Critical Evaluation of Wembley Stadium and MSG Project Management
VerifiedAdded on 2021/01/08
|23
|6000
|171
Report
AI Summary
This report critically evaluates the project management approaches used in the construction of Wembley Stadium and Madison Square Garden, two iconic stadium projects. It begins by examining the methodologies employed, contrasting the waterfall approach used at Wembley with the more agile, phased approach at MSG. The report then delves into key project management knowledge areas, including schedule, scope, and cost management, highlighting the impact of decisions made in each area. It analyzes the financial aspects of both projects, noting significant cost overruns at both stadiums, but particularly at Wembley. Furthermore, the report incorporates a PESTLE analysis to assess the external environmental factors influencing each project. Finally, the report offers recommendations based on the successes and failures of each project, providing insights applicable to future stadium construction projects and emphasizing the importance of adaptable methodologies and meticulous planning. The report emphasizes the critical role of project management in achieving project success, even when the final product is successful.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.

=
ProjectPlanning
and
Management
ProjectPlanning
and
Management
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

A Report Comparing, contrasting,
and Critically Evaluating the
Construction of Wembley
Stadium and Madison Square
Garden in Relation to Project
Management Theory
Word Count:
and Critically Evaluating the
Construction of Wembley
Stadium and Madison Square
Garden in Relation to Project
Management Theory
Word Count:

Table of Contents
List of Figures .................................................................................................................. 4
List of Tables ................................................................................................................... 4
1 Introduction ............................................................................................................. 5
2 Discussion ................................................................................................................ 6
2.1 Methodology and Form of the Projects ......................................................................... 6
2.1.1 Wembley Stadium ............................................................................................................................6
2.1.2 Madison Square Garden ..................................................................................................................7
2.1.3 Analysis of Methodologies ...............................................................................................................7
2.2 Project Management Knowledge Areas ........................................................................ 8
2.2.1 Project Schedule Management ........................................................................................................8
2.2.2 Project Scope Management .............................................................................................................9
2.2.3 Project Cost Management ............................................................................................................ 10
2.3 PESTLE Analysis .......................................................................................................... 13
3 Recommendations...................................................................................................16
4 Conclusion...............................................................................................................18
References ......................................................................................................................19
List of Figures .................................................................................................................. 4
List of Tables ................................................................................................................... 4
1 Introduction ............................................................................................................. 5
2 Discussion ................................................................................................................ 6
2.1 Methodology and Form of the Projects ......................................................................... 6
2.1.1 Wembley Stadium ............................................................................................................................6
2.1.2 Madison Square Garden ..................................................................................................................7
2.1.3 Analysis of Methodologies ...............................................................................................................7
2.2 Project Management Knowledge Areas ........................................................................ 8
2.2.1 Project Schedule Management ........................................................................................................8
2.2.2 Project Scope Management .............................................................................................................9
2.2.3 Project Cost Management ............................................................................................................ 10
2.3 PESTLE Analysis .......................................................................................................... 13
3 Recommendations...................................................................................................16
4 Conclusion...............................................................................................................18
References ......................................................................................................................19

List of Figures
Figure 1 Project Phases and Reviews During the Construction of Madison Square Garden .... 7
Figure 2 Relationship Between Project Schedule and Cost Management During the Wembley
Stadium Construction ................................................................................................................ 9
Figure 3 Relationship Between Project Schedule and Cost Management During the MSG
Construction ............................................................................................................................... 9
Figure 4 Making Changes During a Project .............................................................................. 10
Figure 5 Pie Chart Showing the Sources of Funding for Wembley Stadium (House of
Commons, 2004) ...................................................................................................................... 11
Figure 6 System Structure of Wembley Arena ........................................................................ 13
Figure 7 System Structure of Madison Square Garden ........................................................... 13
Figure 8 PESTLE Analysis of the External Environment During the Construction of Wembley
Stadium .................................................................................................................................... 15
Figure 9 Analysis of the External Environment During the Construction of MSG ................... 15
List of Tables
Table 1 Summary of Project Scope of Wembley Stadium and Madison Square Garden .......... 9
Figure 1 Project Phases and Reviews During the Construction of Madison Square Garden .... 7
Figure 2 Relationship Between Project Schedule and Cost Management During the Wembley
Stadium Construction ................................................................................................................ 9
Figure 3 Relationship Between Project Schedule and Cost Management During the MSG
Construction ............................................................................................................................... 9
Figure 4 Making Changes During a Project .............................................................................. 10
Figure 5 Pie Chart Showing the Sources of Funding for Wembley Stadium (House of
Commons, 2004) ...................................................................................................................... 11
Figure 6 System Structure of Wembley Arena ........................................................................ 13
Figure 7 System Structure of Madison Square Garden ........................................................... 13
Figure 8 PESTLE Analysis of the External Environment During the Construction of Wembley
Stadium .................................................................................................................................... 15
Figure 9 Analysis of the External Environment During the Construction of MSG ................... 15
List of Tables
Table 1 Summary of Project Scope of Wembley Stadium and Madison Square Garden .......... 9
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

1 Introduction
This report will scrutinise the project management approach taken during the construction
of Wembley Stadium and Madison Square Garden. Both projects are within the same
reference class, that being stadium construction. The finished infrastructures have both
become iconic features of their corresponding cities and countries, nevertheless, the
success of the structures cannot be mistaken for successful project management. This
declaration will be investigated further by critically analysing the management of each
project alongside project management theories and concepts to create a balanced
argument. As the projects occurred within the same reference class, fair comparisons and
contrasts can be made to create critical conclusions.
The report will be structured by the discussion of the project forms, the methodologies
chosen, and the relevant project management knowledge areas. Within each section, the
attributes and relevant practises will be critically analysed to allow for significant
testimonies. To substantiate the points of analysis, relevant literature will be drawn upon to
support the arguments being presented.
The analysis will be used to create a set of rules and recommendations for future projects to
follow, of which are within the same reference class and have similar scope and budget with
appropriate variance. These recommendations will be based on the success and failures of
each project in relation to respected theories.
This report will scrutinise the project management approach taken during the construction
of Wembley Stadium and Madison Square Garden. Both projects are within the same
reference class, that being stadium construction. The finished infrastructures have both
become iconic features of their corresponding cities and countries, nevertheless, the
success of the structures cannot be mistaken for successful project management. This
declaration will be investigated further by critically analysing the management of each
project alongside project management theories and concepts to create a balanced
argument. As the projects occurred within the same reference class, fair comparisons and
contrasts can be made to create critical conclusions.
The report will be structured by the discussion of the project forms, the methodologies
chosen, and the relevant project management knowledge areas. Within each section, the
attributes and relevant practises will be critically analysed to allow for significant
testimonies. To substantiate the points of analysis, relevant literature will be drawn upon to
support the arguments being presented.
The analysis will be used to create a set of rules and recommendations for future projects to
follow, of which are within the same reference class and have similar scope and budget with
appropriate variance. These recommendations will be based on the success and failures of
each project in relation to respected theories.

