University Project: Project Network for New Laptop Computer (ACC8105)

Verified

Added on  2022/11/15

|11
|438
|2
Project
AI Summary
This project analyzes the network for designing, manufacturing, and marketing a new laptop computer. The assignment begins with the creation of an Activity on Node (AON) diagram, identifying the critical path and calculating the project's scheduled duration. It then addresses project network management, including strategies to expedite the project launch, considering time and cost trade-offs. The analysis includes project crashing estimations, identifying specific activities for reduction and calculating the impact on the overall project duration. The student utilizes provided data on activity durations, costs, and crash estimations to make informed decisions about project acceleration. The report also includes considerations of management decisions and potential incentive structures. The project also identifies the critical activities for the project, and evaluates the lowest improvement factor for each activity. The final analysis includes the crashing of specific activities to reduce the overall project duration.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Project Network for a New Laptop
Computer
Name of the Student
Name of the University
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
The AON Diagram
(Figure 1: The AON Diagram for the Project)
(Source: Created by author)
Document Page
Identification of Critical Path
The red highlighted sections from Figure 1 are
identified as critical path activities within the project
Scheduled duration of the project is calculated as:
= Sum of the total tasks in the critical path
= (90 + 25 + 14+ 20 + 45) days
= 194 days
Document Page
Information on Project Network
Management would need to complete the project 5
days prior than the scheduled period
Crashing of the critical activities needs to be done
within 5 days
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Information on Project Network
The critical activities are being listed in the following table:
Critical
Path
Length
Of
Critical
Path
Earliest
Start
Earliest
Finish
Latest
Start
Latest
Finish
A 90 0 90 0 90
F 25 90 115 90 115
G 14 115 129 115 129
D 20 129 149 129 149
J 45 149 194 149 194
Document Page
Consideration of Management
Decisions
Management needs the product launch 5 days prior
than the scheduled time
An incentive structure has been planned accordingly
Primary reason is competition with their global
competitor
Document Page
The Project Crash Estimations
Activit
y
Normal
Time
(days)
Normal
Cost
Crash
time
(days)
Crash
Cost
Improvemen
t Factor
A 90 $2,250 85 $2,520 54
B 15 $180 13 $210 15
C 5 $90 4 $120 30
D 20 $300 19 $330 30
E 21 $231 17 $315 21
F 25 $250 21 $382 33
G 14 $70 12 $112 21
H 28 $390 25 $450 20
I 30 $510 28 $570 30
J 45 $1,350 41 $1,530 45
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
The Project Crash Estimations
The highlighted red activities are defined as critical
activities for the project
The critical activities for the project are: A, F, G, D and J
Lowest improvement factor is for activity G
Next lowest improvement factor is for activity D
Further lowest improvement factor is for activity F
Document Page
The Project Crash Estimations
Total reduction in the project duration is 7 days
Duration of critical path after crashing is: 90 + 21 +
12 + 19 + 45 = 187 days
Specific activities that needs to be crashed are: G, D
and F
Capabilities of investment should help in deciding
over the early release of product
Document Page
Bibliography
Ahipasaoglu, S.D., Natarajan, K. and Shi, D., 2019. Distributionally
robust project crashing with partial or no correlation
information. Networks, 74(1), pp.79-106.
Arora, P.K. and Bhatia, R., 2018. Agent-based regression test case
generation using class diagram, use cases and activity
diagram. Procedia Computer Science, 125, pp.747-753.
Ballesteros-Perez, P., Elamrousy, K.M. and González-Cruz, M.C.,
2019. Non-linear time-cost trade-off models of activity crashing:
Application to construction scheduling and project compression with
fast-tracking. Automation in Construction, 97, pp.229-240.
Mahmoudi, A. and Feylizadeh, M.R., 2018. A grey mathematical
model for crashing of projects by considering time, cost, quality, risk
and law of diminishing returns. Grey Systems: Theory and
Application.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Thank You
chevron_up_icon
1 out of 11
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]