This document presents a comprehensive project plan for implementing an advanced voice recognition system, MacSpeech Scribe, in Daintree National Park to enhance tourist services. The plan outlines the project's objectives, which include improving navigation, information access, and recommendations for visitors through voice commands. It details assumptions, justifications, and the importance of project management, including resource and cost structures. The plan incorporates a project team structure with assigned duties and timelines, along with PERT and Gantt charts for analyzing time requirements, costs, and employee duty management. Furthermore, the document includes a written report with a cost-benefit analysis, work breakdown structure, risk management plan, and post-implementation plan to ensure the successful deployment and maintenance of the voice recognition system. Desklib provides access to similar project plans and solved assignments for students.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Information System Project
-Management

1 | P a g e
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Table of Contents
Project Plan
................................................................................................................................................. 6
1. Executive summary
.............................................................................................................................. 6
2. Introduction
......................................................................................................................................... 7
Deploying advanced voice recognition system in Daintree National Park
...........................................7
3. Assumptions
........................................................................................................................................ 9
4. Summary
............................................................................................................................................11
Importance of Voice Recognition Technology
...................................................................................11
Benefits of MacSpeech Scribe voice recognition system to the management are as followed
.........11
5. Project Management
.........................................................................................................................12
Cost and Resource Structure
............................................................................................................. 14
Design Phase
......................................................................................................................................17
Implementation Phase
.......................................................................................................................17
Training Phase
................................................................................................................................... 18
6. Milestone
........................................................................................................................................... 20
7. GANTT Chart
...................................................................................................................................... 21
8. PERT CHART (
Program Evaluation Review Technique)......................................................................22
9. Conclusion
......................................................................................................................................... 23
Written Report
.......................................................................................................................................... 24
1. Executive Summary
........................................................................................................................... 24
2. Introduction
....................................................................................................................................... 25
3. Cost-Benefit Analysis
......................................................................................................................... 26
4. Managing the project
........................................................................................................................ 28
Work Breakdown Structure
............................................................................................................... 29
Monitoring, Review, and Evolution
................................................................................................... 30
5. Implementation Plan
......................................................................................................................... 31
2 | P a g e
Document Page
6. Risk management plan......................................................................................................................33
7. Post-Implementation Plan
.................................................................................................................34
References
................................................................................................................................................. 35
List of Figures

Figure 1: Project Management Workflow
.....................................................................................10
Figure 2: Project Planning Steps
....................................................................................................11
Figure 3: Milestone
........................................................................................................................16
Figure 4: GANTT chart
.................................................................................................................17
Figure 5: Pert Chart
....................................................................................................................... 18
Figure 6: Work Breakdown Structure
............................................................................................25
3 | P a g e
Document Page
Project Plan
1. Executive summary

The focus of the report is to execute voice recognition technology to Daintree National Park. The

Daintree National Park has located far north Queensland. This is one of the most attractive places

in Australia. Daintree National Park is famous due to its ancient ecosystem. Thousands of tourists

around the world visit this destination and spend their relief time. Tourists found it more attractive

due to its natural attractions and ancient ecosystem. Though tour managers and management team

provide various facilities to the tourists the management required more advanced technology for

visitors that provide accurate navigation, information system and recommendations. Hence,

management deliberated MacSpeech Scribe (a voice recognition system) to improve the customer

or tourist services. The features of MacSpeech Scribe enabled users to get information just by

giving the voice command.

Further, PERT chart, Gantt chart and Milestone are used for analysis of process. Management tools

are used to overcome the management issues. PERT chart and Gantt chart are used to analyze the

required time period, applied costs and employee duty management. For better understand the

resources and cost, project plan has created.