2 Discussion
This section will begin the analysis and comparison of the two projects and scrutinise the
management of the Wembley Stadium and Madison Square Garden projects. This paper will
investigate whether project management and project success are related, or whether they
are more independent than anticipated. It has been reported that it is possible to achieve
project success, even when the management has failed (Bjeirmi and Munns, 1996), which
validates the argument chosen to evaluate these projects. Further to a focus on project
management theories will be a analysis on the external environment at the time of each
project, so ensure that the conclusions made are as a result of the project management
approaches and not external influences.
2.1 Methodology and Form of the Projects
Project management methodologies (PMMs) are thought to enhance a project’s chances of
completing on time, to budget and to the requirements of all stakeholders (Charvat, 2003;
Burger and Josler, 2005; Bjermi and Munns, 1996). However, Chin and Spowage (2012)
iterated this to only be true if the PMM is reshaped and scaled to fit the project. The
methodologies of each project will be analysed in reference to this principle to understand
the suitability of the chosen methods.
2.1.1 Wembley Stadium
The objective of the Wembley Stadium construction was outlined clearly during the
conception phase, this being to build an iconic stadium for football, rugby league and
athletics whilst enhancing the nations sporting infrastructure (National Audit Office, 2003).
The clearly defined objective led to clearly defined project phases such as demolition,
foundation, construction, and erection. Each phase was also meticulously planned, the
erection phase followed the plan of; sequencing, working area, assembly, lifting up,
temporary stability, access, alignment and tolerances (Mann, 2006). Due to the
identification of the objective and phases, the life cycle of the project followed planned and
sequential phases which is known as the waterfall methodology (Association for Project
Management, 2012).
This section will begin the analysis and comparison of the two projects and scrutinise the
management of the Wembley Stadium and Madison Square Garden projects. This paper will
investigate whether project management and project success are related, or whether they
are more independent than anticipated. It has been reported that it is possible to achieve
project success, even when the management has failed (Bjeirmi and Munns, 1996), which
validates the argument chosen to evaluate these projects. Further to a focus on project
management theories will be a analysis on the external environment at the time of each
project, so ensure that the conclusions made are as a result of the project management
approaches and not external influences.
2.1 Methodology and Form of the Projects
Project management methodologies (PMMs) are thought to enhance a project’s chances of
completing on time, to budget and to the requirements of all stakeholders (Charvat, 2003;
Burger and Josler, 2005; Bjermi and Munns, 1996). However, Chin and Spowage (2012)
iterated this to only be true if the PMM is reshaped and scaled to fit the project. The
methodologies of each project will be analysed in reference to this principle to understand
the suitability of the chosen methods.
2.1.1 Wembley Stadium
The objective of the Wembley Stadium construction was outlined clearly during the
conception phase, this being to build an iconic stadium for football, rugby league and
athletics whilst enhancing the nations sporting infrastructure (National Audit Office, 2003).
The clearly defined objective led to clearly defined project phases such as demolition,
foundation, construction, and erection. Each phase was also meticulously planned, the
erection phase followed the plan of; sequencing, working area, assembly, lifting up,
temporary stability, access, alignment and tolerances (Mann, 2006). Due to the
identification of the objective and phases, the life cycle of the project followed planned and
sequential phases which is known as the waterfall methodology (Association for Project
Management, 2012).

2.1.2 Madison Square Garden
Similar to Wembley Stadium, the project objective was outlined from the beginning to
provide a state-of-the-art stadium for concerts, sports and entertainment to benefit the
customers and economy of New York City, alongside a further six sub-goals such as
improving customer experience and augmenting revenue streams (The Maddison Square
Garden Company, 2012). The phases were designed around the project goals and occurred
over four consecutive summers, with planning periods in-between. Figure 1 shows the
phases of the project and project reviews in relation to the project lifecycle; the chart has
been adapted for the MSG project from the Association for Project Management (2012).
The clear understanding or project objectives and planning once identifies as a traditional
waterfall methodology. However, it can be said that MSG combined both traditional
waterfall methodologies and agile approaches. Agile approaches allow projects to change
during the project lifecycle (Spundak, 2014). MSG planned the entirety of the project and
there was a clear plan to
what would be completed
during each phase, this is
a very traditional
approach, however the
incorporation of review
periods incorporated an
essence of agile project
management as it allowed
for the accommodation of
uncertainty (Nicholas and Steyn, 2017).
2.1.3 Analysis of Methodologies
By following the waterfall approach, Wembley Stadium faced implications due to the fast-
tracked method and lack of review stages between the phases. This resulted in mistakes
being made and phases having to be repeated. For example, due to the multiple sources of
finance that will later be discussed in more detail, complications arose that created delays
Figure 1 Project Phases and Reviews During the Construction of Madison Square
Garden
Similar to Wembley Stadium, the project objective was outlined from the beginning to
provide a state-of-the-art stadium for concerts, sports and entertainment to benefit the
customers and economy of New York City, alongside a further six sub-goals such as
improving customer experience and augmenting revenue streams (The Maddison Square
Garden Company, 2012). The phases were designed around the project goals and occurred
over four consecutive summers, with planning periods in-between. Figure 1 shows the
phases of the project and project reviews in relation to the project lifecycle; the chart has
been adapted for the MSG project from the Association for Project Management (2012).
The clear understanding or project objectives and planning once identifies as a traditional
waterfall methodology. However, it can be said that MSG combined both traditional
waterfall methodologies and agile approaches. Agile approaches allow projects to change
during the project lifecycle (Spundak, 2014). MSG planned the entirety of the project and
there was a clear plan to
what would be completed
during each phase, this is
a very traditional
approach, however the
incorporation of review
periods incorporated an
essence of agile project
management as it allowed
for the accommodation of
uncertainty (Nicholas and Steyn, 2017).
2.1.3 Analysis of Methodologies
By following the waterfall approach, Wembley Stadium faced implications due to the fast-
tracked method and lack of review stages between the phases. This resulted in mistakes
being made and phases having to be repeated. For example, due to the multiple sources of
finance that will later be discussed in more detail, complications arose that created delays
Figure 1 Project Phases and Reviews During the Construction of Madison Square
Garden
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

