Comprehensive Project Management Report: 94WBR-shed Project Analysis
VerifiedAdded on 2021/05/31
|15
|3725
|90
Report
AI Summary
This report provides a detailed analysis of the project management strategies for the 94WBR-shed project. It covers various aspects of project management, including project initiation, planning, implementation, controlling, and closing phases. The report explores the use of different project management tools like Gantt charts, Work Breakdown Structures, and logic networks. It delves into the management of project scope, risk, communication, procurement, stakeholders, human resources, quality, time, cost, safety, and integration. Each area is discussed with specific strategies and processes relevant to the 94WBR-shed project, ensuring a comprehensive understanding of how to successfully manage all facets of the project from start to finish, including risk identification, quantification, and response strategies. The report also emphasizes the importance of stakeholder management, quality assurance, and effective communication throughout the project lifecycle.

Project Management
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Table of Contents
1. Introduction & basic parameters.........................................................................................3
2. Management of 94WBR-shed project................................................................................3
3. TOOLS to manage the project............................................................................................4
4. Managing SCOPE of the 94WBR-shed project..................................................................5
5. Managing RISK of the 94WBR-shed project.....................................................................6
6. Managing COMMUNICATION of the 94WBR-shed project...........................................7
7. Managing PROCUREMENT of the 94WBR-shed project................................................7
8. Managing STAKEHOLDERS of the 94WBR-shed project...............................................8
9. Managing our HR of the 94WBR-shed project..................................................................9
10. Managing QUALITY of the 94WBR-shed project.........................................................9
11. Managing TIME of the 94WBR-shed project...............................................................10
12. Managing COST of the 94WBR-shed project..............................................................11
13. Managing SAFETY of the 94WBR-shed project.........................................................12
14. Managing INTEGRATION of the 94WBR-shed project.............................................12
References................................................................................................................................13
1. Introduction & basic parameters.........................................................................................3
2. Management of 94WBR-shed project................................................................................3
3. TOOLS to manage the project............................................................................................4
4. Managing SCOPE of the 94WBR-shed project..................................................................5
5. Managing RISK of the 94WBR-shed project.....................................................................6
6. Managing COMMUNICATION of the 94WBR-shed project...........................................7
7. Managing PROCUREMENT of the 94WBR-shed project................................................7
8. Managing STAKEHOLDERS of the 94WBR-shed project...............................................8
9. Managing our HR of the 94WBR-shed project..................................................................9
10. Managing QUALITY of the 94WBR-shed project.........................................................9
11. Managing TIME of the 94WBR-shed project...............................................................10
12. Managing COST of the 94WBR-shed project..............................................................11
13. Managing SAFETY of the 94WBR-shed project.........................................................12
14. Managing INTEGRATION of the 94WBR-shed project.............................................12
References................................................................................................................................13

1. Introduction & basic parameters
Project management is considered as a critical process in any type of project. It connects all
the other activities of the project altogether. There are many of the activities that take place in
project management (Axelos, 2018). Here, the plan for managing the 94WBR-shed project is
developed. The various plans for meeting the needs of the clients and delivering the quality
project are developed. The different tool for managing the project is presented. The processes
that are used for managing the scope, risks, communication, human resources, procurement,
stakeholders, quality, time, cost, integration and safety of the 94WBR-shed project are
presented. The processes for managing these areas of the project are described to demonstrate
the understanding about managing the project.
2. Management of 94WBR-shed project
For managing 94WBR-shed project, five phases will be considered that are:
Project Initiation: in this phase, the requirements will be gathered such as client’s
requirements are identified and the changes in the requirements take place. In the end, the
phase ends with signing off of the requirements.
Project Planning: In this phase, the requirements will be addressed like budget,
requirements scope and timelines. The schedule will be developed after the project plan is
derived. Resources will be allocated as per the schedule and budget (Wrike, 2018).
Project Implementation: the team will carry out the activities assigned to them as per the
schedule and the progress will be tracked with project schedule. The senior management will
be provided with updates of the project progress. The cost and efforts will be tracked for
identifying the progress.
Project management is considered as a critical process in any type of project. It connects all
the other activities of the project altogether. There are many of the activities that take place in
project management (Axelos, 2018). Here, the plan for managing the 94WBR-shed project is
developed. The various plans for meeting the needs of the clients and delivering the quality
project are developed. The different tool for managing the project is presented. The processes
that are used for managing the scope, risks, communication, human resources, procurement,
stakeholders, quality, time, cost, integration and safety of the 94WBR-shed project are
presented. The processes for managing these areas of the project are described to demonstrate
the understanding about managing the project.
