Comprehensive Project Plan: Relaxation Area at ECU Joondalup (MAN2172)
VerifiedAdded on 2023/03/17
|23
|3215
|62
Project
AI Summary
This project management assignment details the planning and execution of a relaxation area at ECU Joondalup, adjacent to the Pines Cinema. The plan encompasses requirement gathering strategies (brainstorming, surveys, and interviews), a three-point estimation technique to determine a budget of approximately $321,880, and a detailed work breakdown structure (WBS). It includes risk analysis with mitigation strategies, a Gantt chart for scheduling the 107-day project, and a schedule outlining project activities. The document also addresses critical path analysis, critical chain management, cost baselines with contingencies, and cash flow forecasting, providing a comprehensive overview of the project's lifecycle. The project's success hinges on the effective management of budget, schedule, and resources, as highlighted by the risk analysis section.

Running head: PROJECT MANAGEMENT
Project management: Setting up a relaxation area at ECU Joondalup adjacent
Name of the Student
Name of the University
Author’s Note
Project management: Setting up a relaxation area at ECU Joondalup adjacent
Name of the Student
Name of the University
Author’s Note
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1
PROJECT MANAGEMENT
Table of Contents
1. Project overview.................................................................................................................2
2. Requirement gathering........................................................................................................2
3. Estimation...........................................................................................................................3
4. Work breakdown structure..................................................................................................7
5. Risk analysis.......................................................................................................................8
6. Gantt chart and schedule...................................................................................................11
6.1 Gantt chart......................................................................................................................11
6.2 Schedule.........................................................................................................................13
7. Critical path.......................................................................................................................16
8. Critical chain.....................................................................................................................17
9. Cost baseline including contingencies..............................................................................18
9.1 Baseline commensurate with WBS and Gantt chart..................................................18
9.2 S-curve demonstration...............................................................................................19
10. Cash flow forecast.........................................................................................................19
Bibliography.............................................................................................................................21
PROJECT MANAGEMENT
Table of Contents
1. Project overview.................................................................................................................2
2. Requirement gathering........................................................................................................2
3. Estimation...........................................................................................................................3
4. Work breakdown structure..................................................................................................7
5. Risk analysis.......................................................................................................................8
6. Gantt chart and schedule...................................................................................................11
6.1 Gantt chart......................................................................................................................11
6.2 Schedule.........................................................................................................................13
7. Critical path.......................................................................................................................16
8. Critical chain.....................................................................................................................17
9. Cost baseline including contingencies..............................................................................18
9.1 Baseline commensurate with WBS and Gantt chart..................................................18
9.2 S-curve demonstration...............................................................................................19
10. Cash flow forecast.........................................................................................................19
Bibliography.............................................................................................................................21

2
PROJECT MANAGEMENT
1. Project overview
The paper mainly reflects on set up of a relaxation area at ECU Joondalup that is
adjacent to the Pine Cinemas. It is found that the project that is mainly undertaken generally
needs permanent seating area, shades, paving, bins, lightening as well as a sand volleyball
court. It is found that the relaxation area set up will be completed successfully within the time
period of 107 days by utilizing budget of around 321,880.
2. Requirement gathering
The requirements that are associated with the project are generally gathered with the
help of the methods that are mainly illustrated below:
Brainstorming: Brainstorming is one of the requirement gathering method that is
mainly utilized in order to gather ideas from different group of people so that the relaxation
area that is set up in the Joondalup area can meet the needs and requirements of the clients
(Hornstein, 2015). In addition to this, the brainstorming method is mainly utilized in order to
determine ways that are very much important for successfully achieving success from the
project.
Survey: Survey is also undertaken in order to gathering ideas as well as views of the
customers about the setup of a relaxation area in Joondalup in order to design the area in such
a way that it would provide proper service to the customers by meeting the requirements of
the customers.