to the project life cycle due to no intermittent periods of review allowing for unexpected
occurrences. The reasoning behind MSG having prolonged periods of review was to
accommodate the needs of important stakeholders requiring the facilities within peak-
seasons, hence the construction only occurred within off-peak summer months. Referring
back to Chin and Spowage (2012), MSG clearly scaled their PMM to match the project, and
tailored it specifically to the needs of the company (Špundak, Suki andŠ triga, 2011).
Wembley Stadium followed a traditional approach to mega-projects, even though it has
been recorded that the agile approach is better suited to today’s projects (Špundak, 2014).
Wembley Stadium cannot be judged purely on this theory, due to the completion of the
project occurring before the paper was published, however, it can be used in support of
traditional approaches being less successful in modern projects and to suggest a mix of agile
and traditional approaches to be recommended (Špundak, 2014).
2.2 Project Management Knowledge Areas
Due to constraints to the length of this report, a selection of the project management
knowledge areas (PMBOK, 2017) will be discussed. A study has been conducted by Zwikael
(2009) which aimed to conclude which of the knowledge areas have most influence on
project success, these being time (schedule) management and scope. As this report is
analysing the independency of project management and project success, the results of the
study will be used to ensure that the points being discussed have influence on project
success. However, it must be noted that managers often give lower priority to knowledge
areas that they are unfamiliar with or that are harder to accomplish (2009), so further
knowledge areas will be discussed to add depth to the argument.
2.2.1 Project Schedule Management
Successful project schedule management is a time-consuming process which involves
dividing the project into tasks and assigning a schedule and cost to each (PMBOK, 2017). An
indicator of successful schedule management is the comparison of the predicted project
completion date, and the actual date of completion. Wembley Stadium predicted the
project would be finished in 2002, however this was changed when the project fell behind
schedule. The new completion targets then became 2006, to which they met successfully
occurrences. The reasoning behind MSG having prolonged periods of review was to
accommodate the needs of important stakeholders requiring the facilities within peak-
seasons, hence the construction only occurred within off-peak summer months. Referring
back to Chin and Spowage (2012), MSG clearly scaled their PMM to match the project, and
tailored it specifically to the needs of the company (Špundak, Suki andŠ triga, 2011).
Wembley Stadium followed a traditional approach to mega-projects, even though it has
been recorded that the agile approach is better suited to today’s projects (Špundak, 2014).
Wembley Stadium cannot be judged purely on this theory, due to the completion of the
project occurring before the paper was published, however, it can be used in support of
traditional approaches being less successful in modern projects and to suggest a mix of agile
and traditional approaches to be recommended (Špundak, 2014).
2.2 Project Management Knowledge Areas
Due to constraints to the length of this report, a selection of the project management
knowledge areas (PMBOK, 2017) will be discussed. A study has been conducted by Zwikael
(2009) which aimed to conclude which of the knowledge areas have most influence on
project success, these being time (schedule) management and scope. As this report is
analysing the independency of project management and project success, the results of the
study will be used to ensure that the points being discussed have influence on project
success. However, it must be noted that managers often give lower priority to knowledge
areas that they are unfamiliar with or that are harder to accomplish (2009), so further
knowledge areas will be discussed to add depth to the argument.
2.2.1 Project Schedule Management
Successful project schedule management is a time-consuming process which involves
dividing the project into tasks and assigning a schedule and cost to each (PMBOK, 2017). An
indicator of successful schedule management is the comparison of the predicted project
completion date, and the actual date of completion. Wembley Stadium predicted the
project would be finished in 2002, however this was changed when the project fell behind
schedule. The new completion targets then became 2006, to which they met successfully

(The Guardian, 2008). Maddison Square
Garden estimated the project completion
date to be October 2013 (NY Times, 2010),
the schedule was met precisely by also
completing the project in October 2013 (CBS,
2013). It has been reported that project
schedule management and project cost
management are inseparable (Kerzner, 2001),
figure 2 and 3 show this relationship which
has been adapted from Anbari (2003). By
looking at the diagram, the link is made clear
between schedule and cost and the negative
implications poor schedule management had
during the construction of Wembley Stadium
in relation to cost. By analysing the research
collected on these two projects, it can be
concluded that gate and stage reviews at
intermittent points of the project schedule mitigated any threats to the schedule due to this
being the differentiating factor.
2.2.2 Project Scope Management
Project Scope Management is crucial to the success of any given project as it outlines the
resources needed to ensure all the required work is completed, but only the required work
(PMBOK, 2017). By defining what is and what is not involved in a project, it is less likely for
resources to be wasted. Wembley and MSG both defined their scope promptly, however,
the accuracy was questionable.
Figure 2 Relationship Between Project Schedule and Cost
Management During the Wembley Stadium Construction
Figure 3 Relationship Between Project Schedule and Cost
Management During the MSG Construction
Table 1 Summary of Project Scope of Wembley Stadium and Madison Square Garden
Garden estimated the project completion
date to be October 2013 (NY Times, 2010),
the schedule was met precisely by also
completing the project in October 2013 (CBS,
2013). It has been reported that project
schedule management and project cost
management are inseparable (Kerzner, 2001),
figure 2 and 3 show this relationship which
has been adapted from Anbari (2003). By
looking at the diagram, the link is made clear
between schedule and cost and the negative
implications poor schedule management had
during the construction of Wembley Stadium
in relation to cost. By analysing the research
collected on these two projects, it can be
concluded that gate and stage reviews at
intermittent points of the project schedule mitigated any threats to the schedule due to this
being the differentiating factor.
2.2.2 Project Scope Management
Project Scope Management is crucial to the success of any given project as it outlines the
resources needed to ensure all the required work is completed, but only the required work
(PMBOK, 2017). By defining what is and what is not involved in a project, it is less likely for
resources to be wasted. Wembley and MSG both defined their scope promptly, however,
the accuracy was questionable.
Figure 2 Relationship Between Project Schedule and Cost
Management During the Wembley Stadium Construction
Figure 3 Relationship Between Project Schedule and Cost
Management During the MSG Construction
Table 1 Summary of Project Scope of Wembley Stadium and Madison Square Garden