2. Management of 94WBR-shed project
For managing 94WBR-shed project, five phases will be considered that are:
Project Initiation: in this phase, the requirements will be gathered such as client’s
requirements are identified and the changes in the requirements take place. In the end, the
phase ends with signing off of the requirements.
Project Planning: In this phase, the requirements will be addressed like budget,
requirements scope and timelines. The schedule will be developed after the project plan is
derived. Resources will be allocated as per the schedule and budget (Wrike, 2018).
Project Implementation: the team will carry out the activities assigned to them as per the
schedule and the progress will be tracked with project schedule. The senior management will
be provided with updates of the project progress. The cost and efforts will be tracked for
identifying the progress.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Project Controlling: with the help of the communication plan, quality assurance tests and
the project plan, the project will be controlled. The success of the activities will be
ascertained through comparing the outcomes with the planned outcomes.
Project Closing: after meeting the requirements, the implemented system will be handed
over and the project will closeout. The entire project will be evaluated and steps will be taken
to identify and reduce mistakes (Bisk , 2018).
3. TOOLS to manage the project
The management of the project is important in order to accomplish the project in the
available time and resources. There are different types of tools that are used for project
management such as Gantt chart, Work Breakdown Structure and logic network.
Gantt chart: Gantt chart is a project management tools that help in demonstrating the
relationship among the tasks. It also helps in tracking the time, demonstrate the phases,
milestones, resources and scheduling the project and the project activities (Maserang, 2002).
Hence, in the 94WBR-shed project, we can use this tool as it will help in establishing
relationship among the tasks, assigning resources, developing schedule and indicating
milestones of the project.
Work Breakdown Structure: it is mainly a tool for a hierarchical breakdown of the project
deliverables that are required to be accomplished. It helps in braking down the deliverables
into manageable parts that can be scheduled with cost estimation (Haughey, 2018). In the
94WBR-shed project, the use of WBS will support in breaking down the tasks of the project
into manageable parts and will also help in making the project and the associated people to
understand about the order of the tasks.
the project plan, the project will be controlled. The success of the activities will be
ascertained through comparing the outcomes with the planned outcomes.
Project Closing: after meeting the requirements, the implemented system will be handed
over and the project will closeout. The entire project will be evaluated and steps will be taken
to identify and reduce mistakes (Bisk , 2018).
3. TOOLS to manage the project
The management of the project is important in order to accomplish the project in the
available time and resources. There are different types of tools that are used for project
management such as Gantt chart, Work Breakdown Structure and logic network.
Gantt chart: Gantt chart is a project management tools that help in demonstrating the
relationship among the tasks. It also helps in tracking the time, demonstrate the phases,
milestones, resources and scheduling the project and the project activities (Maserang, 2002).
Hence, in the 94WBR-shed project, we can use this tool as it will help in establishing
relationship among the tasks, assigning resources, developing schedule and indicating
milestones of the project.
Work Breakdown Structure: it is mainly a tool for a hierarchical breakdown of the project
deliverables that are required to be accomplished. It helps in braking down the deliverables
into manageable parts that can be scheduled with cost estimation (Haughey, 2018). In the
94WBR-shed project, the use of WBS will support in breaking down the tasks of the project
into manageable parts and will also help in making the project and the associated people to
understand about the order of the tasks.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Logic network: This tool helps in demonstrating the sequence of the tasks or the activities in
project. It indicates which activity will logically take place first or follow another activity.
The milestones and the critical path can be identified through this tool. The dependencies
workflow and timescale can be understood through logic network (Haughey, 2018). In the
94WBR-shed project, this tool can be used for understanding the sequence, critical path, time
scale and workflow.
4. Managing SCOPE of the 94WBR-shed project
The scope of the project is to accomplish the 94WBR-shed project that includes some minor
demolition works in the backyard and construction of a large shed on the property on time.
The scope of this project can be managed through following the three steps that are planning,
controlling and closing which are the key steps in scope management of the project.
In the planning of the scope of the project it includes defining the work that should be
accomplished and planning to manage the project. Hence, this should define the work related
to 94WBR-shed project to be accomplished.
In controlling and the monitoring process, it is important to focus on tracking, controlling
scope creep, approval and disapproval of the changes and documentation tracking (APM,
2018). Hence, all the documents related to 94WBR-shed project should be tracked and all the
changes should be evaluated.
