SBM1201 Project Management Plan: Buckley St Crossing Removal
VerifiedAdded on  2023/06/15
|29
|3384
|314
Project
AI Summary
This document presents a comprehensive project management plan for the Essendon & Buckley Street level crossing removal project. It details scope management with a work breakdown structure and change control, schedule and time management including milestones and dependencies, cost/budget management, quality management, human resource management outlining roles and responsibilities, communication management strategies, risk management analysis, and procurement management considerations. The plan covers the entire project lifecycle from initiation to closure, aiming to improve safety and reduce traffic congestion by lowering Buckley Street under the rail line. This student assignment is available on Desklib, where students can find similar solved assignments and study resources.

Running head: PROJECT MANAGEMMENT PLAN
Topic- Essendon & Buckley Street level crossing removal.
Name of the Student
Name of the University
Author’s Note
Topic- Essendon & Buckley Street level crossing removal.
Name of the Student
Name of the University
Author’s Note
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1
PROJECT MANAGEMMENT PLAN
Table of Contents
Project management plan.................................................................................................................3
1. Introduction..............................................................................................................................3
2. Scope management..................................................................................................................3
2.1 Work breakdown Structure................................................................................................3
2.2 Change control management.............................................................................................4
3. Schedule and time management..............................................................................................5
3.1 Milestones..........................................................................................................................5
3.2 Project Schedule................................................................................................................5
3.3 Dependencies.....................................................................................................................8
4. Cost/Budget management......................................................................................................11
5. Quality management..............................................................................................................16
6. Human resource management................................................................................................17
7. Communication management................................................................................................19
8. Risk management...................................................................................................................22
9. Procurement management.....................................................................................................27
10. Quality baseline...................................................................................................................27
Bibliography..................................................................................................................................29
PROJECT MANAGEMMENT PLAN
Table of Contents
Project management plan.................................................................................................................3
1. Introduction..............................................................................................................................3
2. Scope management..................................................................................................................3
2.1 Work breakdown Structure................................................................................................3
2.2 Change control management.............................................................................................4
3. Schedule and time management..............................................................................................5
3.1 Milestones..........................................................................................................................5
3.2 Project Schedule................................................................................................................5
3.3 Dependencies.....................................................................................................................8
4. Cost/Budget management......................................................................................................11
5. Quality management..............................................................................................................16
6. Human resource management................................................................................................17
7. Communication management................................................................................................19
8. Risk management...................................................................................................................22
9. Procurement management.....................................................................................................27
10. Quality baseline...................................................................................................................27
Bibliography..................................................................................................................................29

2
PROJECT MANAGEMMENT PLAN
Project management plan
1. Introduction
The paper mainly focuses on the level crossing removal of Buckley Street, Essondon that
is considered as one of the key arterials in inner North West of Melbourne that mainly connects
Keilor as well as Avondale heights in the west. The boom gates of the Buckley Street are down
for about 78 minutes in the morning and as result, the traveller faces congestion as well as
disruption while passing. In order to resolve this problem, the Victorian government took an
important step and as per it, they wants to remove the level crossing at Buckley Street so that the
passengers can easily travel and which further can be able to reduce traffic congestion as well as
assists in improving safety.
2. Scope management
2.1 Work breakdown Structure
Figure 1: WBS
PROJECT MANAGEMMENT PLAN
Project management plan
1. Introduction
The paper mainly focuses on the level crossing removal of Buckley Street, Essondon that
is considered as one of the key arterials in inner North West of Melbourne that mainly connects
Keilor as well as Avondale heights in the west. The boom gates of the Buckley Street are down
for about 78 minutes in the morning and as result, the traveller faces congestion as well as
disruption while passing. In order to resolve this problem, the Victorian government took an
important step and as per it, they wants to remove the level crossing at Buckley Street so that the
passengers can easily travel and which further can be able to reduce traffic congestion as well as
assists in improving safety.
2. Scope management
2.1 Work breakdown Structure
Figure 1: WBS
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3
PROJECT MANAGEMMENT PLAN
(Source: Created by Author)
2.2 Change control management
Change
identification
Purpose Change
analysis
Change request
approval
Change
tracking
Utilizing
technically
advanced
equipments
It is identified
that use of
technically
advanced
equipments
helps in
removing the
level crossing at
Buckley Street
quite easily.