Interview: Interviewing the users as well as stakeholders are considered as one of the
important as well as critical step in order to gather requirements for the project set up
(Badewi, 2016). It is identified that without proper information as well as knowledge about
the project goals and objectives, it is quite difficult to satisfy the customers by fulfilling their
needs and requirements.
PROJECT MANAGEMENT
1. Project overview
The paper mainly reflects on set up of a relaxation area at ECU Joondalup that is
adjacent to the Pine Cinemas. It is found that the project that is mainly undertaken generally
needs permanent seating area, shades, paving, bins, lightening as well as a sand volleyball
court. It is found that the relaxation area set up will be completed successfully within the time
period of 107 days by utilizing budget of around 321,880.
2. Requirement gathering
The requirements that are associated with the project are generally gathered with the
help of the methods that are mainly illustrated below:
Brainstorming: Brainstorming is one of the requirement gathering method that is
mainly utilized in order to gather ideas from different group of people so that the relaxation
area that is set up in the Joondalup area can meet the needs and requirements of the clients
(Hornstein, 2015). In addition to this, the brainstorming method is mainly utilized in order to
determine ways that are very much important for successfully achieving success from the
project.
Survey: Survey is also undertaken in order to gathering ideas as well as views of the
customers about the setup of a relaxation area in Joondalup in order to design the area in such
a way that it would provide proper service to the customers by meeting the requirements of
the customers.
Interview: Interviewing the users as well as stakeholders are considered as one of the
important as well as critical step in order to gather requirements for the project set up
(Badewi, 2016). It is identified that without proper information as well as knowledge about
the project goals and objectives, it is quite difficult to satisfy the customers by fulfilling their
needs and requirements.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3
PROJECT MANAGEMENT
3. Estimation
It is found that the budget of the project “setting up relaxation area at ECU Joondalup”
will be estimated with the help of three point estimation technique. The three point estimation
is one of the tool that is utilized for cost estimation for increasing the accuracy of the cost
estimation (Kerzner & Kerzner, 2017). The three point estimation generally includes three
types of estimation that include optimistic estimate, pessimistic estimation as well as most
likely estimation. As per the three point estimation technique, it is found that budget of
around $319959 is generally required for setting up the relaxation area near the Pines
Cinema.
Activities Optimistic
estimate
Pessimistic
estimation
Most likely
estimation
Three point
estimation
(Mean)
Setting up
relaxation area at
ECU Joondalup
$316048 $321950 $3,21,880
$319959
Requirement
gathering
940 1000 960
967
Analysis of
project
1200 1,300.00 1280
1260
Resource
estimation
900 960 960
940
Estimating
project schedule
1150 1250 1200
1200
Budget
estimation
1200 1300 1280
1260
Manpower 900 1000 960 953
PROJECT MANAGEMENT
3. Estimation
It is found that the budget of the project “setting up relaxation area at ECU Joondalup”
will be estimated with the help of three point estimation technique. The three point estimation
is one of the tool that is utilized for cost estimation for increasing the accuracy of the cost
estimation (Kerzner & Kerzner, 2017). The three point estimation generally includes three
types of estimation that include optimistic estimate, pessimistic estimation as well as most
likely estimation. As per the three point estimation technique, it is found that budget of
around $319959 is generally required for setting up the relaxation area near the Pines
Cinema.