In closing of the project scope, the audit related to the deliverables of the project and the
evaluation of the outcomes in comparison to the original plan is performed. Hence, the
deliverables of 94WBR-shed project should be audited and the original plan should be
compared with the outcomes (Monnappa, 2018).
project. It indicates which activity will logically take place first or follow another activity.
The milestones and the critical path can be identified through this tool. The dependencies
workflow and timescale can be understood through logic network (Haughey, 2018). In the
94WBR-shed project, this tool can be used for understanding the sequence, critical path, time
scale and workflow.
4. Managing SCOPE of the 94WBR-shed project
The scope of the project is to accomplish the 94WBR-shed project that includes some minor
demolition works in the backyard and construction of a large shed on the property on time.
The scope of this project can be managed through following the three steps that are planning,
controlling and closing which are the key steps in scope management of the project.
In the planning of the scope of the project it includes defining the work that should be
accomplished and planning to manage the project. Hence, this should define the work related
to 94WBR-shed project to be accomplished.
In controlling and the monitoring process, it is important to focus on tracking, controlling
scope creep, approval and disapproval of the changes and documentation tracking (APM,
2018). Hence, all the documents related to 94WBR-shed project should be tracked and all the
changes should be evaluated.
In closing of the project scope, the audit related to the deliverables of the project and the
evaluation of the outcomes in comparison to the original plan is performed. Hence, the
deliverables of 94WBR-shed project should be audited and the original plan should be
compared with the outcomes (Monnappa, 2018).

5. Managing RISK of the 94WBR-shed project
In all the projects, the risk is inevitable. It is important to ensure that the risks are minimal.
The risks can impact the project positively and negatively. For managing the risks of the
94WBR-shed project, fur steps will be considered:
Risk Identification: the risks of the projects can be identified through different strategies and
brain storming. After the identification of the risks, it should be handled by the project
manager and team. The major risks in the project can be budget risk, supplier risk and
resource risk. It is important to manage these risks for the accomplishment of the project on
time (APM, 2018).
Risk Quantification: the evaluation of the identified risks can be performed on the basis of
quantity. The analysis of the likelihood of the risks can be ascertained through the matrix
indicating probability and impact. The matrix will include four categories that are low, high
medium and critical. As per the level of the impact and probability, the risks can be
managed.
Risk Response: it is important to minimize or eliminate the risk to reduce its effect upon the
project. Hence, as per the quantification of the identified risks of the project, the response
strategies for the risks can be implemented that are risk avoidance, risk mitigation, corrective
action and risk acceptance (PB, 2018).
Risk Monitoring and Control: The monitoring of the risks on the regular basis will be
conducted. The changes will be implemented and the new risks will be identified through
evaluating and monitoring (Tutorials Point, 2018).
In all the projects, the risk is inevitable. It is important to ensure that the risks are minimal.
The risks can impact the project positively and negatively. For managing the risks of the
94WBR-shed project, fur steps will be considered:
Risk Identification: the risks of the projects can be identified through different strategies and
brain storming. After the identification of the risks, it should be handled by the project
manager and team. The major risks in the project can be budget risk, supplier risk and
resource risk. It is important to manage these risks for the accomplishment of the project on
time (APM, 2018).
Risk Quantification: the evaluation of the identified risks can be performed on the basis of
quantity. The analysis of the likelihood of the risks can be ascertained through the matrix
indicating probability and impact. The matrix will include four categories that are low, high
medium and critical. As per the level of the impact and probability, the risks can be
managed.
Risk Response: it is important to minimize or eliminate the risk to reduce its effect upon the
project. Hence, as per the quantification of the identified risks of the project, the response
strategies for the risks can be implemented that are risk avoidance, risk mitigation, corrective
action and risk acceptance (PB, 2018).
Risk Monitoring and Control: The monitoring of the risks on the regular basis will be
conducted. The changes will be implemented and the new risks will be identified through
evaluating and monitoring (Tutorials Point, 2018).
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6. Managing COMMUNICATION of the 94WBR-shed project
In the 94WBR-shed project, the communication management is important for ensuring
appropriate and timely storage, distribution, collection and generation of the information.
This will consider that who need what type of information and at what time along with the
goal of communicating the information as well as the channel of communication. The
planning to manage the flow of communication among stakeholders will involve:
Identification of information to be communicated
Identification of the target audience for the communication
Selection of the communication format and time
Approval for communication
Communication of the message through communication channel
Collecting feedback and improving communication processes (Goudar, 2018).
