This project management assignment presents a comprehensive analysis of a project, including the implementation of Microsoft Project for scheduling and resource allocation. The report details project constraints, such as time duration, starting and finishing dates, and the impact of annual holidays on the project timeline. It identifies critical path tasks and suggests strategies to mitigate potential delays. The assignment also addresses resource constraints, explaining how MS Project is used to resolve over-allocation issues and the impact of these constraints on the project's duration and cost. The project's total duration is estimated at 37 weeks, with a cost of 499,120 AUD, and the report includes a revised plan extending the completion period to 52.4 weeks. The report also includes the project management blogs and references used.