The
construction
engineers
understand the
change viability.
The change
viability in the
project is mainly
approved by the
project
managers
Proper master
logbook is
maintained in
order to ensure
that the
construction
engineers use
proper
equipment.
Utilizing
appropriate
quality of
materials
It is very much
necessary to use
proper quality of
materials in
order to
construct the
pathways.
The quality
analyst
understands the
viability of
proper quality of
materials in the
project.
The request for
maintain proper
quality materials
is mainly
approved by the
project manager
Appropriate
logbook is
generally
maintained in
order to make
sure those proper
quality materials
is used in the
project.
PROJECT MANAGEMMENT PLAN
(Source: Created by Author)
2.2 Change control management
Change
identification
Purpose Change
analysis
Change request
approval
Change
tracking
Utilizing
technically
advanced
equipments
It is identified
that use of
technically
advanced
equipments
helps in
removing the
level crossing at
Buckley Street
quite easily.
The
construction
engineers
understand the
change viability.
The change
viability in the
project is mainly
approved by the
project
managers
Proper master
logbook is
maintained in
order to ensure
that the
construction
engineers use
proper
equipment.
Utilizing
appropriate
quality of
materials
It is very much
necessary to use
proper quality of
materials in
order to
construct the
pathways.
The quality
analyst
understands the
viability of
proper quality of
materials in the
project.
The request for
maintain proper
quality materials
is mainly
approved by the
project manager
Appropriate
logbook is
generally
maintained in
order to make
sure those proper
quality materials
is used in the
project.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4
PROJECT MANAGEMMENT PLAN
3. Schedule and time management
3.1 Milestones
Task Name Start
Milestone 1: Completion of project initiation phase Mon 23-05-16
Milestone 2: Completion of planning phase Thu 15-12-16
Milestone 3 : Completion of procurement phase Wed 06-12-17
Milestone 4: Completion of Construction phase Thu 08-08-19
Milestone 4: Completion of project closure phase Wed 20-11-19
3.2 Project Schedule
Task Name Duration Start Finish % Complete
Essendon & Buckley
Street level crossing
removal
985 days Thu 11-02-16 Wed 20-11-19 57%
Initiation phase of the
project
73 days Thu 11-02-16 Mon 23-05-16 100%
Identifying objectives of
the project
15 days Thu 11-02-16 Wed 02-03-16 100%
Undertaking feasibility
study
20 days Thu 03-03-16 Wed 30-03-16 100%
Establishing project 16 days Thu 31-03-16 Thu 21-04-16 100%
PROJECT MANAGEMMENT PLAN
3. Schedule and time management
3.1 Milestones
Task Name Start
Milestone 1: Completion of project initiation phase Mon 23-05-16
Milestone 2: Completion of planning phase Thu 15-12-16
Milestone 3 : Completion of procurement phase Wed 06-12-17
Milestone 4: Completion of Construction phase Thu 08-08-19
Milestone 4: Completion of project closure phase Wed 20-11-19
3.2 Project Schedule
Task Name Duration Start Finish % Complete
Essendon & Buckley
Street level crossing
removal
985 days Thu 11-02-16 Wed 20-11-19 57%
Initiation phase of the
project
73 days Thu 11-02-16 Mon 23-05-16 100%
Identifying objectives of
the project
15 days Thu 11-02-16 Wed 02-03-16 100%
Undertaking feasibility
study
20 days Thu 03-03-16 Wed 30-03-16 100%
Establishing project 16 days Thu 31-03-16 Thu 21-04-16 100%

5
PROJECT MANAGEMMENT PLAN
charter
Appointing team
members of the project
22 days Fri 22-04-16 Mon 23-05-16 100%
Milestone 1:
Completion of project
initiation phase
0 days Mon 23-05-16 Mon 23-05-16 100%
Planning phase of the
project
148 days Tue 24-05-16 Thu 15-12-16 100%
Site investigations 22 days Tue 24-05-16 Wed 22-06-16 100%