Activities Optimistic
estimate
Pessimistic
estimation
Most likely
estimation
Three point
estimation
(Mean)
Setting up
relaxation area at
ECU Joondalup
$316048 $321950 $3,21,880
$319959
Requirement
gathering
940 1000 960
967
Analysis of
project
1200 1,300.00 1280
1260
Resource
estimation
900 960 960
940
Estimating
project schedule
1150 1250 1200
1200
Budget
estimation
1200 1300 1280
1260
Manpower 900 1000 960 953
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4
PROJECT MANAGEMENT
estimation
Resource
estimation
1200 1390 1280
1290
Fund
procurement for the
project
1200 1300 1280
1260
Stakeholders
appointment
1780 1820 1800
1800
Meetings
arrangement
1570 1650 1600
1607
Financial
management
1900 2000 1920
1940
Appointment of
workers
1900 1940 1920
1920
Preparation of
blueprint
1400 1500 1440
1447
Procurement of
land area
1790 1890 1800
1827
Release of legal
notice
1900 2000 1920
1940
Budget
allocation
2800 2880 2880
2853
Resource
procurement
1780 1890 1800
1823
Division of
time
1400 1500 1440
1447
Duty allocation 1578 1650 1600 1609
PROJECT MANAGEMENT
estimation
Resource
estimation
1200 1390 1280
1290
Fund
procurement for the
project
1200 1300 1280
1260
Stakeholders
appointment
1780 1820 1800
1800
Meetings
arrangement
1570 1650 1600
1607
Financial
management
1900 2000 1920
1940
Appointment of
workers
1900 1940 1920
1920
Preparation of
blueprint
1400 1500 1440
1447
Procurement of
land area
1790 1890 1800
1827
Release of legal
notice
1900 2000 1920
1940
Budget
allocation
2800 2880 2880
2853
Resource
procurement
1780 1890 1800
1823
Division of
time
1400 1500 1440
1447
Duty allocation 1578 1650 1600 1609

5
PROJECT MANAGEMENT
Analysis of risk 1070 1100 1080 1083
Preparing risk
mitigation plan
1070 1100 1080
1083
Site preparation 6400 8000 7200 7200
Land
preparation
8600 9000 8640
8747
Installation of
lightening
including electrical
supplier
4140 4200 4160
4167
Installation of
gas lines and
barbeques
62100 63000 63200
62767
Seating
arrangement
98120 98000 98640
98253
Bricks
application
4500 4800 4680
4660
Volleyball court 59,000 70,080 60080 63053
Paving 5800 6000 5760 5853
Concrete
application
11900 1300 12960
8720
Colour
application
4900 4700 4680
4760
Needed system
implementation
3200 3200 3200
3200
Application of 2800 2890 2880 2857
PROJECT MANAGEMENT
Analysis of risk 1070 1100 1080 1083
Preparing risk
mitigation plan
1070 1100 1080
1083
Site preparation 6400 8000 7200 7200
Land
preparation
8600 9000 8640
8747
Installation of
lightening
including electrical
supplier
4140 4200 4160
4167
Installation of
gas lines and
barbeques
62100 63000 63200
62767
Seating
arrangement
98120 98000 98640
98253
Bricks
application
4500 4800 4680
4660
Volleyball court 59,000 70,080 60080 63053
Paving 5800 6000 5760 5853
Concrete
application
11900 1300 12960
8720
Colour
application
4900 4700 4680
4760
Needed system
implementation
3200 3200 3200
3200
Application of 2800 2890 2880 2857
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6
PROJECT MANAGEMENT
tiles
Construction of
pavement, parking
area
6400 6490 6480
6457
Formation of
relaxation area
vision
1400 1450 1440
1430
Project aim
statement
700 740 720
720
Standard
preparation service
900 980 960
947
Parking facility 1400 1450 1440 1430
Finalization of
parking
700 750 720
723
Sign off
stakeholder
1560 1500 1600
1553
Review of post
project
900 1000 960
953
PROJECT MANAGEMENT
tiles
Construction of
pavement, parking
area
6400 6490 6480
6457
Formation of
relaxation area
vision
1400 1450 1440
1430
Project aim
statement
700 740 720
720
Standard
preparation service
900 980 960
947
Parking facility 1400 1450 1440 1430
Finalization of
parking
700 750 720
723
Sign off
stakeholder
1560 1500 1600
1553
Review of post
project
900 1000 960
953
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7
PROJECT MANAGEMENT
4. Work breakdown structure
The work breakdown structure for properly setting up the relaxation area at ECU
Joondalup nearby Pine Cinema is generally provided below:
Setting up relaxation area
at ECU Joondalup
Project planning
Requirement
gathering
Analysis of project
Resource estimation
