Project Management Plan for Server Installation Across 20 PCs

Verified

Added on  2025/08/30

|16
|1610
|61
AI Summary
Desklib provides solved assignments and past papers to help students succeed.
Document Page
Project Management
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Introduction
Project management is one of the most important aspect of any project that is being developed. A
proper management of a project is very necessary in order to develop the project successfully.
The project management basically includes the monitoring and designing of all the processes that
would be in the project. In the report that has been created below, various aspects of project
management would be discussed. In the course of this report a learner would be earning about
various components of project management such as Gantt chart, Work Breakdown structure,
Procurement Plan, Communication Plan, Risk Analysis etc. that would be made for a project of
an organization for running a server over 20 personal computers of the client.
Document Page
Scope Statement
Project Title: Willowdale Mine Site Date Prepared:
Project Scope Description
The organization aims to create a server and then run it to the network to 20 Personal
Computer of the client who has assigned the whole project. All the personal computers are
also required to be installed with the operating system of Window 10 and the whole
configuration of the server needs to be tested properly
Project Deliverables
ï‚· Collecting all the information and resources that might be required for the
implementation of the server
ï‚· Installing the server to all the 20 computers
ï‚· Configuring all the computers with window 10
ï‚· Installing client project software
ï‚· Testing all the 20 computers
ï‚· Testing the server after the implementation
ï‚· Training the clients regarding the server
Project Acceptance Criteria
ï‚· Successfully Installed the server on all the PCs
ï‚· Successfully installed windows 10 in all the PCs
ï‚· Successfully tested the systems for the setup
ï‚· Successfully tested the sever after it has been implemented
ï‚· Successfully trained the client for using the server
ï‚· Deployed the server successfully
Project Exclusions
ï‚· The project excludes the maintenance of the of the server
ï‚· The project also excludes the creation of the network of the systems
ï‚· The whole project excludes the recovery of the data while the installation of Windows
10 in the systems
Document Page
Stake Holder Management Plan
Stakeholder
s
Roles Impact Assessment of Impact
Project
Manager
To Manage all the tasks that are running in the
project.
High Kept Updated
Owner Owner is the person who has the ultimate
ownership of the entire project
Low Kept Updated
Senior
Engineer
Senior engineer is the person who will be
managing the various engineering tasks in the
project such as networking, server
implementation testing etc.
High Involved
Networking
Engineer
The basic task of the networking engineer
would be to configure and install the server on
the network of all 20 computer systems
High Involved
System
Engineer
A system Engineer is the person who will be
configuring the computer as per the
requirement of the project such as, installing
the appropriate operating system and also the
appropriate client project software
Low Involved
Sponsor All the expenses that are to be done in the
development of the project are done by the
sponsor
Low Kept Updated
Tester The testing of the server after completion of the
project would be done by the tester
High Involved
Trainer Trainer is the person who is having the
responsibility of training the employees of the
organization with the server that has been
implemented
Low Kept Updated
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Communication Frequency Goal Owner
Status Report Every Week To know the
current status of the
project
Manager
Modular Report Every Week To know the status
of each module of
the project
Manager
Review At Milestones Assessment of the
deliverables of a
particular phase.
Manager
Budget Meetings At Milestones To know whether
the money that is
being spent is used
properly or nit
Sponsor
Testing Report Weekly after testing starts To know the status
of the test being
done on the project
Manager
System Report Daily To know the
performance of the
system
Manager
Server Updates Daily To know the
performance of the
sever
Manager
Post- Completion Meeting At the end of project To discuss the
whole project and
takeaway ideas.
Manager
Document Page
Risk Analysis
Risk Register
S No. Risk Description Severity Probability Mitigation
1 System Failure The computer on
which the server
is running stops
working.
High Low All the systems must be tested
before being implemented in
the network.