Solution announced 20 days Thu 23-06-16 Wed 20-07-16 100%
Community information
sessions
25 days Thu 21-07-16 Wed 24-08-16 100%
Trader consultation 26 days Thu 25-08-16 Thu 29-09-16 100%
Assessment of design
options
26 days Fri 30-09-16 Fri 04-11-16 100%
Lowering Buckley
street under rail line
29 days Mon 07-11-16 Thu 15-12-16 100%
Milestone 2:
Completion of planning
phase
0 days Thu 15-12-16 Thu 15-12-16 100%
Procurement phase 254 days Fri 16-12-16 Wed 06-12-17 100%
PROJECT MANAGEMMENT PLAN
charter
Appointing team
members of the project
22 days Fri 22-04-16 Mon 23-05-16 100%
Milestone 1:
Completion of project
initiation phase
0 days Mon 23-05-16 Mon 23-05-16 100%
Planning phase of the
project
148 days Tue 24-05-16 Thu 15-12-16 100%
Site investigations 22 days Tue 24-05-16 Wed 22-06-16 100%
Solution announced 20 days Thu 23-06-16 Wed 20-07-16 100%
Community information
sessions
25 days Thu 21-07-16 Wed 24-08-16 100%
Trader consultation 26 days Thu 25-08-16 Thu 29-09-16 100%
Assessment of design
options
26 days Fri 30-09-16 Fri 04-11-16 100%
Lowering Buckley
street under rail line
29 days Mon 07-11-16 Thu 15-12-16 100%
Milestone 2:
Completion of planning
phase
0 days Thu 15-12-16 Thu 15-12-16 100%
Procurement phase 254 days Fri 16-12-16 Wed 06-12-17 100%
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6
PROJECT MANAGEMMENT PLAN
Community input on
design elements
32 days Fri 16-12-16 Mon 30-01-17 100%
North west alliance
project partner announced
39 days Tue 31-01-17 Fri 24-03-17 100%
Construction partner
announced
44 days Mon 27-03-17 Thu 25-05-17 100%
Community consultation 47 days Fri 26-05-17 Mon 31-07-17 100%
Refinement of design
including community inputs
50 days Tue 01-08-17 Mon 09-10-17 100%
Finalizing design 42 days Tue 10-10-17 Wed 06-12-17 100%
Milestone 3 :
Completion of procurement
phase
0 days Wed 06-12-17 Wed 06-12-17 100%
Construction phase 436 days Thu 07-12-17 Thu 08-08-19 19%
On-going community
consultation
32 days Thu 07-12-17 Fri 19-01-18 100%
Construction
commences
34 days Mon 22-01-18 Thu 08-03-18 100%
Preparatory work
commenced
43 days Fri 09-03-18 Tue 08-05-18 42%
Finalized design
released to the community
45 days Wed 09-05-18 Tue 10-07-18 0%
Contract awarded for 52 days Wed 11-07-18 Thu 20-09-18 0%
PROJECT MANAGEMMENT PLAN
Community input on
design elements
32 days Fri 16-12-16 Mon 30-01-17 100%
North west alliance
project partner announced
39 days Tue 31-01-17 Fri 24-03-17 100%
Construction partner
announced
44 days Mon 27-03-17 Thu 25-05-17 100%
Community consultation 47 days Fri 26-05-17 Mon 31-07-17 100%
Refinement of design
including community inputs
50 days Tue 01-08-17 Mon 09-10-17 100%
Finalizing design 42 days Tue 10-10-17 Wed 06-12-17 100%
Milestone 3 :
Completion of procurement
phase
0 days Wed 06-12-17 Wed 06-12-17 100%
Construction phase 436 days Thu 07-12-17 Thu 08-08-19 19%
On-going community
consultation
32 days Thu 07-12-17 Fri 19-01-18 100%
Construction
commences
34 days Mon 22-01-18 Thu 08-03-18 100%
Preparatory work
commenced
43 days Fri 09-03-18 Tue 08-05-18 42%
Finalized design
released to the community
45 days Wed 09-05-18 Tue 10-07-18 0%
Contract awarded for 52 days Wed 11-07-18 Thu 20-09-18 0%
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7
PROJECT MANAGEMMENT PLAN
Buckley street level
crossing removal project
Early works commence 57 days Fri 21-09-18 Mon 10-12-18 0%
Major works commence 48 days Tue 11-12-18 Thu 14-02-19 0%
Boom gates removed 60 days Fri 15-02-19 Thu 09-05-19 0%
Finalizing landscapes 65 days Fri 10-05-19 Thu 08-08-19 0%
Milestone 4:
Completion of Construction
phase
0 days Thu 08-08-19 Thu 08-08-19 0%
Closure phase 74 days Fri 09-08-19 Wed 20-11-19 0%
