This case study examines Globlex's project to develop a training and apprenticeship program (TAHS) for high school students, aiming to enhance farmland productivity and provide job opportunities. The project involves creating an information system to manage the program effectively. The study details the project's measurable organizational value (MOV), scope, resource plan, and scope management plan. It includes a work breakdown structure (WBS) outlining tasks, durations, resource allocation, and budget. The analysis also covers assumptions, constraints, risk identification, mitigation strategies, and quality management plans. The study concludes with closure and evaluation procedures, including an annotated bibliography, closure checklist development, and a project review. This document is shared on Desklib, a platform offering study tools and resources for students.

Running head: PROJECT MANAGEMENT
Case Study- Training and Apprenticeship program for high school Students
Name of the Students
Name of the University
Author’s Note
Case Study- Training and Apprenticeship program for high school Students
Name of the Students
Name of the University
Author’s Note
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1
PROJECT MANAGEMENT
Table of Contents
Introduction................................................................................................................................2
Project description......................................................................................................................2
Part 1: Measurable organizational value....................................................................................3
1.1 Desired area of impact.....................................................................................................3
1.2 Identification of value......................................................................................................3
1.3 Metrics..............................................................................................................................3
1.4 Timeframe........................................................................................................................4
1.5 MOV statement................................................................................................................4
Part 2: Scope of the project........................................................................................................4
2.1 Project scope....................................................................................................................4
2.2 Resource plan...................................................................................................................5
2.3 Scope management plan...................................................................................................6
Part 3: Work breakdown structure.............................................................................................6
3.1Work breakdown structure................................................................................................6
3.2 Duration, allocated resource and project budget..............................................................7
3.3 Assumptions and constraints of the project...................................................................11
3.4 Confidence about estimation of project.........................................................................12
Part 4: Risk analysis and plan..................................................................................................12
4.1 Assumptions...................................................................................................................12
4.2 Risk identification..........................................................................................................13
4.3 Risk analysis...................................................................................................................14
PROJECT MANAGEMENT
Table of Contents
Introduction................................................................................................................................2
Project description......................................................................................................................2
Part 1: Measurable organizational value....................................................................................3
1.1 Desired area of impact.....................................................................................................3
1.2 Identification of value......................................................................................................3
1.3 Metrics..............................................................................................................................3
1.4 Timeframe........................................................................................................................4
1.5 MOV statement................................................................................................................4
Part 2: Scope of the project........................................................................................................4
2.1 Project scope....................................................................................................................4
2.2 Resource plan...................................................................................................................5
2.3 Scope management plan...................................................................................................6
Part 3: Work breakdown structure.............................................................................................6
3.1Work breakdown structure................................................................................................6
3.2 Duration, allocated resource and project budget..............................................................7
3.3 Assumptions and constraints of the project...................................................................11
3.4 Confidence about estimation of project.........................................................................12
Part 4: Risk analysis and plan..................................................................................................12
4.1 Assumptions...................................................................................................................12
4.2 Risk identification..........................................................................................................13
4.3 Risk analysis...................................................................................................................14

2
PROJECT MANAGEMENT
Part 5: Quality management plan.............................................................................................15
5.1 Project quality management...........................................................................................15
5.2 Verification activities.....................................................................................................15
5.3 Validation activities.......................................................................................................15
Part 6: Closure and evaluation.................................................................................................16
6.1 Annotated bibliography..................................................................................................16
6.2 Development of closure checklist..................................................................................17
6.3 Project evaluation...........................................................................................................18
Bibliography.............................................................................................................................19
PROJECT MANAGEMENT
Part 5: Quality management plan.............................................................................................15
5.1 Project quality management...........................................................................................15
5.2 Verification activities.....................................................................................................15
5.3 Validation activities.......................................................................................................15
Part 6: Closure and evaluation.................................................................................................16
6.1 Annotated bibliography..................................................................................................16
6.2 Development of closure checklist..................................................................................17
6.3 Project evaluation...........................................................................................................18
Bibliography.............................................................................................................................19
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3
PROJECT MANAGEMENT
Introduction
The report mainly showcases on Globlex which is one of the organizations that helps
in providing help to the farmers for increasing their farmland productivity by minimizing the
invested time as well as cost. The organization wants to helps the farmers in the future and
therefore they started organizing a program. The program mainly invites students from higher
school and trains them as per farming related expertise so that they can be able to help the
farmers. Moreover, with the help of this program, the chances of job opportunities for the
students rises. For handling the program, the organization mainly aims to develop an
information system. As per the assumptions of the project manager, the work of the project
will be completed within the timeframe of 91 days. The objectives of the project are generally
listed below:
ï‚· Information system development for the organization
ï‚· Management of the program of TAHS for helping the farmers
ï‚· Providing job opportunities to the farmers
Project description
Globlex started a program that will be helpful in enhancing the production of the
farmlands by providing help with the help of trained expertise and giving proper job
opportunities to the students. The program will generally train students on different expertise
of farming that is needed by them in the coming future. For proper management of the
program, a computer-based system is generally required. The organization wants to develop
the system for managing the operations effectively as well as providing fast and efficient
services to the customers.