Estimating project
schedule
Budget estimation
Manpower
estimation
Resource estimation
Milestone 1: Project
plan completion
Project initiation phase
Fund procurement
for the project
Stakeholders
appointment
Meetings
arrangement
Financial
management
Appointment of
workers
Preparation of
blueprint
Procurement of land
area
Release of legal
notice
Budget allocation
Resource
procurement
Division of time
Duty allocation
Analysis of risjk
Preparing risk
mitigation plan
Milestone 2:
Completion of
initiation phase
Project execution phase
Site preparation
Land preparation
Installation of
lightining including
electrical supplier
Installation of gas
lines and barbeques
Seating
arrangement
Bricks application
Volleyball court
Paving
Concrete application
Colour application
Needed system
implementation
Aopplication of tiles
Construction of
pavement, parking
area
Milestone
3:Completion of
execution phase
Development phase
Formation of
relaxation area
vision
Project aim
statement
Standard prepration
service
Parking facility
Finalization of
parking
Milestone 4:
Ddevelopment
phase completion
Closure phase
Sign off stakeholder
Review of post
project
Milestone 5: Closure
phase completion
Figure 1: Work breakdown structure
(Source: Created by Author)
PROJECT MANAGEMENT
4. Work breakdown structure
The work breakdown structure for properly setting up the relaxation area at ECU
Joondalup nearby Pine Cinema is generally provided below:
Setting up relaxation area
at ECU Joondalup
Project planning
Requirement
gathering
Analysis of project
Resource estimation
Estimating project
schedule
Budget estimation
Manpower
estimation
Resource estimation
Milestone 1: Project
plan completion
Project initiation phase
Fund procurement
for the project
Stakeholders
appointment
Meetings
arrangement
Financial
management
Appointment of
workers
Preparation of
blueprint
Procurement of land
area
Release of legal
notice
Budget allocation
Resource
procurement
Division of time
Duty allocation
Analysis of risjk
Preparing risk
mitigation plan
Milestone 2:
Completion of
initiation phase
Project execution phase
Site preparation
Land preparation
Installation of
lightining including
electrical supplier
Installation of gas
lines and barbeques
Seating
arrangement
Bricks application
Volleyball court
Paving
Concrete application
Colour application
Needed system
implementation
Aopplication of tiles
Construction of
pavement, parking
area
Milestone
3:Completion of
execution phase
Development phase
Formation of
relaxation area
vision
Project aim
statement
Standard prepration
service
Parking facility
Finalization of
parking
Milestone 4:
Ddevelopment
phase completion
Closure phase
Sign off stakeholder
Review of post
project
Milestone 5: Closure
phase completion
Figure 1: Work breakdown structure
(Source: Created by Author)

8
PROJECT MANAGEMENT
5. Risk analysis
The risks that are related with setting up a relaxation area at ECU Joondalup is generally
provided in the table below by showcasing the impact and probability of project risk with
proper risk mitigation technique.
Risk Description Impact Probability Responsible Mitigation
Budget
overshoot
If the budget
that is needed
for setting up
the relaxation
area is not
used properly
then the
chances of
getting
budget
overshoot is
much more.
High High Financial
manager
Weekly
tracking of
project budget
is considered
to be helpful
in keeping
track on the
project budget
and as a result
the entire
project get
finished on
time by
avoiding
budget
overshoot.
Schedule
slippage
If the
schedule is
not properly
used by the
High High Project
planner
Calculation of
schedule
variance will
be helpful in
PROJECT MANAGEMENT
5. Risk analysis
The risks that are related with setting up a relaxation area at ECU Joondalup is generally
provided in the table below by showcasing the impact and probability of project risk with
proper risk mitigation technique.
Risk Description Impact Probability Responsible Mitigation
Budget
overshoot
If the budget
that is needed
for setting up
the relaxation
area is not
used properly
then the
chances of
getting
budget
overshoot is
much more.