4 | P a g e
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
2. Introduction
The main focus of the research is to implement an advanced voice recognition system to provide

services to the tourists. Voice recognition system, MacSpeech Scribe introduced at the place of

existing technology using at the Daintree National Park. The tourist attraction is the motto of the

Daintree National Park management team. The report is also provided with the overview and

impact of the implementation of an advanced voice recognition system (
Galy & Sauceda 2014, p.
315)
. Further, assumptions and justification are provided on the advance MacSpeech Scribe. The
report has also explained the importance of project management, how and why it is important for

effective management?

The report further provided information about the cost structure that helps in getting detail about

the utilization of the resources. Project team is created to achieve the requirements of project. They

further grouped as per their duties and time. Effective duty and time allocation are provided

successful completion of the project. In the end, PERT, Gantt chart and milestone are prepared to

get overall information about the time that is required for completion of each activity.

Deploying advanced voice recognition system in Daintree National Park

Daintree National Park located is famous for its natural attraction and ancient ecosystem. It is

allocated far North Queensland in Australia. Daintree River and Mossman Gorge are also located

at the ends of the national park. Visitors/tourists attracted to its natural beauty and rainy forest

terrains. Where the visitors can take a walk and swim also. Apart from all these areas and places,

tourists get more attracted from the range of boardwalks and beaches that are untouched. These

places are found after crossing the Daintree River.

There are several more attractive places that can attract the new and existing visitors. Reason

behind the tourist attraction is the biodiversity of Daintree National Park. On the way to increase

the number of visitors, Daintree National Park should implement the voice recognition system that

could help them to attract number of customers and provide customer services in a better way.

Although, Daintree National Park using advanced technologies to provide assistance to the

visitors/tourists implementation of voice recognition system could increase the interest of visitors

and tourists (Candini et al. 2014, p.
113). Voice recognition software is advanced and reliable
hence it will help Daintree National Park to advance their customer services and online assistance

system.

5 | P a g e
Document Page
3. Assumptions
The research is focused on the implementation of voice recognition technology in Daintree

National Park. Existing assistive technology is a required enhancement. The reason behind the

implementation of voice recognition system is to attract tourists towards the Daintree National

Park. Voice recognition system is effective and reliable when it comes to providing accurate

assistance to the site visitors (Duncan, Mohammed & Li 2014, p. 201). Existing technology doesn't

have the feature of providing service on call. While in voice recognition system enable tourist to

get required information just by using voice commands. voice recognition system can provide

information about nearby places, services and navigation services (Conde,
Gonçalves & Pinheiro
2018
). Hence, the following assumptions are made on the basis of developing service system by
implementing voice recognition system.

Voice recognition is based on the human voice decoding system, where human voice decoded by

the system and converted into the command. Some assumption towards this are as followed:

As the technology is based on the voice command, so that the visitor/tourist can easily
retrieve the required information just by giving voice command to the voice recognition

device (Saunders et al. 2014). Voice recognition technology eliminates the issue of

searching information and provides user-friendly way to get the information.

Training sessions for accurately using voice recognition technology is given to the staff and
employees. It is important because only employees are those who interact with the

tourists/visitors. They can easily assist the visitors to get the information and can also

provide troubleshooting when any error found in the voice recognition system while in

practice.

Voice recognition system can also collect the information about what tourist/visitor looking
for when they use the application. It will help Daintree National Park management to know

more about the interests of visitors/tourists.

Voice recognition technology is very precise and it delivers impressive performance.
Hence, implementation of voice recognition system can provide information whatever has

commanded from the visitor/tourists (Wood, Saunders & Bex 2015). Commands provide

the result within seconds.

6 | P a g e
Document Page
Voice recognition system also able to work on the different languages. Visitors/tourists
from different countries can easily communicate through the voice recognition system and

collect the required information i.e. nearby places, hotels, restaurants etcetera.