2 Server Failure The server that is
implemented on
the systems
receives a bug
High Low The server must be properly
tested before being
implemented to the network
3 Software Error The client
software is not
working properly
High Medium The software must be chosen
properly
4 Undefined Schedule The schedule of
the tasks is not
properly known
by all the stake
holders
Low High Proper communication must
be done in the whole project
frequently
5 Delay in Delivery Deadline of the
project gets
crossed
Medium Medium The deadline of the project
must be decided while
keeping the errors and delays
in mind
6 Improper Testing The project is
deployed without
proper testing and
some errors are
still left
Medium Medium Proper test cases must be
made for testing the network
and the server
7 Improper Training The employees of
the client’s
organization are
not properly
trained to use the
client software
Low High The training to the employees
must be of high quality as
well as easy to understand.
Document Page
Procurement Plan
1. Planning the management of the Procurement
There are various external requirements that could be needed in order to complete the
given project. To start with, the projects would be needing to download the client
software to which the server that has been created would be installed, hardware
requirements such as wires and modems that would be required for the proper networking
over the server are also in the list of the external resources along with the switches and
hubs which would be needed in order to create a bridge between the system and the
network..
2. Conducting the Procurement
As per the requirement of the project that has to be developed, these resources that are
needed are purchased or collected from the resources seller that is chosen on the basis of
the quality, requirement and h the cost of the resources.
3. Controlling the Procurement
After the person or the organization from whom or which the resources are to be bought,
the paper work is to be started and contracts and agreement are made in order to make
sure that the resources that were chosen were delivered to the organization on time and
that too on a particular date and time.
4. Close Procurement
After the delivery has been done to the organization it must be made sure that the
delivery that has been sent is the same as mentioned to the seller and the whole
procurement process is closed in a proper manner.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Gant chart
Task Name Duration Start Finish Predecessors Resource Names Cost
Project
Management 29 days Mon
10/12/09
Thu
11/19/09 $12,000.00
Requirement
Gathering 4 days Mon
10/12/09
Thu
10/15/09 $2,880.00
Requirement
Analysis 2 days Mon
10/12/09
Tue
10/13/09
Owner,Project
Manager,Sponsor $1,440.00
Purchasing the
resources 2 days Wed
10/14/09
Thu
10/15/09 3 Owner,Project
Manager,Sponsor $1,440.00
Milestone 1 0 days Thu
10/15/09
Thu
10/15/09 4 $0.00
Server Installation 3 days Fri
10/16/09
Tue
10/20/09 $840.00
Configuring the
server 2 days Fri
10/16/09
Mon
10/19/09 4
Networking
Engineer,Senior
Engineer
$560.00
Installing the
server 1 day Tue
10/20/09
Tue
10/20/09 7
Networking
Engineer,Senior
Engineer
$280.00
Milestone 2 0 days Tue
10/20/09
Tue
10/20/09 8 $0.00
Installation of
server software 2 days Wed
10/21/09
Thu
10/22/09 $600.00
Download of the
Server Software 1 day Wed
10/21/09
Wed
10/21/09 8 Senior Engineer,
Sponsor $320.00
Installing the
server software 1 day Thu
10/22/09