High High Financial
manager
Weekly
tracking of
project budget
is considered
to be helpful
in keeping
track on the
project budget
and as a result
the entire
project get
finished on
time by
avoiding
budget
overshoot.
Schedule
slippage
If the
schedule is
not properly
used by the
High High Project
planner
Calculation of
schedule
variance will
be helpful in
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9
PROJECT MANAGEMENT
project
manager in
order to
progress
within the
project then
the chances
of schedule
slippage is
quite high
that further
helps in
creating
delay within
the project.
keeping track
on the
schedule of
the project
that further
helps in
avoiding
schedule
slippage and
thus the
project gets
finished on
time.
Inexperienced
team
members
If the project
team
members are
not
experienced
then, it will
be quite
difficult for
them to
manage the
Medium High HR manager Proper facility
of training
should be
provided to
the project
team so that
they can be
able to set up
the relaxation
area
PROJECT MANAGEMENT
project
manager in
order to
progress
within the
project then
the chances
of schedule
slippage is
quite high
that further
helps in
creating
delay within
the project.
keeping track
on the
schedule of
the project
that further
helps in
avoiding
schedule
slippage and
thus the
project gets
finished on
time.
Inexperienced
team
members
If the project
team
members are
not
experienced
then, it will
be quite
difficult for
them to
manage the
Medium High HR manager Proper facility
of training
should be
provided to
the project
team so that
they can be
able to set up
the relaxation
area
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10
PROJECT MANAGEMENT
cost and
schedule of
the project
effectively.
effectively for
successfully
accomplishing
goals and
objectives of
the project
quite
effectively.
Lack of
management
If the
management
of the
organization
are unable to
manage the
project that is
generally
setup for the
relaxation
area then
they will
unable to
manage the
project
effectively.
Medium Medium Managemen
t team
It is necessary
to use proper
strategies in
order to
manage the
project so that
the entire
goals and
objectives of
the project
can get
achieved
within the
budget that is
around
$319959.
Lack of If the The resources
PROJECT MANAGEMENT
cost and
schedule of
the project
effectively.
effectively for
successfully
accomplishing
goals and
objectives of
the project
quite
effectively.
Lack of
management
If the
management
of the
organization
are unable to
manage the
project that is
generally
setup for the
relaxation
area then
they will
unable to
manage the
project
effectively.
Medium Medium Managemen
t team
It is necessary
to use proper
strategies in
order to
manage the
project so that
the entire
goals and
objectives of
the project
can get
achieved
within the
budget that is
around
$319959.
Lack of If the The resources

11
PROJECT MANAGEMENT
resources resources
which are
required for
setting up the
relaxation
area is not
present then
due to
unavailability
of resources,
the project
managers
will face
difficulty in
finishing the
project work
on time.
that are
needed must
be estimated
at the initial
stage of the
project and as
per the needs
of the project,
the resources
must be
present so that
the project
team does not
face difficulty
in proper
management
of the project.
6. Gantt chart and schedule
6.1 Gantt chart
Gantt chart are mainly considered as one of the planning as well as scheduling
technique that us is used for scheduling the project activities. The Gantt chart that is
developed in order to set up the relaxation area near the Pine Cinema is generally reflected
below:
PROJECT MANAGEMENT
resources resources
which are
required for
setting up the
relaxation
area is not
present then
due to
unavailability
of resources,
the project
managers
will face
difficulty in
finishing the
project work
on time.
that are
needed must
be estimated
at the initial
stage of the
project and as
per the needs
of the project,
the resources
must be
present so that
the project
team does not
face difficulty
in proper
management
of the project.
6. Gantt chart and schedule
6.1 Gantt chart
Gantt chart are mainly considered as one of the planning as well as scheduling
technique that us is used for scheduling the project activities. The Gantt chart that is
developed in order to set up the relaxation area near the Pine Cinema is generally reflected
below:
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 23
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.