PROJECT MANAGEMENT
Introduction
The report mainly showcases on Globlex which is one of the organizations that helps
in providing help to the farmers for increasing their farmland productivity by minimizing the
invested time as well as cost. The organization wants to helps the farmers in the future and
therefore they started organizing a program. The program mainly invites students from higher
school and trains them as per farming related expertise so that they can be able to help the
farmers. Moreover, with the help of this program, the chances of job opportunities for the
students rises. For handling the program, the organization mainly aims to develop an
information system. As per the assumptions of the project manager, the work of the project
will be completed within the timeframe of 91 days. The objectives of the project are generally
listed below:
ï‚· Information system development for the organization
ï‚· Management of the program of TAHS for helping the farmers
ï‚· Providing job opportunities to the farmers
Project description
Globlex started a program that will be helpful in enhancing the production of the
farmlands by providing help with the help of trained expertise and giving proper job
opportunities to the students. The program will generally train students on different expertise
of farming that is needed by them in the coming future. For proper management of the
program, a computer-based system is generally required. The organization wants to develop
the system for managing the operations effectively as well as providing fast and efficient
services to the customers.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4
PROJECT MANAGEMENT
Part 1: Measurable organizational value
1.1 Desired area of impact
The area of impact for the project are mainly highlighted in the table below:
Factor Rank
Operational 1st
Customer 2nd
Financial 3rd
Social 4th
Strategy 5th
1.2 Identification of value
The value that is provided by the new information system are generally illustrated
below:
Better: Efficient as well as better services are provided by the new system in
comparison to the system that was used earlier for managing the operation of the
organization.
Faster: The new information system helps the organization to reach to the customers
quite easily and therefore they can fulfill the demands of the customers quite effectively.
1.3 Metrics
Factor Metrics
Operational The operation of the program gets improved
by 13%.
Customer 15% rise in the number of customers are
PROJECT MANAGEMENT
Part 1: Measurable organizational value
1.1 Desired area of impact
The area of impact for the project are mainly highlighted in the table below:
Factor Rank
Operational 1st
Customer 2nd
Financial 3rd
Social 4th
Strategy 5th
1.2 Identification of value
The value that is provided by the new information system are generally illustrated
below:
Better: Efficient as well as better services are provided by the new system in
comparison to the system that was used earlier for managing the operation of the
organization.
Faster: The new information system helps the organization to reach to the customers
quite easily and therefore they can fulfill the demands of the customers quite effectively.
1.3 Metrics
Factor Metrics
Operational The operation of the program gets improved
by 13%.
Customer 15% rise in the number of customers are

5
PROJECT MANAGEMENT
reflected.
Financial 20% rise in the financial budget of the
project is needed.
Social 5% of the customers increases due to use of
social media.
Strategy Use of proper strategy helps in improving
the organization.
1.4 Timeframe
Factor Timeframe
Operational 2 months
Customer 3 months
Financial 3 months
Social 1month
Strategy 2 months
1.5 MOV statement
Measurable organizational value is mainly defined as an important goal of the project
which is generally used in order to illustrate the value that project generally brings to the
customers of the organization. For providing value to the organization, it is quite necessary to
properly align it with the mission and strategy of the organization.