7 | P a g e
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4. Summary
Voice recognition technology is an advanced technology that eliminates the language issues and

provides results and information on just voice command. Visitors can easily retrieve the

information by giving voice command on the software. After taking some assumption about the

technology, it has introduced. Daintree National Park official website provides information about

the visitors/tourists that, sometimes they are facing issues of getting information about the places

and general queries. Voice recognition system helps to prevent such issues

(Daintreerainforestinformation.com 2018). By using such technology visitors can easily collect the

information by giving the voice command. They don't need to call at hotels or places for the

information. Only voice command can provide all the information they wanted.

Importance of Voice Recognition Technology

This is an emerging technology that delivered extraordinary performance. whether it is using at the

industry, company or for individual. It provides the same results and works efficiently with

accuracy. These features can help Daintree National Park to improve their services and increase the

number of visitors (Highwaytraveller.com.au 2018). Voice recognition can also help Daintree

National Park to collect the information about searches and voice commands to better understand

the requirements and visitor’s interests.

Benefits of MacSpeech Scribe voice recognition system to the management are as followed

The MacSpeech Scribe provides high of 99% accuracy while performing as an information
provider. It works on voice commands (Wu 2018, p. 175). Once anyone gives voice

command to the voice recognition software it quickly responds to it and provide relevantly

and required information.

It can also help park staff and employees to seek visitor’s attraction by providing
knowledge about voice recognition software.

Visitors can get the required information, that is only one voice command to go.
Implementation of voice recognition software can attract more visitors because it is able to

provide accurate result at any place.

The MacSpeech Scribe voice recognition software is quite smart. It opens right at the time
when visitor/tourist ask help on the device or site.

8 | P a g e
Document Page
5. Project Management
Project management is required for achieving the expected results. It includes allocation of

resources and activities. Hence, it is necessary to find various activities and tasks for the

development of voice recognition technology in Daintree National Park. The project plan includes

almost every tasks and actions that help in getting desired output. It includes execution, controlling

and planning of activities. Effective project management helps to get the desired results. For

effective project management following steps are required and it can also help to develop the voice

recognition system for the Daintree National Park.

Figure
1: Project Management Workflow
(Source: Author, 2018)

Initiation

At the initial stage of project plan, project manager explained the plan, scope, objectives,

responsibilities and roles of each team member. These process helps project manager and

management to evaluate the issues and problems associated with the existing technology or

system. Evaluation is done on the basis of problem assessment. Further, the project manager

identifies the tasks that are important for the completion of project. Towards that project

9 | P a g e

Initiating
Planning
Exectuing
Monitorin
g and
Controllin
g
Closing
Document Page
management has been prepared a project proposal and provides regarding information to the team
members so that they will be aware of the objectives of the project.

Planning

In this process, the project manager provides overview of cost, risk, time and other problems that

could be seen while developing project activities. Towards that project manager prepared a

framework having information of cost and resources (Ferwerda 2014, p. 2). Resource allocation is

done by the project manager. Following steps are need to be followed by each team member so that

task execution can be done in proper way –

Figure
2: Project Planning Steps
(Source: Author, 2018)

10 | P a g e

Project
scope
Project
schedule
Project
resources
Project
budget
and cost
Project
Quality
Project
Risk
Project
communic
ation
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
SWOT analysis –
SWOT analysis helps Daintree National Park to implement new voice recognition system that

helps Daintree National Park to eliminate weaknesses and threads associated with the existing

technology. SWOT analysis also helps to identify Strengths, Weaknesses, Opportunities and

Threads of Daintree National Park.

Cost and Resource Structure

Administrative cost

Resource Name
Work Start Finish Std. Rate Cost
Application programmer
24
hrs

Tue 02-10-

18

Thu 01-11-

18
$55.00/hr $1,320.00
Project manager (Technical)
24
hrs

Wed 26-09-

18

Tue 30-10-

18
$52.00/hr $1,248.00
Project manager
80
hrs

Mon 24-09-

18

Tue 06-11-

18
$57.00/hr $4,560.00
Developer
8 hrs Mon 15-10-
18

Mon 15-10-

18
$51.00/hr $408.00
System integrator
48
hrs

Tue 02-10-

18

Wed 24-10-

18
$59.00/hr $2,832.00
Quality assurance officer
32
hrs

Thu 25-10-

18

Wed 07-11-

18
$57.00/hr $1,824.00
Business Analyst
40
hrs

Mon 24-09-

18

Tue 06-11-

18
$53.00/hr $2,120.00
Project Budgeting

Resource name
Total cost in $
Charges for server room modification
$37,000.00
CAT 6a Patch Cable
$825.00
11 | P a g e
Document Page
Apple Hardware $2,600.00
Total Cost