Initial observations show MSG to have a more detailed project scope in comparison to
Wembley Stadium, which according to PMBOK (2017) is crucial to the success of the project.
The scope of the Wembley Stadium project changed during construction periods, which
later became damaging to its success. To begin with, the involvement of athletics facilities
within the scope were removed. As the financial stakeholders invested in the project under
pretences that athletic facilities would be including, the funding was pulled from the project
which created significant delays. Further, the hospitality suites were also removed from the
scope, which resulted in designers and engineers having to redesign the plans. There is
correlation between
the effectiveness and
cost of change with the
period the change is
implemented. Figure 4,
adapted from Smith
(2003), shows this
correlation and the
importance of
adhering to the initial
scope. If Wembley
Stadium had created a
more realistic scope,
or made the changes during the initiation stage, the implications would have been fewer.
2.2.3 Project Cost Management
Although the study into the influence of project management knowledge areas on project
success noted project cost management as less influential (Zwikael, 2009), Wembley arena
inadvertently became one of the most expensive stadiums of its kind ever built (Reed,
2018). The management and control of costs is indispensable to all projects, impartial to the
industry they operate (Smith, 2007). Specifically, within the construction industry it is not
Figure 4 Making Changes During a Project
Wembley Stadium, which according to PMBOK (2017) is crucial to the success of the project.
The scope of the Wembley Stadium project changed during construction periods, which
later became damaging to its success. To begin with, the involvement of athletics facilities
within the scope were removed. As the financial stakeholders invested in the project under
pretences that athletic facilities would be including, the funding was pulled from the project
which created significant delays. Further, the hospitality suites were also removed from the
scope, which resulted in designers and engineers having to redesign the plans. There is
correlation between
the effectiveness and
cost of change with the
period the change is
implemented. Figure 4,
adapted from Smith
(2003), shows this
correlation and the
importance of
adhering to the initial
scope. If Wembley
Stadium had created a
more realistic scope,
or made the changes during the initiation stage, the implications would have been fewer.
2.2.3 Project Cost Management
Although the study into the influence of project management knowledge areas on project
success noted project cost management as less influential (Zwikael, 2009), Wembley arena
inadvertently became one of the most expensive stadiums of its kind ever built (Reed,
2018). The management and control of costs is indispensable to all projects, impartial to the
industry they operate (Smith, 2007). Specifically, within the construction industry it is not
Figure 4 Making Changes During a Project
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

uncommon for costs to overrun by 50 - 100% (Flyvbjerg et al., 2002). The construction of
Wembley Stadium had predicted costs of £320 million (House of Commons, 2004), but their
actual costs exceeded this figure and totalled £757 million (2004). In comparison, the
construction of Madison Square Garden was estimated to cost $850 million (NY Times,
2010), but grew to $1 billion on completion. By comparing with the global study on
construction over-spending (Flyvbjerg et al., 2002), Wembley Stadium exceeded the 50 -
100% range as their project costs increased by 136.6%. Dissimilar, the Madison Square
Garden project spent more than anticipated, but the costs only grew by 17.6% which is far
less than the commonalities of over-spending within the construction industry and can be
explained partially by a lack of forecasting to the net present value. However, to give fair
critique on how each project managed their project costs, it must be understood further the
reasonings behind the higher project costs and the importance each project placed on
project cost management.
Wembley Arena sourced their funding from
multiple public and private sector investors.
Figure 5 shows the specific percentages that
were to fund the initial £320 million. From the
chart, it is apparent that only 2% of the cash
was sourced internally from the Wembley
National Stadium Limited company, this
increased the number of influential
stakeholders and risk. As previously discussed,
when the project scope was shifted, original
investors withdrew their funding as it was no longer fulfilling their requirements. This
created delays, and it is important to note that time is costly within projects. As the funding
was a key resource to the project, the delays impacted the critical path as the critical path
could not start until the funding issues had been resolved. This instance also links greatly
with project stakeholder management. Reverse to this, Madison Square Garden funded the
project entirely from internal sources from the Madison Square Garden Company. This
made the cost management of investments much simpler than obtaining funds from
internal, external, public and private sources.
Figure 5 Pie Chart Showing the Sources of Funding
for Wembley Stadium (House of Commons, 2004)
Wembley Stadium had predicted costs of £320 million (House of Commons, 2004), but their
actual costs exceeded this figure and totalled £757 million (2004). In comparison, the
construction of Madison Square Garden was estimated to cost $850 million (NY Times,
2010), but grew to $1 billion on completion. By comparing with the global study on
construction over-spending (Flyvbjerg et al., 2002), Wembley Stadium exceeded the 50 -
100% range as their project costs increased by 136.6%. Dissimilar, the Madison Square
Garden project spent more than anticipated, but the costs only grew by 17.6% which is far
less than the commonalities of over-spending within the construction industry and can be
explained partially by a lack of forecasting to the net present value. However, to give fair
critique on how each project managed their project costs, it must be understood further the
reasonings behind the higher project costs and the importance each project placed on
project cost management.
Wembley Arena sourced their funding from
multiple public and private sector investors.
Figure 5 shows the specific percentages that
were to fund the initial £320 million. From the
chart, it is apparent that only 2% of the cash
was sourced internally from the Wembley
National Stadium Limited company, this
increased the number of influential
stakeholders and risk. As previously discussed,
when the project scope was shifted, original
investors withdrew their funding as it was no longer fulfilling their requirements. This
created delays, and it is important to note that time is costly within projects. As the funding
was a key resource to the project, the delays impacted the critical path as the critical path
could not start until the funding issues had been resolved. This instance also links greatly
with project stakeholder management. Reverse to this, Madison Square Garden funded the
project entirely from internal sources from the Madison Square Garden Company. This
made the cost management of investments much simpler than obtaining funds from
internal, external, public and private sources.
Figure 5 Pie Chart Showing the Sources of Funding
for Wembley Stadium (House of Commons, 2004)

