Camden Sickle Cell and
Thalassaemia Service Group
Project Brief
1
Thalassaemia Service Group
Project Brief
1
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

Table of Contents
Introduction......................................................................................................................................3
Task 1...............................................................................................................................................3
Task 2...............................................................................................................................................4
Stakeholder analysis...............................................................................................................4
Task 3...............................................................................................................................................4
Task 4...............................................................................................................................................5
Risk analysis...........................................................................................................................5
Task 5...............................................................................................................................................7
Task 6...............................................................................................................................................8
Appropriate methodology.......................................................................................................8
References......................................................................................................................................10
2
Introduction......................................................................................................................................3
Task 1...............................................................................................................................................3
Task 2...............................................................................................................................................4
Stakeholder analysis...............................................................................................................4
Task 3...............................................................................................................................................4
Task 4...............................................................................................................................................5
Risk analysis...........................................................................................................................5
Task 5...............................................................................................................................................7
Task 6...............................................................................................................................................8
Appropriate methodology.......................................................................................................8
References......................................................................................................................................10
2

Introduction
Project management is defined as process that involves applications of skills along with
experience for managing project. Basically, it involves process to lead the team for attainment of
goals and ensure success within peculiar time frame (Bjorvatn and Wald, 2018). In this report,
the project is carried out for Camden Sickle Cell and Thalassaemia Service Group who are
planning for organising musical concert for raising funds as well as creating awareness. With
reference to this, network diagram, work breakdown structure and stakeholder analysis will be
illustrated. Furthermore, risk analysis will also be conducted by taking into consideration
different methodologies.
Task 1
Solution
The network diagram above has illustrated probable two critical paths:
1→2→4→9→10→21→22 = 109 days
1→2→4→6→7→20→21→22 =109 days
Therefore, the minimum time that is needed for completion of project is around 109 days.
The duration that is set for completing project is 101 days. The extra cost involved within this is
near about £5,000 × 8 which amounts to £ 45,000 of the project due to additional time period of
8 days that are considered for completion.
3
Project management is defined as process that involves applications of skills along with
experience for managing project. Basically, it involves process to lead the team for attainment of
goals and ensure success within peculiar time frame (Bjorvatn and Wald, 2018). In this report,
the project is carried out for Camden Sickle Cell and Thalassaemia Service Group who are
planning for organising musical concert for raising funds as well as creating awareness. With
reference to this, network diagram, work breakdown structure and stakeholder analysis will be
illustrated. Furthermore, risk analysis will also be conducted by taking into consideration
different methodologies.
Task 1
Solution
The network diagram above has illustrated probable two critical paths:
1→2→4→9→10→21→22 = 109 days
1→2→4→6→7→20→21→22 =109 days
Therefore, the minimum time that is needed for completion of project is around 109 days.
The duration that is set for completing project is 101 days. The extra cost involved within this is
near about £5,000 × 8 which amounts to £ 45,000 of the project due to additional time period of
8 days that are considered for completion.
3

Task 2
Stakeholder analysis
The individuals or group of people who have direct or indirect interest within the peculiar project
refers to stakeholders. In context of musical concert, the internal stakeholders are organising
team of events, raw material suppliers, sponsors and many others. On the other hand external
stakeholders are local communities, spectators, government, etc (Demirkesen and Ozorhon,
2017). The power matrix for musical concert is specified below:
Keep satisfied: Within this quadrant, the stakeholders who have low interest are included
but the decision making power is high and scalable for event organisation. For an
instance, government as event is carried out in public domain then they are liable to
ensure that adequate business practices are utilised by them. This makes it important that
all the needs are communicated in an appropriate manner.
Manage closely: Here, those stakeholders are involved who have high interest as well as
high decision making capabilities. An instance can be taken into consideration like
sponsors, event organisers, owners and various others (Ika and et. al, 2020). They are
accountable for ensuring that event is carried out in successful manner and will have high
impact through this. Thus, all the requirements must be included while carrying out
communication.
