This project management report details the construction and furnishing of the St. Dismas assisted living facility. The project, divided into four phases, focuses on the construction of a facility to house approximately 150 patients. The report outlines project goals, objectives, and scope, including the construction phases: excavation and foundation, structural steel framing, enclosure development, and interior furnishing. It presents a work breakdown structure, project schedule via a Gantt chart and network diagram, and a bibliography of relevant project management resources. The project aims to provide convenient living facilities for patients, expand the medical center, and improve patient care by offering convenient access to rehabilitation programs. The report provides a detailed overview of the project's timeline, phases, and deliverables.
Document Page
Running Head: PROJECT MANAGEMENT
PROJ6002: St. Dismas Assisted Living Facility Project
Name of the Student
Name of the University
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1PROJECT MANAGEMENT
Project Goals and Objectives
The overall project requires the construction and development of the proposed St. Dismas
assisted living facility for the patients of St. Dismas Medical Centre. Since, the overall project is
of very large scale, it has been divided into four parts with each part given to each of four
different contractors. The four parts of the overall project include Operations, Legal and
Licensing, Marketing and Construction and Furnishing. Of the four, the focus of this particular
report is on the Construction and Furnishing Project for St. Dismas.
The goal of the project is the construction of the St. Dismas assisted living facility as well
as its furnishing such that it is ready for delivery and use by the patients of the medical centre. As
per the initial plan, the goal is to provide living facility for around 150 patients with proper
furnishing, facilities and amenities required for the patients.
The objectives of the project are as follows.
Residence of the Patients – It has been found that in the current situation, the Medical
Centre is losing the number of patients because there are no medical assistance facilities where
the injured patients can stay and undergo rehabilitation programs. Current system only allows
immediate therapy and medication for the patients after which, they need to visit the medical
centre on regular basis for check-ups and periodic medication process, which is very
inconvenient, especially for the heavily / critically injured patients. With the new assisted living
facility, the patients will be able to stay for the medication period that will be very convenient for
them.
Document Page
2PROJECT MANAGEMENT
Expansion – In addition to providing the patients with the assisted living facility, it will
also act as one step towards expansion of the medical centre. Once the assisted living facility is
built, it is estimated that the number of patients coming to the centre will increase by 60% within
the next 1 year that will help St. Dismas to grow from its current regional background to national
level. Hence, this project is a part of an important strategic direction of the company keeping in
mind the long term growth and solution to the current problems instead short term fixes with no
specific end goal.
Project Scope Statement
Project scope is defined as the overall limit of the project with each details including
schedule, budget, quality and others specified. The project scope covers the entire span of its
objectives, goals and milestones that must be fulfilled within the limitations of the specified
details.
The main scope of this project involves the construction and furnishing of the proposed
assisted living facility. As per the scope, the project will be executed in four phases, each of
which will deal with specific works related to construction and furnishing. The first phase will
deal with the excavation of site after which, the foundation of the facility will be built. After the
development of the foundation, the basement will be set up and the first floor slabs will be set.
After all the setup is done, the project will proceed to the second stage in which the framework
of the facility will be developed using steel frames. Once the frameworks are properly set, the
third phase can be initiated that will include masonry works, enclosure development and the
installation of doors and windows. Finally, in the last phase, furnishing and interior works will be
Document Page
3PROJECT MANAGEMENT
performed and when the furnishing is complete, the rooms will be opened for occupancy in two
different phases.
Work Breakdown Structure
The work breakdown structure of the project is shown in the following.
4 Construction and Furnishing (417 Days)
4.1 Phase 1 - Foundation and Excavation (Basement/1st Floor Slab) (95 days)
4.2 Phase 2 - Structure (Steel/Framing) (113 days)
4.3 Phase 3 - Enclosure (Masonry/Windows/Roof) (134 days)
4.4 Phase 4 - Interiors (Drywall/Ceiling/Flooring/Case Goods) (234 days)
4.5 First 45 (Light Assisted) Units Readiness to Prepare for Occupancy (10 days)
4.6 First 45 Units Ready for Residents (8 wks)
4.7 Remaining 57 Units (Light and Heavy) Readiness to Prepare for Occupancy (10
days)
4.8 Construction Complete (0 days)
4.9 Building Ready for Residents (8 wks)
Project Schedule
The project schedule is shown in the Gantt chart as follows (with the critical path marked
in red).
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4PROJECT MANAGEMENT
Figure 1: Gantt Chart of the Project
(Source: Created by Author)
Furthermore, the network diagram of the project is shown below.
Figure 2: Network Diagram of the Project
(Source: Created by Author)
Document Page
5PROJECT MANAGEMENT
Bibliography
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management.
Project Management Institute.
Heagney, J. (2016). Fundamentals of project management. Amacom.
Kerzner, H. (2017). Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Meredith, J. R., Mantel Jr, S. J., & Shafer, S. M. (2017). Project management: a managerial
approach. John Wiley & Sons.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.
Walker, A. (2015). Project management in construction. John Wiley & Sons.
chevron_up_icon
1 out of 6
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]