According to Smith (2007), professionals whom are qualified to manage project costs are;
project managers, quantity surveyors and cost engineers. Despite both projects having
these professional resources, there were differences to their management. Multiplex
construction company won the bid to build Wembley Stadium at their promise to build the
structure for £326 million, it was contractually agreed that Multiplex would receive a fixed-
amount for their services (Gribben, 2007). Because of this agreement, Multiplex would
profit more if costs were kept low, but be at a loss if cost crept higher. However, this
initiative was not a successful ploy. Multiplex managed the sub-contractors, the
relationships between themselves and the steel sub-contractor, Cleveland Bridge, became
volatile. This unstable supplier relationship was impactful to the project as they had to
source a new sub-contractor. Due to the disputes, a value can be placed in the form of a £20
million settlement awarded to Cleveland Bridge (Morris, 2004). This shows that relationship
management has influence on the success or project cost management. Karim et al. (2013)
conducted a study into the factors that cause construction to overrun, to which a significant
factor was found to be the relationships between management and labour. In this example,
Multiplex were the managing body, and Cleveland Bridge the labour. As the relationship
was managed poorly and cost implications occur, it is appropriate to say this project
managed project costs poorly. Combining this analysis with the system structure of each
project (shown in figure 6 and 7) may suggest that keeping a projects system structure
simple, and hence retaining control, may reduce the risk of relationships breakdown.
project managers, quantity surveyors and cost engineers. Despite both projects having
these professional resources, there were differences to their management. Multiplex
construction company won the bid to build Wembley Stadium at their promise to build the
structure for £326 million, it was contractually agreed that Multiplex would receive a fixed-
amount for their services (Gribben, 2007). Because of this agreement, Multiplex would
profit more if costs were kept low, but be at a loss if cost crept higher. However, this
initiative was not a successful ploy. Multiplex managed the sub-contractors, the
relationships between themselves and the steel sub-contractor, Cleveland Bridge, became
volatile. This unstable supplier relationship was impactful to the project as they had to
source a new sub-contractor. Due to the disputes, a value can be placed in the form of a £20
million settlement awarded to Cleveland Bridge (Morris, 2004). This shows that relationship
management has influence on the success or project cost management. Karim et al. (2013)
conducted a study into the factors that cause construction to overrun, to which a significant
factor was found to be the relationships between management and labour. In this example,
Multiplex were the managing body, and Cleveland Bridge the labour. As the relationship
was managed poorly and cost implications occur, it is appropriate to say this project
managed project costs poorly. Combining this analysis with the system structure of each
project (shown in figure 6 and 7) may suggest that keeping a projects system structure
simple, and hence retaining control, may reduce the risk of relationships breakdown.

Figure 6 System Structure of Wembley Arena
Figure 7 System Structure of Madison Square Garden
2.3 PESTLE Analysis
A noticeable difference was the economic conditions. In 2002, the world economy was
slowing and heading towards a recession (United Nations, 2002), whereas the economy in
2013 was improving and gaining momentum in economic activity (United Nations, 2013).
The differences could suggest why Wembley Stadium had poor project cost management as
Figure 7 System Structure of Madison Square Garden
2.3 PESTLE Analysis
A noticeable difference was the economic conditions. In 2002, the world economy was
slowing and heading towards a recession (United Nations, 2002), whereas the economy in
2013 was improving and gaining momentum in economic activity (United Nations, 2013).
The differences could suggest why Wembley Stadium had poor project cost management as
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

their investors may have receded in response to fears of a recession. The delays that
resulted from investor sources impacted schedule and cost.
Another impactful condition was the technological advances of each period. It is undeniable
that technology advanced greatly between both projects’ dates. It has been said that
technological advancement greatly influences construction performance and productivity
(Goodrum, 2009), this statement suggests that the environment at the time of MSGs
erection aided the productivity which would have a positive impact on their project
schedule management.
Thus far, the external environment seemed more beneficial to the construction of MSG.
However, the legal factors relevant to stadium construction could be seen as
disadvantageous to MSG. Health and safety regulations and policies had been expanded on
greatly since the construction of Wembley Stadium, in 2013 twelve health and safety
legislations were amended and protocols were made more stringent (Health and Safety
Executive, 2013). Intensified health and safety may have impacted the schedule
management of MSG due to the tiring processes involved. Contrary, it may have improved
their stakeholder management by improving the safety of workers. On reverse, the reduced
Health and Safety guidelines in 2002 may have been the cause of detriment during the
Wembley Stadium construction. During construction, a worker lost their life as the result of
a platform falling (BBC, 2014). It cannot be said surely, but it is acceptable to hypothesise
that stricter health and safety guidelines may have prevented this situation. Resultingly,
work had to be ceased which creating further delays to the schedule. The full PESTLE
analysis can be seen in figures 8 and 9.
resulted from investor sources impacted schedule and cost.
Another impactful condition was the technological advances of each period. It is undeniable
that technology advanced greatly between both projects’ dates. It has been said that
technological advancement greatly influences construction performance and productivity
(Goodrum, 2009), this statement suggests that the environment at the time of MSGs
erection aided the productivity which would have a positive impact on their project
schedule management.
Thus far, the external environment seemed more beneficial to the construction of MSG.
However, the legal factors relevant to stadium construction could be seen as
disadvantageous to MSG. Health and safety regulations and policies had been expanded on
greatly since the construction of Wembley Stadium, in 2013 twelve health and safety
legislations were amended and protocols were made more stringent (Health and Safety
Executive, 2013). Intensified health and safety may have impacted the schedule
management of MSG due to the tiring processes involved. Contrary, it may have improved
their stakeholder management by improving the safety of workers. On reverse, the reduced
Health and Safety guidelines in 2002 may have been the cause of detriment during the
Wembley Stadium construction. During construction, a worker lost their life as the result of
a platform falling (BBC, 2014). It cannot be said surely, but it is acceptable to hypothesise
that stricter health and safety guidelines may have prevented this situation. Resultingly,
work had to be ceased which creating further delays to the schedule. The full PESTLE
analysis can be seen in figures 8 and 9.

Figure 8 PESTLE Analysis of the External Environment During the Construction of Wembley Stadium
Figure 9 Analysis of the External Environment During the Construction of MSG
Figure 9 Analysis of the External Environment During the Construction of MSG