Monitor: Within this quadrant, stakeholders are regarded those who possess low power
as well as decision making such as spectators who are concerned with results that will be
attained from event. Thus, there is no need to interact all the critical details with such
kind of stakeholders.
Keep informed: This comprises of stakeholders who possess high interest within the
event but decision making is restricted or low. They are volunteers, employees and
workers of event who have organised event. These stakeholders must be informed with
necessary information only but only decisions or information must be interacted that are
concerned with their responsibilities (Kerzner, 2019).
Task 3
By segregating work into different specifications within standard profit methods will be
utilised for making work more congenial as well as rational is referred to work breakdown
4
Stakeholder analysis
The individuals or group of people who have direct or indirect interest within the peculiar project
refers to stakeholders. In context of musical concert, the internal stakeholders are organising
team of events, raw material suppliers, sponsors and many others. On the other hand external
stakeholders are local communities, spectators, government, etc (Demirkesen and Ozorhon,
2017). The power matrix for musical concert is specified below:
Keep satisfied: Within this quadrant, the stakeholders who have low interest are included
but the decision making power is high and scalable for event organisation. For an
instance, government as event is carried out in public domain then they are liable to
ensure that adequate business practices are utilised by them. This makes it important that
all the needs are communicated in an appropriate manner.
Manage closely: Here, those stakeholders are involved who have high interest as well as
high decision making capabilities. An instance can be taken into consideration like
sponsors, event organisers, owners and various others (Ika and et. al, 2020). They are
accountable for ensuring that event is carried out in successful manner and will have high
impact through this. Thus, all the requirements must be included while carrying out
communication.
Monitor: Within this quadrant, stakeholders are regarded those who possess low power
as well as decision making such as spectators who are concerned with results that will be
attained from event. Thus, there is no need to interact all the critical details with such
kind of stakeholders.
Keep informed: This comprises of stakeholders who possess high interest within the
event but decision making is restricted or low. They are volunteers, employees and
workers of event who have organised event. These stakeholders must be informed with
necessary information only but only decisions or information must be interacted that are
concerned with their responsibilities (Kerzner, 2019).
Task 3
By segregating work into different specifications within standard profit methods will be
utilised for making work more congenial as well as rational is referred to work breakdown
4
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

structure or distribution structure. Organisations utilises this approach and leads them to ensure
there liabilities that are associated with the project. This will further aid within coordinating, cost
and ensure that all the activities are done within desired time frame.
Project management illustrates breakdown structure like a progressive breakdown of
work that has to be carried out by the employees associated with the project (Kivilä, Martinsuo
and Vuorinen, 2017). Basically, there exist two kinds of WBS; they are publication based and
tier based. Generally, delivery based approach is utilised by organisation as here emphasis is laid
on delivering project on time with desired standards of preciseness. The work breakdown
structure with respect to music concert is illustrated beneath:
Task 4
Risk analysis
Risk Impact Strategy to mitigate the impact
High noise or volume High The noise pollution will be created via music system
therefore specific permissions must be taken and
kept away from spectators.
5
there liabilities that are associated with the project. This will further aid within coordinating, cost
and ensure that all the activities are done within desired time frame.
Project management illustrates breakdown structure like a progressive breakdown of
work that has to be carried out by the employees associated with the project (Kivilä, Martinsuo
and Vuorinen, 2017). Basically, there exist two kinds of WBS; they are publication based and
tier based. Generally, delivery based approach is utilised by organisation as here emphasis is laid
on delivering project on time with desired standards of preciseness. The work breakdown
structure with respect to music concert is illustrated beneath:
Task 4
Risk analysis
Risk Impact Strategy to mitigate the impact
High noise or volume High The noise pollution will be created via music system
therefore specific permissions must be taken and
kept away from spectators.
5

Risk of thieves High Relevant safety measures must be strict, vigilant and
no individual must be allowed without tickets.
Furthermore, the space must be provided to them for
keeping their things and ensure that they are secured
(Müller, Drouin and Sankaran, 2019).
