforming
researchers into continuous improvement scientists. Educational Policy, 29(1), 257-277.
Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., & de Almeida, L. F. M. 2014. Can
agile project management be adopted by industries other than software
development?. Project Management Journal, 45(3), 21-34.
Conger, S. (2015). Six sigma & business process management. In H&book on Business Process
Management 1 (pp. 127-146). Springer, Berlin, Heidelberg.
First, M. B. (2016). Adopting a continuous improvement model for future DSM revisions. World
Psychiatry, 15(3), 223-224.
Heldman, K. (2015). PMP project management professional exam deluxe study guide: updated
for the (2015) Exam. John Wiley & Sons.
Hornstein, H. A. (2015). The integration of project management & organizational change
management is now a necessity. International Journal of Project Management, 33(2),
291-298.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 17
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.