Resource name
Total cost in $
Administrative cost
14312
Project Budgeting
42345
Total Cost (in $)
56657
Resource, time and cost structure

Task Name
Duration Start Finish Resource Names Cost
Planning
15 days
Mon

24-09-

18

Fri 12-

10-18
$6,240.00
Identify the problem
2 days
Mon

24-09-

18

Tue

25-09-

18

Business Analyst, Project

manager
$1,760.00
Prepare a proposal
2 days
Wed

26-09-

18

Thu

27-09-

18

Project manager, Project

manager (Technical)
$1,744.00
Define duties of each

team
3 days Fri 28-
09-18

Mon

01-10-

18

Project manager
$912.00
Identify existing

capacity
7 days Tue
02-10-

Wed

03-10-

Application programmer,

System integrator
$1,824.00
12 | P a g e
Document Page
18 18
Planning face

completed
1 day
Thu

04-10-

18

Fri 12-

10-18
$0.00
13 | P a g e
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Design Phase
Task Name
Duration Start Finish Resource Names Cost
Implement
1 day Mon 15-
10-18

Mon 15-10-

18
Developer $408.00
Increase the server

capacity
1 day Tue 16-10-
18

Tue 16-10-

18

System

integrator
$472.00
Setup required
2 days Wed 17-
10-18

Thu 18-10-

18

System

integrator
$944.00
Design phase

completed
3 days Fri 19-10-
18

Tue 23-10-

18
$0.00
Implementation Phase

Task Name
Duration Start Finish Resource Names Cost
Install MacSpeech

Scribe recognition

application

1 day
Wed 24-
10-18

Wed 24-

10-18
System integrator $472.00
Test the performance
1 day Thu 25-
10-18

Thu 25-

10-18

Project

manager,Quality

assurance officer

$912.00

Note the impact on the

server
1 day Fri 26-10-
18

Fri 26-10-

18

Quality assurance

officer
$456.00
Note time is taken to

respond the query
1 day Mon 29-
10-18

Mon 29-

10-18

Quality assurance

officer
$456.00
Provide practical

demonstration
1 day Tue 30-
10-18

Tue 30-

10-18

Project

manager,Project

manager (Technical)

$872.00

Take customer

feedback
1 day Wed 31-
10-18

Wed 31-

10-18
Business Analyst $424.00
Do changes

accordingly
1 day Thu 01-
11-18

Thu 01-

11-18

Application

programmer,Project

manager

$896.00

14 | P a g e
Document Page
Installation phase
completed
1 day Fri 02-11-
18

Fri 02-11-

18
$0.00
Training Phase

Task Name
Duration Start Finish Resource Names Cost
Prepare training
1 day Mon 05-
11-18

Mon 05-11-

18
Business Analyst $424.00
Give training to team

members
1 day Tue 06-11-
18

Tue 06-11-

18

Business

Analyst,Project

manager

$880.00

Identify the issues
1 day Wed 07-
11-18

Wed 07-11-

18

Quality assurance

officer
$456.00
Training phase

completed
1 day Thu 08-11-
18

Thu 08-11-

18
$0.00
HR Phase

Designation

Educational

Qualificatio

n

Professional

Experience

Number of

year

experience

in this

organization

Domain

Knowledge

Level

Communicatio

n Level

Application

programmer

B’Tech

(Computer

Science)