Disputes Low Difference of opinion or clashes might take place
among crowd therefore relevant security must be
present to ensure event is not impacted.
Stampede Medium It is necessary that adequate entry as well as exit is
formulated for avoiding any critical conditions that
might happen.
Fire casualties Low A relevant fire extinguisher needs to be installed
along with this, fire brigade vehicles needs to be
there at venue.
Stale food items Medium The food items must be approved in terms of their
manufacturing dates and when they are prepared.
Drugs High Drugs must be completely restricted and must not be
allowed in any conditions (Parker, Parsons and
Isharyanto, 2015).
Heat strokes Medium Relevant arrangements need to be made for shades.
Dehydration High Drinking water must be clean within the venue so
that any kind of problems are not faced by guests.
System failure Medium The technical system needs to be checked before the
concert takes place and also have a backup for the
same.
Financial requirements Moderate The budget for event must be clearly specified and
ensured that activities are within this only.
Accidents Low All the necessary medical facilities must be made
available; nurses and doctors must be present at the
premises.
Crowd management High The tickets have to be sold on the basis of capacity of
6
no individual must be allowed without tickets.
Furthermore, the space must be provided to them for
keeping their things and ensure that they are secured
(Müller, Drouin and Sankaran, 2019).
Disputes Low Difference of opinion or clashes might take place
among crowd therefore relevant security must be
present to ensure event is not impacted.
Stampede Medium It is necessary that adequate entry as well as exit is
formulated for avoiding any critical conditions that
might happen.
Fire casualties Low A relevant fire extinguisher needs to be installed
along with this, fire brigade vehicles needs to be
there at venue.
Stale food items Medium The food items must be approved in terms of their
manufacturing dates and when they are prepared.
Drugs High Drugs must be completely restricted and must not be
allowed in any conditions (Parker, Parsons and
Isharyanto, 2015).
Heat strokes Medium Relevant arrangements need to be made for shades.
Dehydration High Drinking water must be clean within the venue so
that any kind of problems are not faced by guests.
System failure Medium The technical system needs to be checked before the
concert takes place and also have a backup for the
same.
Financial requirements Moderate The budget for event must be clearly specified and
ensured that activities are within this only.
Accidents Low All the necessary medical facilities must be made
available; nurses and doctors must be present at the
premises.
Crowd management High The tickets have to be sold on the basis of capacity of
6

venue and no additional passes will not be furnished.
Environmental issues Medium Environmental influence assessment has to be
conducted by pre-planning and adequate space must
be provided for disposing waste.
Accidents with cast Low Crew and cast have to be ensured along with backup
has to be created in case if any accident took place.
Selection of song High The songs must be carefully chosen as it is an event
for social-fund raising.
Accidental damages Low Provisions have to be meant for dealing with any
kind of contingencies.
Influence on local
communities
High The event is carried out for fund raising and has to be
the primary aspect for the concert.
Service motive Medium The message must be communicated clearly as it is
for creating awareness related with Thalassemia.
Event-management team High Only the compassionate individuals will be the part
of management team.
Task 5
Quality Expectation
It is important that quality of lighting and sound is good. Crew along with performers
must possess experience of around 1 year. Furthermore, it is necessary that costumes that are
being used are in good condition as well as the costumes are not in torned so that at the end
moment any kind of difficulties are not faced by them. Photography crew must have high quality
camera, should have high storage space with night vision as well as flash light (Rodríguez-
Rivero and et. al, 2020). The rehearsal must be conducted in order to ensure that all the activities
are synchronised and are managed timely. Furthermore, there have to be adequate number of
security guards for managing crowd and avoid any kind of unwanted situation.
Acceptance Criteria
The project must not be finished in more than 101 days as this will lead them to minimise
the additional cost related with complete project. Sound must be clear and any kind of
disturbance must not be there and on the other hand lighting must be done properly in necessary
places such as rehearsal rooms and all the places of the venue.
7
Environmental issues Medium Environmental influence assessment has to be
conducted by pre-planning and adequate space must
be provided for disposing waste.