7. Managing PROCUREMENT of the 94WBR-shed project
In the 94WBR-shed project, the procurement management is important for establishing
relationship with the vendors of the goods and the services throughout the product life cycle.
The procurements management includes mainly three processes that are:
Planning Process: In the planning process, the official plan for the procurement
management will be developed. The decision related to items to be procured internally and
externally outsourced will be taken. This will impact the financial scope and the budget of the
project. Sample documents of procurements will be prepared. The criteria framework for
selecting potential vendors will be developed. The selection matrix will be developed on the
basis of requirements, budget, risks, schedule and scope of project.
In the 94WBR-shed project, the communication management is important for ensuring
appropriate and timely storage, distribution, collection and generation of the information.
This will consider that who need what type of information and at what time along with the
goal of communicating the information as well as the channel of communication. The
planning to manage the flow of communication among stakeholders will involve:
Identification of information to be communicated
Identification of the target audience for the communication
Selection of the communication format and time
Approval for communication
Communication of the message through communication channel
Collecting feedback and improving communication processes (Goudar, 2018).
7. Managing PROCUREMENT of the 94WBR-shed project
In the 94WBR-shed project, the procurement management is important for establishing
relationship with the vendors of the goods and the services throughout the product life cycle.
The procurements management includes mainly three processes that are:
Planning Process: In the planning process, the official plan for the procurement
management will be developed. The decision related to items to be procured internally and
externally outsourced will be taken. This will impact the financial scope and the budget of the
project. Sample documents of procurements will be prepared. The criteria framework for
selecting potential vendors will be developed. The selection matrix will be developed on the
basis of requirements, budget, risks, schedule and scope of project.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Selection Process: The different vendors will be compared and the best ones will be selected.
Procurement contracts will be decided and the resource calendars will be created. The
changes in the project will be made as per the resource calendars
Administration Process: The tools and techniques will be used for managing the
relationship with the vendors. The changes in the project will occur due to the development
of the procurement spreadsheets and documents. The changes in the contract will be
evaluated through centralized contract system to identify the need of change in the contract.
Closing process: It involves noting successful processes, weaknesses and summarizing
future needs of the project. Audits can be done through utilizing performance matrices to
grade overall project (Best Value Schools, 2018).
8. Managing STAKEHOLDERS of the 94WBR-shed project
The stakeholders’ management is considered about meeting the expectations of the
stakeholders of the project. It is important to keep the stakeholders of the project happy. The
analysis of the stakeholders is first priority in the stakeholders’ management. The
stakeholders are classified and the requirements and the needs of the stakeholders are
identified. The strategies are used for managing the stakeholders.
For managing customers, the needs of the customers, their culture are identified before
execution of project to resolve conflicts. Project team members are managed by satisfying
them through communicating the information in meetings. The executives are managed
through providing them with the milestone plan and they are provided with the updated
information related to risks in the project. The resource managers are managed through
establishing good relationship so that they can fulfil the request related to manpower or
equipment (Wrike Inc. , 2018).
Procurement contracts will be decided and the resource calendars will be created. The
changes in the project will be made as per the resource calendars
Administration Process: The tools and techniques will be used for managing the
relationship with the vendors. The changes in the project will occur due to the development
of the procurement spreadsheets and documents. The changes in the contract will be
evaluated through centralized contract system to identify the need of change in the contract.
Closing process: It involves noting successful processes, weaknesses and summarizing
future needs of the project. Audits can be done through utilizing performance matrices to
grade overall project (Best Value Schools, 2018).
8. Managing STAKEHOLDERS of the 94WBR-shed project
The stakeholders’ management is considered about meeting the expectations of the
stakeholders of the project. It is important to keep the stakeholders of the project happy. The
analysis of the stakeholders is first priority in the stakeholders’ management. The
stakeholders are classified and the requirements and the needs of the stakeholders are
identified. The strategies are used for managing the stakeholders.
For managing customers, the needs of the customers, their culture are identified before
execution of project to resolve conflicts. Project team members are managed by satisfying
them through communicating the information in meetings. The executives are managed
through providing them with the milestone plan and they are provided with the updated
information related to risks in the project. The resource managers are managed through
establishing good relationship so that they can fulfil the request related to manpower or
equipment (Wrike Inc. , 2018).

9. Managing our HR of the 94WBR-shed project
In managing human resources, it is important to organize, manage and lead the team
members of the project. The people are assigned with the responsibilities and roles for
accomplishing the project on time. The processes that are involved in human resource
management are:
Human resource management plan: the identification and documentation of the project
responsibilities roles, required skills, creating staff management plan and reporting
relationships will be included in this process.