3 years
1 years Expert Expert
Project

manager

(Technical)

B’Tech

(Computer

Science)

3 years
2 years Professional Professional
Project

manager

M’Tech
15 years 5 years Professional Professional
Developer
B’Tech
(Computer

Science)

3 years
2 years Expert Beginner
15 | P a g e
Document Page
System
integrator

B’Tech

(Electrical)

5 Years
3 years Expert Beginner
Quality

assurance

officer

MBA
5 Years 2 years Expert Expert
Business

Analyst

MBA in

marketing

6 years
4 years Professional Professional
16 | P a g e
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
6. Milestone
24-09-18

27-09-18

30-09-18

03-10-18

06-10-18

09-10-18

12-10-18

15-10-18

18-10-18

21-10-18

24-10-18

27-10-18

30-10-18

02-11-18

05-11-18

08-11-18

0

5

10

15

20

25

30

Remaining Tasks
Remaining Actual Tasks
Figure
3: Milestone
17 | P a g e
Document Page
7. GANTT Chart
ID Task
Mode
Task Name Duration Start Finish Predecessors Resource Names
0 Project1 34 days Mon 24-09-18Thu 08-11-18
1 1 Planning 15 days Mon 24-09-18Fri 12-10-18
2 1.1 Identify the problem2 days Mon 24-09-18 Tue 25-09-18 Business Analyst,Project manager
3 1.2 Prepare a proposal2 days Wed 26-09-18 Thu 27-09-18 2 Project manager,Project manager (Technical)
4 1.3 Define duties of each tem2 days Fri 28-09-18 Mon 01-10-18 3 Project manager
5 1.4 Identify existing capacity2 days Tue 02-10-18 Wed 03-10-18 4 Application programmer,System integrator
6 1.5 Planning face completed7 days Thu 04-10-18 Fri 12-10-18 5
7 1.6 Planning phase
completed
0 days Fri 12-10-18 Fri 12-10-18 6
8 2 Design 7 days Mon 15-10-18Tue 23-10-18 1
9 2.1 Implement 1 day Mon 15-10-18 Mon 15-10-18 Developer
10 2.2 Increase the server capacity1 day Tue 16-10-18 Tue 16-10-18 9 System integrator
11 2.3 Setup required 2 days Wed 17-10-18 Thu 18-10-18 10 System integrator
12 2.4 Design phase completed3 days Fri 19-10-18 Tue 23-10-18 11
13 2.5 Design phase
completed
0 days Tue 23-10-18 Tue 23-10-18 12
14 3 Instrallation and
Implementation
8 days Wed 24-10-18Fri 02-11-18 8
15 3.1 Install MacSpeech Scribe recognition application1 day Wed 24-10-18 Wed 24-10-18 System integrator
16 3.2 Test the performance1 day Thu 25-10-18 Thu 25-10-18 15 Project manager,Quality assurance officer
17 3.3 Note the impact on the server1 day Fri 26-10-18 Fri 26-10-18 16 Quality assurance officer
18 3.4 Note time taken to respond the query1 day Mon 29-10-18 Mon 29-10-18 17 Quality assurance officer
19 3.5 Provide practical demonstration1 day Tue 30-10-18 Tue 30-10-18 18 Project manager,Project manager (Technical)
20 3.6 Take customer feedback1 day Wed 31-10-18 Wed 31-10-18 19 Business Analyst
21 3.7 Do changes accordingly1 day Thu 01-11-18 Thu 01-11-18 20 Application programmer,Project manager
22 3.8 Installation phase completed1 day Fri 02-11-18 Fri 02-11-18 21
23 3.9 installation
phase completed
0 days Fri 02-11-18 Fri 02-11-18 22
Business Analyst,Project manager
Project manager,Project manager (Technical)
Project manager
Application programmer,System integrator
12-10
Developer
System integrator
System integrator
23-10
System integrator
Project manager,Quality assurance officer
Quality assurance officer
Quality assurance officer
Project manager,Project manager (Technical)
Business Analyst
Application programmer,Project manager
02-11
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
24 Sep '18 01 Oct '18 08 Oct '18 15 Oct '18 22 Oct '18 29 Oct '18 05 Nov '18