3 Recommendations
By analysing the comparison of the two projects, clear differences can be observed which
highlight best practice for success, and practices that have fewer desirable outcomes. These
observations have been used to develop the set of recommendations for future projects
within the stadium construction reference class.
1) Integrate substantial gate and stage reviews into the schedule.
• In the case of Wembley Stadium, poor cost, resource, and scope management had a
great impact on project schedule management. It is acceptable to presume that
MSG faced challenges during construction due to the rise in costs, however, few of
the challenges were impactful to the schedule. The distinct factor that can be used
to explain the scheduling success is the use of prolonged gate and stage reviews.
Although prolonged review periods can be seen as periods of unproductiveness, the
short spouts of no activity outweighed the cost Wembley Stadium faced by having
no time to account for changes. This recommendation is therefore aimed at projects
with high risk of external influences effecting the ability to complete the critical
chain.
2) Ensure project methodologies match the characteristics of the project.
• By contrasting Wembley Stadium and MSG, it cannot be stated that a traditional
approach will lead to failure as it did in the case of Wembley Arena. However, the
differentiating factor between the two was that MSG aligned the chosen
methodology with the needs of the project. Tailoring the methodology to the
company needs will increase the chances of success (Špundak, Suki andŠ triga,
2011).
• A sub-recommendation to this would be to opt for a mixture of traditional and agile
approaches. MSG was constructed seven years subsequent to Wembley Arena,
which shows the advancement of modern mega construction and the development
of appropriate methodologies. Therefore, as traditional methods are noted as being
less successful in modern times, a mix of the two is heavily recommended (Špundak,
2014).
By analysing the comparison of the two projects, clear differences can be observed which
highlight best practice for success, and practices that have fewer desirable outcomes. These
observations have been used to develop the set of recommendations for future projects
within the stadium construction reference class.
1) Integrate substantial gate and stage reviews into the schedule.
• In the case of Wembley Stadium, poor cost, resource, and scope management had a
great impact on project schedule management. It is acceptable to presume that
MSG faced challenges during construction due to the rise in costs, however, few of
the challenges were impactful to the schedule. The distinct factor that can be used
to explain the scheduling success is the use of prolonged gate and stage reviews.
Although prolonged review periods can be seen as periods of unproductiveness, the
short spouts of no activity outweighed the cost Wembley Stadium faced by having
no time to account for changes. This recommendation is therefore aimed at projects
with high risk of external influences effecting the ability to complete the critical
chain.
2) Ensure project methodologies match the characteristics of the project.
• By contrasting Wembley Stadium and MSG, it cannot be stated that a traditional
approach will lead to failure as it did in the case of Wembley Arena. However, the
differentiating factor between the two was that MSG aligned the chosen
methodology with the needs of the project. Tailoring the methodology to the
company needs will increase the chances of success (Špundak, Suki andŠ triga,
2011).
• A sub-recommendation to this would be to opt for a mixture of traditional and agile
approaches. MSG was constructed seven years subsequent to Wembley Arena,
which shows the advancement of modern mega construction and the development
of appropriate methodologies. Therefore, as traditional methods are noted as being
less successful in modern times, a mix of the two is heavily recommended (Špundak,
2014).
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

3) Spend more time outlining a detailed scope during project conception to prevent
complications later on.
• Scope management is a time-consuming process, and project areas that are harder
to accomplish are often given less priority by project managers (Zwikael, 2009).
However, this paper concludes project scope management to be one of most
important areas to focus on. The compassion of Wembley Stadium and MSG
highlights the implications that poor scope management can have on project
success. Specifically, if project scope is not accurate and susceptible to change, the
cost of making changes further along the project life cycle are much higher and less
effective (Smith, 2003).
4) Limit the number of financial sources, particularly the number of external investors.
• Although this recommendation is specific to the lessons learnt from Wembley
Stadium, the advice should be noted by all projects of similar nature. The use of
multiple sources of funding, particularly external sources, increased the risk of
implications and so it is advised to opt for guaranteed sources of cash. However, full
accountability cannot be placed on financial management as if project risk
management was successfully in place, the risk associated with funding would have
been known and mitigated. Therefore, the exception to this recommendation would
be to projects who consider their sources of funding risky, but have sufficient risk
management in place.
complications later on.
• Scope management is a time-consuming process, and project areas that are harder
to accomplish are often given less priority by project managers (Zwikael, 2009).
However, this paper concludes project scope management to be one of most
important areas to focus on. The compassion of Wembley Stadium and MSG
highlights the implications that poor scope management can have on project
success. Specifically, if project scope is not accurate and susceptible to change, the
cost of making changes further along the project life cycle are much higher and less
effective (Smith, 2003).
4) Limit the number of financial sources, particularly the number of external investors.
• Although this recommendation is specific to the lessons learnt from Wembley
Stadium, the advice should be noted by all projects of similar nature. The use of
multiple sources of funding, particularly external sources, increased the risk of
implications and so it is advised to opt for guaranteed sources of cash. However, full
accountability cannot be placed on financial management as if project risk
management was successfully in place, the risk associated with funding would have
been known and mitigated. Therefore, the exception to this recommendation would
be to projects who consider their sources of funding risky, but have sufficient risk
management in place.

4 Conclusion
This report has analysed the project management of both Wembley Stadium and Madison
Square Garden, conclusively answering the initial aim of discovering the dependency of
successful project management and successful projects. Even though the report was written
impartially, the conclusions show the project management of Wembley Stadium to be
unsuccessful in comparison. To summarise, the project failed to manage their cost,
schedule, and scope and seemed somewhat in a loss of control to the discrepancies from
the original plan. Despite this, both constructions have been deemed equally successful
based on the buildings that are standing today. This shows that project success and
successful project management are not dependant of each other as Wembley Stadium was
successful despite unsuccessful project management. This statement cannot be taken
indefinitely as the reverse has not been analysed. It cannot be said whether successful
project management can result in an unsuccessful project. The final point of consideration is
the disadvantageous external conditions that Wembley Stadium faced during construction
in comparison to the more favourable conditions that MSG uncounted. Overall, projects of
similar nature must use the analysis conducted within this report to improve their
management. Although it was concluded that successful projects are not dependant on
successful project management, the benefits of ensuring successful project management
have been exemplified by the consequences faced by Wembley Stadium.
This report has analysed the project management of both Wembley Stadium and Madison
Square Garden, conclusively answering the initial aim of discovering the dependency of
successful project management and successful projects. Even though the report was written
impartially, the conclusions show the project management of Wembley Stadium to be
unsuccessful in comparison. To summarise, the project failed to manage their cost,
schedule, and scope and seemed somewhat in a loss of control to the discrepancies from
the original plan. Despite this, both constructions have been deemed equally successful
based on the buildings that are standing today. This shows that project success and
successful project management are not dependant of each other as Wembley Stadium was
successful despite unsuccessful project management. This statement cannot be taken
indefinitely as the reverse has not been analysed. It cannot be said whether successful
project management can result in an unsuccessful project. The final point of consideration is
the disadvantageous external conditions that Wembley Stadium faced during construction
in comparison to the more favourable conditions that MSG uncounted. Overall, projects of
similar nature must use the analysis conducted within this report to improve their
management. Although it was concluded that successful projects are not dependant on
successful project management, the benefits of ensuring successful project management
have been exemplified by the consequences faced by Wembley Stadium.