Post-project review 20 days Fri 09-08-19 Thu 05-09-19 0%
Stakeholder-sign off 30 days Fri 06-09-19 Thu 17-10-19 0%
Documentation 24 days Fri 18-10-19 Wed 20-11-19 0%
Milestone 4:
Completion of project
closure phase
0 days Wed 20-11-19 Wed 20-11-19 0%
3.3 Dependencies
Task Name Duration Predecessors
Essendon & Buckley Street level
crossing removal
985 days
Initiation phase of the project 73 days
PROJECT MANAGEMMENT PLAN
Buckley street level
crossing removal project
Early works commence 57 days Fri 21-09-18 Mon 10-12-18 0%
Major works commence 48 days Tue 11-12-18 Thu 14-02-19 0%
Boom gates removed 60 days Fri 15-02-19 Thu 09-05-19 0%
Finalizing landscapes 65 days Fri 10-05-19 Thu 08-08-19 0%
Milestone 4:
Completion of Construction
phase
0 days Thu 08-08-19 Thu 08-08-19 0%
Closure phase 74 days Fri 09-08-19 Wed 20-11-19 0%
Post-project review 20 days Fri 09-08-19 Thu 05-09-19 0%
Stakeholder-sign off 30 days Fri 06-09-19 Thu 17-10-19 0%
Documentation 24 days Fri 18-10-19 Wed 20-11-19 0%
Milestone 4:
Completion of project
closure phase
0 days Wed 20-11-19 Wed 20-11-19 0%
3.3 Dependencies
Task Name Duration Predecessors
Essendon & Buckley Street level
crossing removal
985 days
Initiation phase of the project 73 days

8
PROJECT MANAGEMMENT PLAN
Identifying objectives of the project 15 days
Undertaking feasibility study 20 days 2
Establishing project charter 16 days 3
Appointing team members of the
project
22 days 4
Milestone 1: Completion of project
initiation phase
0 days 5
Planning phase of the project 148 days
Site investigations 22 days 6
Solution announced 20 days 8
Community information sessions 25 days 9
Trader consultation 26 days 10
Assessment of design options 26 days 11
Lowering Buckley street under rail
line
29 days 12
Milestone 2: Completion of planning
phase
0 days 13
Procurement phase 254 days
Community input on design elements 32 days 14
North west alliance project partner
announced
39 days 16
Construction partner announced 44 days 17
PROJECT MANAGEMMENT PLAN
Identifying objectives of the project 15 days
Undertaking feasibility study 20 days 2
Establishing project charter 16 days 3
Appointing team members of the
project
22 days 4
Milestone 1: Completion of project
initiation phase
0 days 5
Planning phase of the project 148 days
Site investigations 22 days 6
Solution announced 20 days 8
Community information sessions 25 days 9
Trader consultation 26 days 10
Assessment of design options 26 days 11
Lowering Buckley street under rail
line
29 days 12
Milestone 2: Completion of planning
phase
0 days 13
Procurement phase 254 days
Community input on design elements 32 days 14
North west alliance project partner
announced
39 days 16
Construction partner announced 44 days 17
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9
PROJECT MANAGEMMENT PLAN
Community consultation 47 days 18
Refinement of design including
community inputs
50 days 19
Finalizing design 42 days 20
Milestone 3 : Completion of
procurement phase
0 days 21
Construction phase 436 days
On-going community consultation 32 days 22
Construction commences 34 days 24
Preparatory work commenced 43 days 25
Finalized design released to the
community
45 days 26
Contract awarded for Buckley street
level crossing removal project
52 days 27
Early works commence 57 days 28
Major works commence 48 days 29
Boom gates removed 60 days 30
Finalizing landscapes 65 days 31
Milestone 4: Completion of
Construction phase
0 days 32
Closure phase 74 days
Post-project review 20 days 33
PROJECT MANAGEMMENT PLAN
Community consultation 47 days 18
Refinement of design including
community inputs
50 days 19
Finalizing design 42 days 20
Milestone 3 : Completion of
procurement phase
0 days 21
Construction phase 436 days