Figure
4: GANTT chart
18 | P a g e
Document Page
8. PERT CHART (Program Evaluation Review Technique)
This chart provides graphical representation of project’s timeline. PERT chart divides individual

tasks of project for evaluation (Nas 2016). The graphical representation provides overview of tasks

such as task, resource type, cost. PERT (
Program Evaluation Review Technique) chart also
provides information about key activities along with their sub-activities.

Figure
5: Pert Chart
19 | P a g e
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
9. Conclusion
The project plan is provided overall information about the effects and advantages of

implementation of voice recognition system at Daintree National Park. It is important to implement

new technology at the tourist places because visitors/tourists attracted to the advanced

technologies. Voice recognition technology found effective and popular when it comes to

delivering assistive performance. In the project plan new software MacSpeech Scribe has

introduced that provide features such as voice command assistance, recommendations etcetera.

Implementation of new voice recognition software enabled user to collect required information

without surfing the internet, checking website or call to the site.

Further, project planning has developed. It is important for getting estimated cost and resources

that are involved in project. In addition, time required to complete each task has also identified

using Gantt chart (a project planning tool). After estimating time, cost and resources, project

manage allocated duties and tasks to each team member. Project managed played an important role

to complete the task on time as project manager communicated with the team members on regular

basis.

20 | P a g e
Document Page
References
Conde, T, Gonçalves, ÓF & Pinheiro, AP 2018,
Stimulus complexity matters when you hear your
own voice: Attention effects on self-generated voice processing,
International Journal of
Psychophysiology
.
Ferwerda, J 2014,
Cost-benefit analysis. Chapters, 5, pp. 1-4.
Harrison, F & Lock D 2017,
Advanced project management: a structured approach. Routledge.
Highwaytraveller.com.au, 2018,
Australian Towns and Highways’, In Australian Towns and
Highways, <
http://highwaytraveller.com.au/highways >.
Kendrick, T 2015,
Identifying and managing project risk: essential tools for failure-proofing your
project
. Amacom.
Saunders, DR, Bex, PJ, Rose, DJ & Woods, RL 2014,
Measuring information acquisition from
sensory input using automated scoring of natural-language descriptions
, PloS one.
Wood, RL, Saunders, DR & Bex, P 2015,
Measuring Information Acquisition Using Free Recall,
U.S. Patent Application.

21 | P a g e
Document Page
Written Report
1. Executive Summary

The report is focused on the showing impact of MacSpeech Scribe voice recognition software

implementation in Daintree National Park. The report is also provided brief information about cost

benefits after implementing MacSpeech Scribe in Daintree National Park. Towards that,

justification is also provided on the implementation of MacSpeech Scribe. The report has also

covered the steps that are important for non-technical staff. For that, a work breakdown structure is

developed in the way to provide employee's overview of their work and tasks along with the sub-

tasks. The work breakdown structure is effective because of its feature of providing time-efficiency

while completing tasks.

The non-technical team members are focused on the report where their tasks, roles and

responsibilities are justified. To overcome the risks and vulnerabilities, precautions are also

considered so that risk rate can be minimized. To make it more accurate, post-implementation plan

is explained that provide way to mitigate and remove the risk changes in the project.

22 | P a g e
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
2. Introduction
The report is focused on the execution of MacSpeech Scribe voice recognition software in Daintree

National Park. The report is also covered the impacts that could be seen after implementation of

voice recognition software for customer services and assistance. Daintree National Park is known

for its beauty and natural attraction that make an attractive destination and visiting place of

Australia. The report is analyzed the cost benefits that could be seen after the implementation of

voice recognition system. This report has also covered the tasks, rules and responsibilities of non-

technical team members including control measures at every step of the plan. These steps are

important because they could reduce the chances of risks and further, precautions are also provided

that covered the steps that are important to take.