References
Anbari, F. T. (2003) Earned Value Project Management Method and Executions. Project
Management Journal, 34(4) 12-23. Project Management Institute.
Association for Project Management (2012) APM Body of Knowledge, 6th Edition.
Buckinghamshire, England: APM.
Bjeirmi, B. F. and Munns, A. K. (1996) The Role of Project Management in Achieving Project
Success. International Journal of Project Management, 14(2) 81-87. Available from:
https://www.sciencedirect.com/science/article/pii/0263786395000577 [Accessed on 10th
November 2019]
Burger, J. and Josler, C. (2005) Project management methodology in HRM. Cupa HR Journal,
56(2) 25-30.
CBS (2013) Transformation of Madison Square Garden Complete. New York: CBS New York.
Available from: https://newyork.cbslocal.com/2013/10/24/transformation-of-madison-
square-garden-complete/ [Accessed on 21st October 2019]
Charvat, J. (2003) Project management methodologies: selecting, implementing and
supporting methodologies and processes for projects. John Wiley & Sons.
Chin, C. M. M. and Spowage, A. C. (2012) Project Management Methodologies: A
Comparative Analysis. Journal for the Advancement of Performance Information and Value,
4(1) 106-118.
CNBC (2013) The Billion-dollar Makeover of Madison Square Garden. CNBC. Available from:
https://www.cnbc.com/2013/10/25/the-billion-dollar-makeover-of-madison-square-
garden.html [Accessed on 21st October 2019]
Anbari, F. T. (2003) Earned Value Project Management Method and Executions. Project
Management Journal, 34(4) 12-23. Project Management Institute.
Association for Project Management (2012) APM Body of Knowledge, 6th Edition.
Buckinghamshire, England: APM.
Bjeirmi, B. F. and Munns, A. K. (1996) The Role of Project Management in Achieving Project
Success. International Journal of Project Management, 14(2) 81-87. Available from:
https://www.sciencedirect.com/science/article/pii/0263786395000577 [Accessed on 10th
November 2019]
Burger, J. and Josler, C. (2005) Project management methodology in HRM. Cupa HR Journal,
56(2) 25-30.
CBS (2013) Transformation of Madison Square Garden Complete. New York: CBS New York.
Available from: https://newyork.cbslocal.com/2013/10/24/transformation-of-madison-
square-garden-complete/ [Accessed on 21st October 2019]
Charvat, J. (2003) Project management methodologies: selecting, implementing and
supporting methodologies and processes for projects. John Wiley & Sons.
Chin, C. M. M. and Spowage, A. C. (2012) Project Management Methodologies: A
Comparative Analysis. Journal for the Advancement of Performance Information and Value,
4(1) 106-118.
CNBC (2013) The Billion-dollar Makeover of Madison Square Garden. CNBC. Available from:
https://www.cnbc.com/2013/10/25/the-billion-dollar-makeover-of-madison-square-
garden.html [Accessed on 21st October 2019]
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Flyvbjerg, B., Holm, M. S. and Buhl, S. (2002) Underestimating Costs in Public Works
Projects: Error or lie? Journal of the American Planning Association, 68(3) 279–295.
Goodrum, P. M., Zhai, D. and Yasin, M. F. (2009) Relationship between changes in material
technology and construction productivity. Journal of construction engineering and
management, 135(4) 278-287.
Gribben, R. (2007) Multiplex Sold after Wembley Fiasco. The Telegraph. Available from:
https://www.telegraph.co.uk/finance/markets/2810431/Multiplex-sold-after-Wembley-
fiasco.html [Accessed on 11th November 2019]
Health and Safety Executive (2013) The History of HSE. Health and Safety Executive.
Available from: https://www.hse.gov.uk/aboutus/timeline/index.htm [Accessed on 7th
January 2020]
House of Commons (2014) The English national stadium project at Wembley. London: House
of Commons. Available from:
https://publications.parliament.uk/pa/cm200304/cmselect/cmpubacc/254/254.pdf
[Accessed on 21st October 2019]
House of Commons (2014) The English National Stadium Project at Wembley. London:
House of Commons. Available from:
https://publications.parliament.uk/pa/cm200304/cmselect/cmpubacc/254/254.pdf
[Accessed on 21st October 2019]
Morris, S. (2004) Wembley Building Work Row Causes Slippage. The Guardian. Available
from: https://www.theguardian.com/uk/2004/aug/28/wembleystadium.stevenmorris
[Accessed on 11th November 2019]
Karim, A, T, A., Memon, A. H. and Rahman, I. A. (2013) Relationship Between Factors of
Construction Resources Affecting Project Cost. Modern Applied Science, 7(1) 67-75.
Projects: Error or lie? Journal of the American Planning Association, 68(3) 279–295.
Goodrum, P. M., Zhai, D. and Yasin, M. F. (2009) Relationship between changes in material
technology and construction productivity. Journal of construction engineering and
management, 135(4) 278-287.
Gribben, R. (2007) Multiplex Sold after Wembley Fiasco. The Telegraph. Available from:
https://www.telegraph.co.uk/finance/markets/2810431/Multiplex-sold-after-Wembley-
fiasco.html [Accessed on 11th November 2019]
Health and Safety Executive (2013) The History of HSE. Health and Safety Executive.
Available from: https://www.hse.gov.uk/aboutus/timeline/index.htm [Accessed on 7th
January 2020]
House of Commons (2014) The English national stadium project at Wembley. London: House
of Commons. Available from:
https://publications.parliament.uk/pa/cm200304/cmselect/cmpubacc/254/254.pdf
[Accessed on 21st October 2019]
House of Commons (2014) The English National Stadium Project at Wembley. London:
House of Commons. Available from:
https://publications.parliament.uk/pa/cm200304/cmselect/cmpubacc/254/254.pdf
[Accessed on 21st October 2019]
Morris, S. (2004) Wembley Building Work Row Causes Slippage. The Guardian. Available
from: https://www.theguardian.com/uk/2004/aug/28/wembleystadium.stevenmorris
[Accessed on 11th November 2019]
Karim, A, T, A., Memon, A. H. and Rahman, I. A. (2013) Relationship Between Factors of
Construction Resources Affecting Project Cost. Modern Applied Science, 7(1) 67-75.