Thu
10/22/09 11
Networking
Engineer, Senior
Engineer
$280.00
Milestone 3 0 days Thu
10/22/09
Thu
10/22/09 12 $0.00
Setup the client's
computer with
Windows 10
3 days Fri
10/23/09
Tue
10/27/09 $840.00
Checking for the
systems without
windows 10
1 day Fri
10/23/09
Fri
10/23/09 12
Senior
Engineer,System
Engineer
$280.00
Installing
windows 10 2 days Mon
10/26/09
Tue
10/27/09 15
Senior
Engineer,System
Engineer
$560.00
Milestone 4 0 days Tue
10/27/09
Tue
10/27/09 16 $0.00
Installing project
software on each
2 days Wed
10/28/09
Thu
10/29/09
$600.00
Document Page
system
Downloading
Project Software 1 day Wed
10/28/09
Wed
10/28/09 16 Senior
Engineer,Sponsor $320.00
Installing project
software on each
system
1 day Thu
10/29/09
Thu
10/29/09 19
Senior
Engineer,System
Engineer
$280.00
Milestone 5 0 days Thu
10/29/09
Thu
10/29/09 20 $0.00
Parsing and
Importing Data 2 days Fri
10/30/09
Mon
11/2/09 $720.00
Parsing 1 day Fri
10/30/09
Fri
10/30/09 20
Project
Manager,System
Engineer
$360.00
Importing 1 day Mon
11/2/09
Mon
11/2/09 23
Project
Manager,System
Engineer
$360.00
Millstone 6 0 days Mon
11/2/09
Mon
11/2/09 24 $0.00
User Acceptance
Testing 4 days Tue
11/3/09
Fri
11/6/09 $1,120.00
Testing 2 days Tue
11/3/09
Wed
11/4/09 24
Senior
Engineer,Testing
Engineer
$560.00
Debugging 2 days Thu
11/5/09 Fri 11/6/09 27
Testing
Engineer,Senior
Engineer
$560.00
Milestone 7 0 days Fri 11/6/09 Fri 11/6/09 28 $0.00
Training 4 days Mon
11/9/09
Thu
11/12/09 $1,280.00
Training the
Employees 2 days Mon
11/9/09
Tue
11/10/09 28 Project
Manager,Trainer $640.00
Assessment of
Training 2 days Wed
11/11/09
Thu
11/12/09 31 Project
Manager,Trainer $640.00
Milestone 8 0 days Thu
11/12/09
Thu
11/12/09 32 $0.00
Go Live Support 3 days Fri
11/13/09
Tue
11/17/09 $1,840.00
Beta
Implementation 2 days Fri
11/13/09
Mon
11/16/09 32 Owner,Project
Manager $1,120.00
Deployment 1 day Tue
11/17/09
Tue
11/17/09 35
Owner,Project
Manager,Senior
Engineer
$720.00
Milestone 9 0 days Tue
11/17/09
Tue
11/17/09 36 $0.00
Project Review 2 days Wed Thu $1,280.00
Document Page
11/18/09 11/19/09
Analysis 1 day Wed
11/18/09
Wed
11/18/09 36
Owner,Project
Manager,Senior
Engineer
$720.00
Documentation 1 day Thu
11/19/09
Thu
11/19/09 39 Owner,Project
Manager $560.00
Milestone 10 0 days Thu
11/19/09
Thu
11/19/09 40 $0.00
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Work Breakdown Structure
Project
Manegment
Requirement
Gathering
Requirement
Analysis
Purchasing the
resources
Server
Installation
Configuring the
server
Installing the
server
Installation of
Server Software
Download of
the server
software
Installing the
softwware
Setup Client's
computer with
Windows 10
Checking for
system without
Windows 10
Installing
windows 10
Installing
project software
Download
project software
Installing
project software
Parsing and
Importing Data
Parsing
Importing
User Accetance
Testing
Testing
Debugging
Training
Training
Employees
Assessment
Go Live Support
Beta
Implementation
Deployment
Project Review
Analysis
Documentation
Document Page
Cost Baseline
Name Cost Baseline
Cost
Cost
Variance
Project Manager $3,600.00 $0.00 $3,600.00
Owner $2,880.00 $0.00 $2,880.00
Senior Engineer $2,560.00 $0.00 $2,560.00
Netowrking Engineer $480.00 $0.00 $480.00
System Engineer $720.00 $0.00 $720.00
Testing Engineer $480.00 $0.00 $480.00
Sponsor $960.00 $0.00 $960.00
Trainer $320.00 $0.00 $320.00
Name Actual
Work
Actual Cost Standard
Rate
Project Manager 0 hrs $0.00 $30.00/hr
Owner 0 hrs $0.00 $40.00/hr