Part 2: Scope of the project
2.1 Project scope
The scope of the project is mainly reflected below:
ï‚· Development of information system for the organization
ï‚· Providing tracking and reporting facility
PROJECT MANAGEMENT
reflected.
Financial 20% rise in the financial budget of the
project is needed.
Social 5% of the customers increases due to use of
social media.
Strategy Use of proper strategy helps in improving
the organization.
1.4 Timeframe
Factor Timeframe
Operational 2 months
Customer 3 months
Financial 3 months
Social 1month
Strategy 2 months
1.5 MOV statement
Measurable organizational value is mainly defined as an important goal of the project
which is generally used in order to illustrate the value that project generally brings to the
customers of the organization. For providing value to the organization, it is quite necessary to
properly align it with the mission and strategy of the organization.
Part 2: Scope of the project
2.1 Project scope
The scope of the project is mainly reflected below:
ï‚· Development of information system for the organization
ï‚· Providing tracking and reporting facility
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6
PROJECT MANAGEMENT
ï‚· To give invitation to the students
ï‚· To provide training facility to the higher school students
ï‚· Providing help to the farmers in increasing productivity
2.2 Resource plan
Human resource: The human resources who are associated with the information
system development are listed below:
Figure 1: Human resource
(Source: Created by Author)
Technology: The needed technologies mainly include:
ï‚· Software: Development tools and designing tools
ï‚· Hardware: CPU, Hard disk, desktop
Facility: Travelling allowances are provided to the project team for working
additional hours.
PROJECT MANAGEMENT
ï‚· To give invitation to the students
ï‚· To provide training facility to the higher school students
ï‚· Providing help to the farmers in increasing productivity
2.2 Resource plan
Human resource: The human resources who are associated with the information
system development are listed below:
Figure 1: Human resource
(Source: Created by Author)
Technology: The needed technologies mainly include:
ï‚· Software: Development tools and designing tools
ï‚· Hardware: CPU, Hard disk, desktop
Facility: Travelling allowances are provided to the project team for working
additional hours.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7
PROJECT MANAGEMENT
Others: Workshop facility should be given to the team so that the project team can
gain knowledge about the project.
2.3 Scope management plan
Scope management is defined as one of the procedures that helps in elaborating the
work tat is generally needed and then it ensures that all the work that are related with the
project will be completed on time. The scope management plan must include proper detailed
procedure about the determination of the scope, its management as well as control. The steps
which are given below helps in managing the project scope quite effectively.
ï‚· The needs of the project should be determined effectively for ensuring that all the
needs of the project are met
ï‚· Understanding about the objectives are important for meeting the project goals
ï‚· Avoiding scope creep in the initial stage of the project is important for avoiding
challenges.
Part 3: Work breakdown structure
3.1Work breakdown structure
Development of
computer based
system.mpp
Project initiation phase
Undertaking survey
for gathering data
Gathering data
about project
Determining the
important data
Stkaeholders
identification
Project plan
Business plan
Charter
development
Milestone
1:Completion of
initiation phase
Project planning phase
Project resource
estimation
Duration estimation
Resource plan
estimation
Recruitment of team
members
Analyzing system
Project schedule
development
Project plan
Milestone
2:Completion of
planning phase
Project designing phase
Selection of proper
design
Development of
prototype
Design outline
Review of design
Milestone
3:Completion of the
design phase of the
project
Project development
phase
Project plan
development
Invitation to the
students
Facility of training
Adding ideas related
to student
Development of
database
Placement of
student
Tracking apprentice
Milestone 4:
Completion of
development phase
Closing phase
Providing manuals
for training purpose
Training fcaility to
the employees
Project review
Milestone
5:Completion of
closure phase
PROJECT MANAGEMENT
Others: Workshop facility should be given to the team so that the project team can
gain knowledge about the project.
2.3 Scope management plan
Scope management is defined as one of the procedures that helps in elaborating the
work tat is generally needed and then it ensures that all the work that are related with the
project will be completed on time. The scope management plan must include proper detailed
procedure about the determination of the scope, its management as well as control. The steps
which are given below helps in managing the project scope quite effectively.