Accidents with cast Low Crew and cast have to be ensured along with backup
has to be created in case if any accident took place.
Selection of song High The songs must be carefully chosen as it is an event
for social-fund raising.
Accidental damages Low Provisions have to be meant for dealing with any
kind of contingencies.
Influence on local
communities
High The event is carried out for fund raising and has to be
the primary aspect for the concert.
Service motive Medium The message must be communicated clearly as it is
for creating awareness related with Thalassemia.
Event-management team High Only the compassionate individuals will be the part
of management team.
Task 5
Quality Expectation
It is important that quality of lighting and sound is good. Crew along with performers
must possess experience of around 1 year. Furthermore, it is necessary that costumes that are
being used are in good condition as well as the costumes are not in torned so that at the end
moment any kind of difficulties are not faced by them. Photography crew must have high quality
camera, should have high storage space with night vision as well as flash light (Rodríguez-
Rivero and et. al, 2020). The rehearsal must be conducted in order to ensure that all the activities
are synchronised and are managed timely. Furthermore, there have to be adequate number of
security guards for managing crowd and avoid any kind of unwanted situation.
Acceptance Criteria
The project must not be finished in more than 101 days as this will lead them to minimise
the additional cost related with complete project. Sound must be clear and any kind of
disturbance must not be there and on the other hand lighting must be done properly in necessary
places such as rehearsal rooms and all the places of the venue.
7
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Quality Specification
The acoustic metrics of room are (EDT, T10 , T20 , T30 , Ts , C80 , D50) and the sound
pressure levels are (example LAmaxF, LCPeak,LAeq), frequency spectrums, speech
intelligibility. The A-chain implies artistic chain that involves stage equipments, performers
along with mixing effects that are being made via sound engineers with reference to performers.
Chain B comprises of PA structure that includes preparation of structured signals, enhancers and
extension devices. PA structures denotes transition structure for outdoor environment, stable
structure for having indoor views along with this they are characterised via peculiar recyclability
as well as have restricted levels of sound pressure.
Measures to control the event
1. Minimisation of impact that will be caused by a peculiar hazard
2. Eradicating hazard by execution of adequate support along with medical facilities
(Radujković and Sjekavica, 2017).
3. Maintain quality anticipations by ensuring quality standards.
Task 6
Appropriate methodology
Six Sigma: Here, emphasis is laid on enhancement of performance of project by
improvisation of capabilities. In this stress is being made on minimisation of generation
of waste and opt for waste management practices. This will aid event-management firm
within improvisation of their services along with cost involved.
Waterfall model: This utilises sequential along with linear approach for creation of
project life cycle. It will aid event management firm to segregate event through which
output of one stage acts as input for the other. This comprises of initiation, building,
construction, hiring, execution, etc. This aids them within planning as well as completing
within peculiar time frame.
Agile: The method utilises technology for promoting, developing as well as test project’s
life cycle. Event management firm can effectively utilise the project within the
stakeholder management as well as have communication (Tereso and et. al, 2019). This
8
The acoustic metrics of room are (EDT, T10 , T20 , T30 , Ts , C80 , D50) and the sound
pressure levels are (example LAmaxF, LCPeak,LAeq), frequency spectrums, speech
intelligibility. The A-chain implies artistic chain that involves stage equipments, performers
along with mixing effects that are being made via sound engineers with reference to performers.
Chain B comprises of PA structure that includes preparation of structured signals, enhancers and
extension devices. PA structures denotes transition structure for outdoor environment, stable
structure for having indoor views along with this they are characterised via peculiar recyclability
as well as have restricted levels of sound pressure.
Measures to control the event
1. Minimisation of impact that will be caused by a peculiar hazard
2. Eradicating hazard by execution of adequate support along with medical facilities
(Radujković and Sjekavica, 2017).
3. Maintain quality anticipations by ensuring quality standards.
Task 6
Appropriate methodology
Six Sigma: Here, emphasis is laid on enhancement of performance of project by
improvisation of capabilities. In this stress is being made on minimisation of generation
of waste and opt for waste management practices. This will aid event-management firm
within improvisation of their services along with cost involved.