Acquiring project team: This process includes the confirmation of the availability of the
human resources and acquiring the required team to accomplish the tasks of the project.
Developing project team: improving the interaction among the team members, improving
competencies and team environment is included in this process for enhancing the
performance of the project.
Managing project team: the performance of the team members will be tracked in this
process. The team will be provided with the feedback and the issues of the team will be
resolved along with managing the change (Murdick, 1976).
10. Managing QUALITY of the 94WBR-shed project
Quality management of the project is important for delivering good quality of project. The
quality management includes three phases that are:
Quality planning: It involves the identification of the quality requirements for the project
and the deliverables. The documentation of the measures to meet the quality requirements is
In managing human resources, it is important to organize, manage and lead the team
members of the project. The people are assigned with the responsibilities and roles for
accomplishing the project on time. The processes that are involved in human resource
management are:
Human resource management plan: the identification and documentation of the project
responsibilities roles, required skills, creating staff management plan and reporting
relationships will be included in this process.
Acquiring project team: This process includes the confirmation of the availability of the
human resources and acquiring the required team to accomplish the tasks of the project.
Developing project team: improving the interaction among the team members, improving
competencies and team environment is included in this process for enhancing the
performance of the project.
Managing project team: the performance of the team members will be tracked in this
process. The team will be provided with the feedback and the issues of the team will be
resolved along with managing the change (Murdick, 1976).
10. Managing QUALITY of the 94WBR-shed project
Quality management of the project is important for delivering good quality of project. The
quality management includes three phases that are:
Quality planning: It involves the identification of the quality requirements for the project
and the deliverables. The documentation of the measures to meet the quality requirements is
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

prepared. The quality checklists, quality metrics and quality management plan are the outputs
of this process (Chandana, 2017). As meeting the needs of the customers and the stakeholders
is the objective of this project hence the plan will focus on it for this project.
Quality assurance: The verification of the processes of the project is performed in this phase
of quality management plan to deliver good quality of project. The project audits and the
process checklist are the methods that can be used for quality assurance of the project.
Quality control: The verification of the project about whether the quality requirements are
met or not are included in this process. Quality control of project can be done through testing
and peer reviews. The results of the process will provide with the information whether the
corrective actions are needed or not (PROJECT-MANAGEMENT-SKILLS, 2018).
11. Managing TIME of the 94WBR-shed project
The time management of the project is important as it affects the overall cost of the project.
the process of time management includes:
Defining activities: All the activities of the project are defined in this process
Sequencing activities: The defined activities are arranged in a sequence to be executed. The
interdependencies should be considered while sequencing
Resource estimation: the resources needed to accomplish the activity are estimated. The
duration of activity depends upon allocated resources. Resource allocation should be clear to
project team so that the time can be managed accurately.
Duration and effort estimation: the duration of each activity should be estimated through
estimation mechanisms like WBS. After this, the critical path of project must be determined
to identify the total duration of project.
of this process (Chandana, 2017). As meeting the needs of the customers and the stakeholders
is the objective of this project hence the plan will focus on it for this project.
Quality assurance: The verification of the processes of the project is performed in this phase
of quality management plan to deliver good quality of project. The project audits and the
process checklist are the methods that can be used for quality assurance of the project.
Quality control: The verification of the project about whether the quality requirements are
met or not are included in this process. Quality control of project can be done through testing
and peer reviews. The results of the process will provide with the information whether the
corrective actions are needed or not (PROJECT-MANAGEMENT-SKILLS, 2018).
11. Managing TIME of the 94WBR-shed project
The time management of the project is important as it affects the overall cost of the project.
the process of time management includes:
Defining activities: All the activities of the project are defined in this process
Sequencing activities: The defined activities are arranged in a sequence to be executed. The
interdependencies should be considered while sequencing
Resource estimation: the resources needed to accomplish the activity are estimated. The
duration of activity depends upon allocated resources. Resource allocation should be clear to
project team so that the time can be managed accurately.
Duration and effort estimation: the duration of each activity should be estimated through
estimation mechanisms like WBS. After this, the critical path of project must be determined
to identify the total duration of project.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Schedule development: schedule of project is developed with the help of the duration,
sequence and resources for each activity. The schedule can be developed using Gantt chart in
MS project. It can help in monitoring the activities visually.
Schedule control: Update of the project schedule is important for executing the change
(Tutorials Point, 2018).