ï‚· The needs of the project should be determined effectively for ensuring that all the
needs of the project are met
ï‚· Understanding about the objectives are important for meeting the project goals
ï‚· Avoiding scope creep in the initial stage of the project is important for avoiding
challenges.
Part 3: Work breakdown structure
3.1Work breakdown structure
Development of
computer based
system.mpp
Project initiation phase
Undertaking survey
for gathering data
Gathering data
about project
Determining the
important data
Stkaeholders
identification
Project plan
Business plan
Charter
development
Milestone
1:Completion of
initiation phase
Project planning phase
Project resource
estimation
Duration estimation
Resource plan
estimation
Recruitment of team
members
Analyzing system
Project schedule
development
Project plan
Milestone
2:Completion of
planning phase
Project designing phase
Selection of proper
design
Development of
prototype
Design outline
Review of design
Milestone
3:Completion of the
design phase of the
project
Project development
phase
Project plan
development
Invitation to the
students
Facility of training
Adding ideas related
to student
Development of
database
Placement of
student
Tracking apprentice
Milestone 4:
Completion of
development phase
Closing phase
Providing manuals
for training purpose
Training fcaility to
the employees
Project review
Milestone
5:Completion of
closure phase

8
PROJECT MANAGEMENT
Figure 1: Work breakdown Structure
(Source: Created by Author)
3.2 Duration, allocated resource and project budget
The table that is given below reflects on the duration, allocated resources as well as on
the needed budget of the project.
WBS Task Name Duration Resource Names Cost
0
Development of
computer-based system
91 days $82,328.00
1
Project initiation
phase
19 days $7,392.00
1.1
Undertaking survey
for gathering data
4 days Project Manager $960.00
1.2
Gathering data about
project
3 days Project Planner $600.00
1.3
Determining the
important data
2 days
Business Analyst, Project
Manager
$960.00
1.4
Stakeholders
identification
3 days
Project Manager, HR
Manager
$1,392.00
1.5 Project plan 2 days IT Manager, Project Planner $752.00
1.6 Business plan 3 days
IT Manager, Business
Analyst, Project Planner
$1,848.00
1.7 Charter development 2 days
Project Manager, Project
Planner
$880.00
PROJECT MANAGEMENT
Figure 1: Work breakdown Structure
(Source: Created by Author)
3.2 Duration, allocated resource and project budget
The table that is given below reflects on the duration, allocated resources as well as on
the needed budget of the project.
WBS Task Name Duration Resource Names Cost
0
Development of
computer-based system
91 days $82,328.00
1
Project initiation
phase
19 days $7,392.00
1.1
Undertaking survey
for gathering data
4 days Project Manager $960.00
1.2
Gathering data about
project
3 days Project Planner $600.00
1.3
Determining the
important data
2 days
Business Analyst, Project
Manager
$960.00
1.4
Stakeholders
identification
3 days
Project Manager, HR
Manager
$1,392.00
1.5 Project plan 2 days IT Manager, Project Planner $752.00
1.6 Business plan 3 days
IT Manager, Business
Analyst, Project Planner
$1,848.00
1.7 Charter development 2 days
Project Manager, Project
Planner
$880.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9
PROJECT MANAGEMENT
1.8
Milestone 1:
Completion of initiation
phase
0 days $0.00
2
Project planning
phase
22 days $8,000.00
2.1
Project resource
estimation
3 days
Financial Officer, HR
Manager, Project Sponsor
$1,872.00
2.2 Duration estimation 4 days Project Manager $960.00
2.3
Resource plan
estimation
3 days HR Manager $672.00
2.4
Recruitment of team
members
3 days HR Manager $672.00
2.5 Analyzing system 4 days
Designer, IT Consultant, IT
Manager
$2,304.00
2.6
Project schedule
development
2 days
IT Consultant, Project
Planner
$800.00
2.7 Project plan 3 days Project Manager $720.00
2.8
Milestone 2:
Completion of planning
phase
0 days
Project Manager, Project
Planner
$0.00
3
Project designing
phase
12 days $41,792.00
3.1
Selection of proper
design
4 days
Business Analyst, Designer,
Developer
$2,464.00
PROJECT MANAGEMENT
1.8
Milestone 1:
Completion of initiation
phase
0 days $0.00
2
Project planning
phase
22 days $8,000.00
2.1
Project resource
estimation
3 days
Financial Officer, HR
Manager, Project Sponsor
$1,872.00
2.2 Duration estimation 4 days Project Manager $960.00
2.3
Resource plan
estimation
3 days HR Manager $672.00
2.4
Recruitment of team
members
3 days HR Manager $672.00
2.5 Analyzing system 4 days
Designer, IT Consultant, IT
Manager
$2,304.00
2.6
Project schedule
development
2 days
IT Consultant, Project
Planner
$800.00
2.7 Project plan 3 days Project Manager $720.00
2.8
Milestone 2:
Completion of planning
phase
0 days
Project Manager, Project
Planner
$0.00
3
Project designing
phase
12 days $41,792.00
3.1
Selection of proper
design
4 days
Business Analyst, Designer,
Developer
$2,464.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10
PROJECT MANAGEMENT
3.2
Development of
prototype
3 days Business Analyst, Designer $1,320.00
3.3 Design outline 3 days
Designer, IT Consultant, IT
Manager, Hardware [1]
$16,728.00
3.4 Review of design 2 days
Designer, IT Consultant,
Project Manager, Software
[1]
$21,280.00
3.5
Milestone 3:
Completion of the
design phase of the
project
0 days Designer $0.00
4
Project development
phase
25 days $20,328.00
4.1
Project plan
development
6 days Developer, System Analyst $2,256.00
4.2
Invitation to the
students
5 days Business Analyst $1,200.00
4.3 Facility of training 4 days Trainer, Other cost [1] $10,736.00
4.4
Adding ideas related
to student
3 days
Project Manager, Project
Planner, Risk Manager
$1,968.00
4.5
Development of
database
4 days
Designer, Developer,
System Analyst, Tester
$2,944.00
4.6 Placement of student 3 days Project Planner $600.00
4.7 Tracking apprentice 3 days Operational Manager $624.00
PROJECT MANAGEMENT
3.2
Development of
prototype
3 days Business Analyst, Designer $1,320.00
3.3 Design outline 3 days
Designer, IT Consultant, IT
Manager, Hardware [1]
$16,728.00
3.4 Review of design 2 days
Designer, IT Consultant,
Project Manager, Software
[1]
$21,280.00
3.5
Milestone 3:
Completion of the
design phase of the
project
0 days Designer $0.00
4
Project development
phase
25 days $20,328.00
4.1
Project plan
development
6 days Developer, System Analyst $2,256.00
4.2
Invitation to the
students
5 days Business Analyst $1,200.00
4.3 Facility of training 4 days Trainer, Other cost [1] $10,736.00
4.4
Adding ideas related
to student
3 days
Project Manager, Project
Planner, Risk Manager
$1,968.00
4.5
Development of
database
4 days
Designer, Developer,
System Analyst, Tester
$2,944.00
4.6 Placement of student 3 days Project Planner $600.00
4.7 Tracking apprentice 3 days Operational Manager $624.00

11
PROJECT MANAGEMENT
4.8
Milestone 4:
Completion of
development phase
0 days Project Manager $0.00
5 Closing phase 13 days $4,816.00
5.1
Providing manuals for
training purpose
3 days
Business Analyst, IT
Consultant, Trainer
$1,872.00
5.2
Training facility to
the employees
6 days Trainer $1,104.00
5.3 Project review 4 days
Project Manager, Project
Planner, Project Sponsor
$1,840.00
5.4
Milestone 5:
Completion of closure
phase
0 days Project Manager $0.00
PROJECT MANAGEMENT
4.8
Milestone 4:
Completion of
development phase
0 days Project Manager $0.00
5 Closing phase 13 days $4,816.00
5.1
Providing manuals for
training purpose
3 days
Business Analyst, IT
Consultant, Trainer
$1,872.00
5.2
Training facility to
the employees
6 days Trainer $1,104.00
5.3 Project review 4 days
Project Manager, Project
Planner, Project Sponsor
$1,840.00
5.4
Milestone 5:
Completion of closure
phase
0 days Project Manager $0.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 23
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.