Kerzner, H. (2001) Project Management: A Systems Approach to Planning, Scheduling, and
Controlling, 7th edition. New York, NY: John Wiley & Sons.
Mann, A. P. (2006) Design and Fabrication of the new Wembley Stadium Roof. Available
from: http://www.mae.uk.com/Wembley%20Stadium%20with%20Pictures.PDF [Accessed
on 10th November 2019]
NAO (2003) The English national stadium project at Wembley. London: National Audit
Office. Available from: https://www.nao.org.uk/wp-content/uploads/2003/06/0203699.pdf
[Accessed on 21st October 2019]
Nicholas, J., and Steyn, H. (2017) Project Management for Engineering, 5th Edition. Oxon:
Routledge.
NY Times (2010) Madison Square Garden to Slow for Construction. New York: NY Times.
Available from: https://www.nytimes.com/2010/05/06/sports/06garden.html [Accessed on
21st October 2019]
NY Times (2010) Madison Square Garden to Slow for Construction. New York: NY Times.
Available from: https://www.nytimes.com/2010/05/06/sports/06garden.html [Accessed on
21st October 2019]
PMBOK (2017) A guide to the Project Management Body of Knowledge, 6th Edition.
Pennsylvania, United States: Project Management Institute, Inc.
Reed, A. (2018) U.S. Billionaire Launches Bid to Buy Wembley Stadium, the Home of English
Soccer. CNBC. Available from: https://www.cnbc.com/2018/04/26/u-s-billionaire-wants-to-
buy-wembley-soccer-stadium-in-england.html [Accessed on 11th November 2019]
Smith, N. J. (2003) Appraisal, Risk and Uncertainty. London: Thomas Telford.
Controlling, 7th edition. New York, NY: John Wiley & Sons.
Mann, A. P. (2006) Design and Fabrication of the new Wembley Stadium Roof. Available
from: http://www.mae.uk.com/Wembley%20Stadium%20with%20Pictures.PDF [Accessed
on 10th November 2019]
NAO (2003) The English national stadium project at Wembley. London: National Audit
Office. Available from: https://www.nao.org.uk/wp-content/uploads/2003/06/0203699.pdf
[Accessed on 21st October 2019]
Nicholas, J., and Steyn, H. (2017) Project Management for Engineering, 5th Edition. Oxon:
Routledge.
NY Times (2010) Madison Square Garden to Slow for Construction. New York: NY Times.
Available from: https://www.nytimes.com/2010/05/06/sports/06garden.html [Accessed on
21st October 2019]
NY Times (2010) Madison Square Garden to Slow for Construction. New York: NY Times.
Available from: https://www.nytimes.com/2010/05/06/sports/06garden.html [Accessed on
21st October 2019]
PMBOK (2017) A guide to the Project Management Body of Knowledge, 6th Edition.
Pennsylvania, United States: Project Management Institute, Inc.
Reed, A. (2018) U.S. Billionaire Launches Bid to Buy Wembley Stadium, the Home of English
Soccer. CNBC. Available from: https://www.cnbc.com/2018/04/26/u-s-billionaire-wants-to-
buy-wembley-soccer-stadium-in-england.html [Accessed on 11th November 2019]
Smith, N. J. (2003) Appraisal, Risk and Uncertainty. London: Thomas Telford.

Smith, P. (2014) Project Cost Management – Global Issues and Challenges. Procedia – Social
and Behavioural Sciences, 119 485-494.Š
pundak, M. (2014) Mixed Agile/Traditional Project Management Methodology – Reality or
Illusion? Procedia – Social and Behavioural Sciences, 11(9) 939-948. Available from:
https://www.researchgate.net/publication/270846766_Mixed_AgileTraditional_Project_Ma
nagement_Methodology_-_Reality_or_Illusion [Accessed on 10th November 2019] Š
pundak, M., Suki, H. and Š triga, K. (2011) How to improve Project Management in Croatia?
Dublin, Ireland: Proceeding of the PMI Global Congress EME.
The Guardian (2008) £253m legal battle over Wembley delays. The Guardian. Available
from: https://www.theguardian.com/business/2008/mar/16/construction.wembleystadium
[Accessed on 21st October 2019]
The Madison Square Garden Company (2012) Annual Report. New York: United States
Securities and Exchange Commission.
Turner Construction (2019) Madison Square Garden Transformation. Turner Construction
Company. Available from:
https://www.turnerconstruction.com/experience/project/11E6/madison-square-garden-
transformation [Accessed on 21st October 2019]
United Nations (2002) World Economic Situation and Prospects 2002. Department of
Economic and Social Affairs. Available from:
https://www.un.org/en/development/desa/policy/wesp/wesp_archive/2002wesp.pdf
[Accessed on 7th January 2020]
United Nations (2013) World Economic Situation and Prospects 2013. Department of
Economic and Social Affairs. Available from:
https://www.un.org/en/development/desa/policy/wesp/wesp2013/wesp13update.pdf
[Accessed on 7th January 2020]
and Behavioural Sciences, 119 485-494.Š
pundak, M. (2014) Mixed Agile/Traditional Project Management Methodology – Reality or
Illusion? Procedia – Social and Behavioural Sciences, 11(9) 939-948. Available from:
https://www.researchgate.net/publication/270846766_Mixed_AgileTraditional_Project_Ma
nagement_Methodology_-_Reality_or_Illusion [Accessed on 10th November 2019] Š
pundak, M., Suki, H. and Š triga, K. (2011) How to improve Project Management in Croatia?
Dublin, Ireland: Proceeding of the PMI Global Congress EME.
The Guardian (2008) £253m legal battle over Wembley delays. The Guardian. Available
from: https://www.theguardian.com/business/2008/mar/16/construction.wembleystadium
[Accessed on 21st October 2019]
The Madison Square Garden Company (2012) Annual Report. New York: United States
Securities and Exchange Commission.
Turner Construction (2019) Madison Square Garden Transformation. Turner Construction
Company. Available from:
https://www.turnerconstruction.com/experience/project/11E6/madison-square-garden-
transformation [Accessed on 21st October 2019]
United Nations (2002) World Economic Situation and Prospects 2002. Department of
Economic and Social Affairs. Available from:
https://www.un.org/en/development/desa/policy/wesp/wesp_archive/2002wesp.pdf
[Accessed on 7th January 2020]
United Nations (2013) World Economic Situation and Prospects 2013. Department of
Economic and Social Affairs. Available from:
https://www.un.org/en/development/desa/policy/wesp/wesp2013/wesp13update.pdf
[Accessed on 7th January 2020]
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

Zwikael, O. (2009) The Relative Importance of the PMBOK Guide’s Nine Knowledge Areas
During Project Planning. Project Management Journal, 40(4) 94-103.
During Project Planning. Project Management Journal, 40(4) 94-103.
1 out of 23
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.