The work breakdown chart is also prepared to provide information about tasks and sub-tasks to the

non-technical team members. The report is focused on the collection of cost-related information.

Costs that are needed to complete the scheduled tasks and sub-tasks. Further, post-implementation

plan and risk assessment are also created that provide overview of risks and related precautions.

Control measured are also performed at each step of the plan.

23 | P a g e
Document Page
3. Cost-Benefit Analysis
The cost-benefit analysis provided explanation of detailed project plan that includes cost of each

task. The assumption has made on the Daintree National Park visitor’s number and that is 120

visitors/day. Daintree National Park provides accommodation and travelling facility. There are

natural ponds located in forest terrain and animal safari is also provided to the visitors. These

facilities will add more benefits. The vehicle parking and restaurants are also provided more

benefits. For all these facilities from travelling to accommodation and food to parking, visitors

need to pay $70/person. The overall monthly sale is estimated to be 261170 $

TOTAL COST

COST BENEFIT ANALYSIS

Total Expenses
Per tourist
Total

revenu

e
261170
3072.5

88

Less:

Total

Cost
119675
1407.9

41

Expect

ed

Profit
141495
1664.6

47
54%
Revenue items

Per

mont

h($)

Online Ticket Sales

1045

70

parking
4000
Cafetaria

3400

0

Jungle safari charges
2800
24 | P a g e
Document Page
Camping
1500

0

Other Faciltiies

1680

0

Accommodation

8400

0

Total

2611

70

In the project plan, non-technical persons are selected because they are helpful in execution of plan

and activities. Business analyst is important for the project because they can provide positive or

negative impact of implementing voice recognition system in Daintree National Park. Where the

business analyst is required as they can provide report of expenses and costs. Guidelines are

provided to the project manager via administrative office. Administrative office also coordinated

with the team members for completing the activities. Towards that Administrative office also

organized meetings and pieces of training to discuss the project costing, project planning and

project resources and administrative officer is important because they formulate a communication

channel that helps to function the tasks and activities.

Further, project manager manages the resources that are required to accomplish the task and data

entry office helps to get the cost related information. Developers help to install MacSpeech Scribe

in Daintree National Park. System integrator installs the hardware and software that are related to

the voice recognition technology. It is also increased the server capacity. For providing voice

recognition technology training to the employees, trainers are similarly required who has the

complete knowledge of voice recognition technology.

25 | P a g e
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4. Managing the project
Project management is required in this report because it provides way to develop an effective and

feasible plan. Project management included allocation of resources and planning of activities.

These processes can help to accomplish settled result. Finding new tasks and activities for the

development of voice recognition technology is also required. Project management includes

overview of activities, planning and executions. Effective project management can be produced by

using various tools and techniques (Kerzner & Kerzner 2017). It could help in implementation of

MacSpeech Scribe voice recognition software in Administrative office. Management of all the

activities and resources are also required to avoid fatigue in project. The planning is done by

project manager, as they have overall information that is required in the project management.

Hence, project manager assigned roles and tasks to each employee. To plan accordingly, project

management use tools and techniques i.e. cost-benefit analysis, Gantt chart and critical path

analysis (Harrison & Lock 2017). After using all these tools and techniques, breakdown structure is

prepared for providing information about duties that need to be done by the employees.

1.
Risk assessment
2.
Project integration
3.
Cost management
4.
Time management
5.
Quality management
6.
Communication management
Above mentioned are the key area that is considered while implementing MacSpeech Scribe voice

recognition software in Daintree National Park.