12. Managing COST of the 94WBR-shed project
Cost management help in accomplishing the project within the approved budget. The process
of cost management includes:
Project Cost Estimating: Estimation of the total cost for accomplishment of all the
activities of the project is included in this process. The estimation of cost is done
considering materials, equipments, labor, facilities and services.
Project Cost Budgeting: the information related to creating cost baseline of the project is
obtained after the estimation of cost. The budget of the project is formed by the approved
cost baseline. It includes cost estimation of individual activity over project life. The
expenditures are measured against the cost baseline.
Project Cost Control: the approved budget and the cost baseline help in approaching to
execution phase. The monitoring of the status of the activities is done in the execution
phase. The variation in quality, schedule or scope of the activity impacts cost. Hence,
checking the status of every activity against baseline is important for cost control. The
performance of project can be determined through it. The need to take corrective actions
can be determined through this information (PROJECT-MANAGEMENT-SKILLS,
2018).
sequence and resources for each activity. The schedule can be developed using Gantt chart in
MS project. It can help in monitoring the activities visually.
Schedule control: Update of the project schedule is important for executing the change
(Tutorials Point, 2018).
12. Managing COST of the 94WBR-shed project
Cost management help in accomplishing the project within the approved budget. The process
of cost management includes:
Project Cost Estimating: Estimation of the total cost for accomplishment of all the
activities of the project is included in this process. The estimation of cost is done
considering materials, equipments, labor, facilities and services.
Project Cost Budgeting: the information related to creating cost baseline of the project is
obtained after the estimation of cost. The budget of the project is formed by the approved
cost baseline. It includes cost estimation of individual activity over project life. The
expenditures are measured against the cost baseline.
Project Cost Control: the approved budget and the cost baseline help in approaching to
execution phase. The monitoring of the status of the activities is done in the execution
phase. The variation in quality, schedule or scope of the activity impacts cost. Hence,
checking the status of every activity against baseline is important for cost control. The
performance of project can be determined through it. The need to take corrective actions
can be determined through this information (PROJECT-MANAGEMENT-SKILLS,
2018).

13. Managing SAFETY of the 94WBR-shed project
Safety management is important for ensuring the safety and health at workplace. the process
includes:
Hazard identification and risk assessment: the hazards should be identified and assessed
on regular basis. It involves hazard identification, risk rating, control and review and taking
risk control measures. After identification, the rating to the risk can help in identifying the
high level of risk and the actions to control such risks.
Training and continuous improvement: the training should be provided to the project team
in order to reduce accidents by providing information for wearing safety equipments and
careful handling of the various machines and equipments. In the training, the team will be
able to develop the skills to perform the activity with safety and skills.
Reporting: Any type of accident during the project should be report and should be further
initiated to identify the cause. Treating the injuries of individuals and taking actions to reduce
the risks of accidents is important for improving the commitment of the project team towards
the project and the organization. Considering team’s safety can improve their commitment.
Reviewing: reviewing the safety plan and the effectiveness of the plan should be review to
identify whether the plan is able to meet the expectations or not. The action plans for the
improvement of the safety should be developed (Wordpress, 2002).
14. Managing INTEGRATION of the 94WBR-shed project
Integration management involves the activities for defining, identifying, combining,
coordinating and unifying the different processes of the project. It includes:
Safety management is important for ensuring the safety and health at workplace. the process
includes:
Hazard identification and risk assessment: the hazards should be identified and assessed
on regular basis. It involves hazard identification, risk rating, control and review and taking
risk control measures. After identification, the rating to the risk can help in identifying the
high level of risk and the actions to control such risks.
Training and continuous improvement: the training should be provided to the project team
in order to reduce accidents by providing information for wearing safety equipments and
careful handling of the various machines and equipments. In the training, the team will be
able to develop the skills to perform the activity with safety and skills.
Reporting: Any type of accident during the project should be report and should be further
initiated to identify the cause. Treating the injuries of individuals and taking actions to reduce
the risks of accidents is important for improving the commitment of the project team towards
the project and the organization. Considering team’s safety can improve their commitment.
Reviewing: reviewing the safety plan and the effectiveness of the plan should be review to
identify whether the plan is able to meet the expectations or not. The action plans for the
improvement of the safety should be developed (Wordpress, 2002).
14. Managing INTEGRATION of the 94WBR-shed project
Integration management involves the activities for defining, identifying, combining,
coordinating and unifying the different processes of the project. It includes:
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 15
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.