This assignment focuses on the analysis of a project network diagram and schedule. The solution includes the creation of a project network diagram, identification of the critical path, and calculation of early start, early finish, late start, and late finish times for each activity. The assignment also determines the total project duration, which is 41 weeks, and assesses whether the project meets the specified time constraints. The critical path is identified as A→B→C→I→J→K→N. The analysis also includes a discussion of the project's flexibility and potential for delays, and the implications of these factors on the overall project timeline.
Document Page
ASSESSMENT
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Task 2
1. Project network diagram
Float
ES Activity LS
EF Duration LF
Float = Delay in project activity
ES = Early start
EF = Early finish
LS = Late start
LF = Late finish
In the above diagram, red line indicates the critical path of the project, this series of activities
showing through red line is the minimum duration taken by the project to finish. There was no
successor activity available after M task, thus a dummy activity with duration 4 weeks have been
taken to balance the activities. The minimum taken by the project is 44 weeks. Thus, this
particular project is not subject to any penalty or additional incentive, as doesn’t exceed 47
weeks nor it meet 40 weeks duration.
2. Schedule of the project
Time required to complete the project if no delays occur
41 Weeks
Start and finish of individuals to meet the project completion (EF and LF)
Activity LS LF
A 0 2
B 2 6
C 6 16
Document Page
D 16 22
E 16 20
F 20 25
G 22 29
H 29 38
I 18 25
J 25 33
K 34 38
L 33 38
M 38 40
N 38 44
Start and finish with no delays (ES and EF)
Activity ES EF
A 0 2
B 2 6
C 6 16
D 16 22
E 16 20
F 20 25
G 22 29
H 29 38
I 16 23
J 25 33
K 33 37
L 33 38
M 38 40
N 38 44
Critical activities with no delays
A → B → C → I → J → K → N
= 2 + 4 + 10 + 7 + 8 + 4 + 6 = 41 Weeks
chevron_up_icon
1 out of 3
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]