BM522 Project Management: Comprehensive Road Construction Plan for TFL

Verified

Added on  2023/06/17

|19
|2029
|92
Report
AI Summary
This report provides a comprehensive project management plan for Transport of London (TFL) concerning a road construction project. It details the selected waterfall methodology, a Gantt chart outlining the project timeline, a stakeholder analysis identifying key stakeholders and their communication strategies, and a risk analysis matrix providing mitigation strategies for potential risks. The report also includes a Work Breakdown Structure (WBS) chart, an organizational structure, and concludes with project measurement factors to ensure quality and successful project completion. The analysis considers both internal and external factors influencing the project's success, offering a structured approach to managing the TFL road construction endeavor. Desklib offers similar project management resources for students.
Document Page
BM522 PROJECT
MANAGEMENT (1)
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Table of Contents
INTRODUCTION...........................................................................................................................3
TASK 1............................................................................................................................................3
Project Methodology...................................................................................................................3
TASK 2............................................................................................................................................4
Gantt Chart...................................................................................................................................4
Manual Network Diagram...........................................................................................................5
Critical Path.................................................................................................................................6
TASK 3............................................................................................................................................6
Stakeholder Analysis...................................................................................................................6
TASK 4..........................................................................................................................................10
WBS Chart.................................................................................................................................10
Organizational Structure............................................................................................................12
TASK 5..........................................................................................................................................12
Risk Analysis.............................................................................................................................12
TASK 6..........................................................................................................................................16
Project Measurement.................................................................................................................16
CONCLUSION..............................................................................................................................17
REFERENCES................................................................................................................................1
Document Page
INTRODUCTION
Project Management (PM) can be defined as a process of leading the work of a team with
the help of which the projects goals and objectives are get achieved. The present report will
prepare the PM plan for the Transport of London (TFL) that wants to construct the road. Further,
the report will describe the methodology selected along with the Gantt chart showing total time
required to complete the project. The report will also conduct the stakeholder analysis and risk
analysis via providing proper strategies for risk mitigation.
TASK 1
Project Methodology
This is basically defines as method or practices with the help of which the project
manager can complete its project and achieve ultimate goals. For the present project plan,
waterfall methodology is best suitable and appropriate. It is because this method is one of the
most simple, easy to set up and logical method. If the project manager have identified and clear
objective then adaption & implementation of this method is beneficial. But on the other hand, the
Harrison and Lock (2017), argued that waterfall method is time consuming so their is a chance of
getting delay in project completion.
Document Page
TASK 2
Gantt Chart
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Manual Network Diagram
Document Page
Critical Path
On the basis of above network diagram their are basically two path and that is:
Path 1: 1 + 2 + 4 + 5 + 9 + 10 + 20 + 21 + 22
Path 2: 1 + 2 + 4 +5+ 9 + 10 + 21 + 22
Calculation of critical path:
Path 1: 1 + 14 + 7 + 7 + 2 + 84 + 5 + 1 + 10 = 131
Path 2: 1 + 14 + 7 + 7 + 2 + 84 + 1 + 10 = 126
As critical path is the path which takes minimum time to complete the project thus in this case
Path 2 is critical because it takes shortest time i.e., 126 days.
TASK 3
Stakeholder Analysis
Matrix of stakeholder analysis
High
Power National Media.
Construction Company.
Health Secretary.
Project Sponsor.
Construction site managers.
Low
Power Local transport company.
Local schools.
Employees.
Machinery suppliers.
Local Residents.
Low Interest High Interest
On the basis of above stakeholder analysis, it is identified that their are three internal as
well as external stakeholders which have high interest but because of low power do not take part
in project plan. So, in order to solve the issues the appropriate communication strategy need to be
adopted by the company which helps in timely completion of road construction (Silvius, 2017).
Document Page
The below table helps in adopting the communication strategy for TFL company each
stakeholders.
Stakeholder External or
Internal
Power/ Interest Impact Communication
Method
1. National
Media
External High Power/
Low Interest
They are the one
that provides
new and
information
about the
construction to
general and local
people.
Billboards and
Leaflet
2. Construction
Company.
Internal High Power/
Low Interest
They are the one
that construct the
road thus have to
make sure that
the project
successfully
completed
(Mohammed,
and et.al., 2019).
Phone Calls and
Regular meetings
3. Health
Secretary
External High Power/
Low Interest
They have power
to ensure that the
project follows
all health related
legislation
because they
provide fund to
the company.
Monthly report
4. Local External Low Power/ Low They get affected Meetings and
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
transport
company
interest if the road
construction
found any
default. As it
affects the life of
the people
transporting
(Eskerod and
Larsen, 2018).
Emails
5. Local schools External Low Power/ Low
interest
They get benefit
in the term of
children safety
because of
proper road
construction.
Emails
6. Project
Sponsor
Internal High Power/
High Interest
These are the one
that provide
funds for project
thus interested in
knowing whether
the project is
successful or not.
Regular and
Timely meetings
7. Construction
site managers
Internal High Power/
High Interest
Involved in
successful and
timely
completion of
project.
Monthly report
8. Employees Internal Low Power/
High Interest
They have
interest in project
because they will
get wages
Phone Calls
Document Page
benefits from
this.
9. Machinery
Suppliers
External Low Power/
High Interest
They provide
raw material and
machinery that’s
why involved in
the success of the
project.
Phone Calls plus
emails
10. Local
Residents
External Low Power/
High Interest
With the help of
road
construction, the
resident get the
safety and
security benefits
while travelling
(Raum, 2018).
Leaflet
Document Page
TASK 4
WBS Chart
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Document Page
Organizational Structure
TASK 5
Risk Analysis
Matrix of Risk analysis
High
Probabilit
y
Design risk
Accident risk
Construction risk
Complying with law
Resource risk
Environmental risk
Quality testing
External risk
Performance risk
Organizational risk
Low
Portabilit
y
Market risk
Contradiction with
contractors
Communication risk
High-cost risk
Leadership risk
Time risk
Project management risk
Operational strategy
Right of way risk
Change management style