Waterfall model: This utilises sequential along with linear approach for creation of
project life cycle. It will aid event management firm to segregate event through which
output of one stage acts as input for the other. This comprises of initiation, building,
construction, hiring, execution, etc. This aids them within planning as well as completing
within peculiar time frame.
Agile: The method utilises technology for promoting, developing as well as test project’s
life cycle. Event management firm can effectively utilise the project within the
stakeholder management as well as have communication (Tereso and et. al, 2019). This
8

will aid them within rendering adequate direction through which event can be completed
in desired time frame.
9
in desired time frame.
9

References
Books and Journal
Bjorvatn, T. and Wald, A., 2018. Project complexity and team-level absorptive capacity as
drivers of project management performance. International Journal of Project
Management. 36(6). pp.876-888.
Demirkesen, S. and Ozorhon, B., 2017. Impact of integration management on construction
project management performance. International Journal of Project Management, 35(8),
pp.1639-1654.
Ika, L.A. and et. al, 2020. Cross-learning between project management and international
development: analysis and research agenda. International Journal of Project
Management.
Kerzner, H., 2019. Using the project management maturity model: strategic planning for project
management. John Wiley & Sons.
Kivilä, J., Martinsuo, M. and Vuorinen, L., 2017. Sustainable project management through
project control in infrastructure projects. International Journal of Project
Management, 35(6), pp.1167-1183.
Müller, R., Drouin, N. and Sankaran, S., 2019. Modeling organizational project
management. Project Management Journal, 50(4), pp.499-513.
Parker, D.W., Parsons, N. and Isharyanto, F., 2015. Inclusion of strategic management theories
to project management. International Journal of Managing Projects in Business.
Radujković, M. and Sjekavica, M., 2017. Project management success factors. Procedia
engineering, 196, pp.607-615.
Rodríguez-Rivero, R. and et. al, 2020. Applying the strategic prospective approach to project
management in a development project in Colombia. International Journal of Project
Management.
Tereso, A. and et. al, 2019. Project management practices in private organizations. Project
Management Journal, 50(1), pp.6-22.
(Bjorvatn and Wald, 2018) (LARSON and GRAY, 2018) (Kerzner, 2019) (Parker, Parsons and
Isharyanto, 2015)
10
Books and Journal
Bjorvatn, T. and Wald, A., 2018. Project complexity and team-level absorptive capacity as
drivers of project management performance. International Journal of Project
Management. 36(6). pp.876-888.
Demirkesen, S. and Ozorhon, B., 2017. Impact of integration management on construction
project management performance. International Journal of Project Management, 35(8),
pp.1639-1654.
Ika, L.A. and et. al, 2020. Cross-learning between project management and international
development: analysis and research agenda. International Journal of Project
Management.
Kerzner, H., 2019. Using the project management maturity model: strategic planning for project
management. John Wiley & Sons.
Kivilä, J., Martinsuo, M. and Vuorinen, L., 2017. Sustainable project management through
project control in infrastructure projects. International Journal of Project
Management, 35(6), pp.1167-1183.
Müller, R., Drouin, N. and Sankaran, S., 2019. Modeling organizational project
management. Project Management Journal, 50(4), pp.499-513.
Parker, D.W., Parsons, N. and Isharyanto, F., 2015. Inclusion of strategic management theories
to project management. International Journal of Managing Projects in Business.
Radujković, M. and Sjekavica, M., 2017. Project management success factors. Procedia
engineering, 196, pp.607-615.
Rodríguez-Rivero, R. and et. al, 2020. Applying the strategic prospective approach to project
management in a development project in Colombia. International Journal of Project
Management.
Tereso, A. and et. al, 2019. Project management practices in private organizations. Project
Management Journal, 50(1), pp.6-22.
(Bjorvatn and Wald, 2018) (LARSON and GRAY, 2018) (Kerzner, 2019) (Parker, Parsons and
Isharyanto, 2015)
10
1 out of 10
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.