On-going community consultation 32 days 22
Construction commences 34 days 24
Preparatory work commenced 43 days 25
Finalized design released to the
community
45 days 26
Contract awarded for Buckley street
level crossing removal project
52 days 27
Early works commence 57 days 28
Major works commence 48 days 29
Boom gates removed 60 days 30
Finalizing landscapes 65 days 31
Milestone 4: Completion of
Construction phase
0 days 32
Closure phase 74 days
Post-project review 20 days 33
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10
PROJECT MANAGEMMENT PLAN
Stakeholder-sign off 30 days 35
Documentation 24 days 36
Milestone 4: Completion of project
closure phase
0 days 37
4. Cost/Budget management
Task Name Duration Resource Names Cost
Essendon & Buckley Street
level crossing removal
985 days $114,664,480.00
Initiation phase of the
project
73 days $254,480.00
Identifying objectives of the
project
15 days Project manager $34,800.00
Undertaking feasibility
study
20 days Project manager $46,400.00
Establishing project charter 16 days
Project manager, Project
planner
$72,960.00
Appointing team members
of the project
22 days
Project manager, Project
planner
$100,320.00
Milestone 1: Completion of
project initiation phase
0 days $0.00
PROJECT MANAGEMMENT PLAN
Stakeholder-sign off 30 days 35
Documentation 24 days 36
Milestone 4: Completion of project
closure phase
0 days 37
4. Cost/Budget management
Task Name Duration Resource Names Cost
Essendon & Buckley Street
level crossing removal
985 days $114,664,480.00
Initiation phase of the
project
73 days $254,480.00
Identifying objectives of the
project
15 days Project manager $34,800.00
Undertaking feasibility
study
20 days Project manager $46,400.00
Establishing project charter 16 days
Project manager, Project
planner
$72,960.00
Appointing team members
of the project
22 days
Project manager, Project
planner
$100,320.00
Milestone 1: Completion of
project initiation phase
0 days $0.00

11
PROJECT MANAGEMMENT PLAN
Planning phase of the
project
148 days $7,765,120.00
Site investigations 22 days
Supervisor, Construction
manager
$89,760.00
Solution announced 20 days
Construction technician,
Contractor, Equipment
cost[1]
$7,081,600.00
Community information
sessions
25 days
Construction manager,
Contractor
$102,000.00
Trader consultation 26 days
Construction manager,
Contractor
$106,080.00
Assessment of design
options
26 days
Construction manager,
Contractor, Sub-
contractor
$156,000.00
Lowering Buckley street
under rail line
29 days
Architect, Construction
manager, Construction
technician, Sub-
contractor
$229,680.00
Milestone 2: Completion of
planning phase
0 days $0.00
Procurement phase 254 days $34,070,960.00
Community input on design
elements
32 days Cost for removing level
crossing[1], Supervisor,
$16,194,560.00
PROJECT MANAGEMMENT PLAN
Planning phase of the
project
148 days $7,765,120.00
Site investigations 22 days
Supervisor, Construction
manager
$89,760.00
Solution announced 20 days
Construction technician,
Contractor, Equipment
cost[1]
$7,081,600.00
Community information
sessions
25 days
Construction manager,
Contractor
$102,000.00
Trader consultation 26 days
Construction manager,
Contractor
$106,080.00
Assessment of design
options
26 days
Construction manager,
Contractor, Sub-
contractor
$156,000.00
Lowering Buckley street
under rail line
29 days
Architect, Construction
manager, Construction
technician, Sub-
contractor
$229,680.00
Milestone 2: Completion of
planning phase
0 days $0.00
Procurement phase 254 days $34,070,960.00
Community input on design
elements
32 days Cost for removing level
crossing[1], Supervisor,
$16,194,560.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 29
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.