26 | P a g e
Document Page
Work Breakdown Structure
Figure
6: Work Breakdown Structure
(Source: Author, 2018)

27 | P a g e
Document Page
28 | P a g e
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Monitoring, Review, and Evolution
Activity monitoring is an important process as it provides way to accomplish project target before

the deadline. Monitoring of cost, risk, performance and time could decrease the chances of wastage

of costs and resources. Accurate completion of project is depended upon the process of measuring

controls (Marchewka 2014). Towards that, project manager analyzes collected reports and

effectively implement control measures at every stage of project.

For successful completion of project, some steps are needed to be considered and these are as

followed –

Scheduling

Scheduling of all activities is required to complete tasks on or before deadlines. Activities and sub-

activities are also needed to get scheduled (Moyle et al. 2014, p. 1040). Hence. Timetable of

activities is mandatory if an effective output is required.

Budgeting

Proper budgeting of each task should be prepared which is having detail of cost required to

complete each task. Budgeting help to minimize overall expenses and calculate the necessary

expenses.

Quality of the output

Every project is required an effective and quality of output. For that, quality check at every stage

should be done properly to get efficient task and activity output (Pelosi et al. 2014, p. 64).

Developing a proper communication channel

Administrative officer develops a communication channel between workers/employees and team

leaders. This communication channel help employees to get information whenever wanted

(Kendrick 2015). Communication between team lead and employee can reduce the chances of

errors in operation.

29 | P a g e
Document Page
5. Implementation Plan
Activities
Time Cost Resources Allocated
1st Week

Preparing Project Proposal
1 day $800 Computers and external drives
Drafting Project Charter
1 day $900 Computers and external drives
Defining roles and responsibilities of the

team members

1 day
$1,000 Computers, projectors, and
external drives

Evaluating the existing capacity
2
days

$800
Computers and external drives
Presenting the draft to the stakeholders
1 day $2,500 Computers, projectors, and
external drives

2nd Week

Evaluating the harware and software

requirement

1 day
$800 Computers and external drives
Enhancing Server capacity
3
days

$23,000
Network cables and other
equipment

Identifying the vendor for procuring

hardware

1 day
$600 Computers
Purchasing the new hardware
1 day $2,200 CAT 6a Patch Cable
3rd Week

Installing MacSpeech Scribe Software
1 day $3,000 Computers
Testing the performance
1 day $5,500 Computers
Evaluating the time taken to respond to

the queries

1 day
$1,800 Computers
4th week

Providing practical demonstration to the

visitors

2

days

$5,000
Computers
Requesting 20 visitors to use the

application

1 day
$1,800 Leaflets, Information guides
Taking feedback for evaluating the

results

1 day
$2,300 Hard copies of questionnaires
30 | P a g e
Document Page
5th week
Making changes according to the

feedback received

2

days

$6,000
Computers and external drives
6th week

Defining training needs
2
days

$2,800
Computers and external drives
Preparing appropriate training modules
3
days

$1,800
Computers and external drives
7th Week

Providing training to the staff
4
days

$13,000
Computers, and projectors
8th week

Conducting tests
3
days

$6,500
Computers
9th Week

Evaliuating performance and identifying

further training requirements

4

days

$3,800
Computers, hard copies of
answer keys

31 | P a g e
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
6. Risk management plan
Types of

Risks
Risk Evaluation Impact Risk Management Techniques
Time
Delays in completing the activities High
Deadline provided to for the

completion of priority-based

tasks

Delays in executing priority-based

tasks
High
Preparing and maintaining

appropriate time table by listing

all the activities

Providing insufficient time for

completing the tasks
High Providing accurate training and
write down all the requirements

Cost
Wastages of resources High Allocating only the required
resources

Loss due to theft and fire
High Adequate supervision of the
work performed

Loss due to natural disaster
High Taking help of insurance
companies

Quality
Reduced quality of work due to in-
experienced staff
High Providing adequate training
before commencing the tasks

Improper quality checks
High Proper control measures have to
be implemented at all levels

Purchasing inferior quality

hardware
High Proper checks to be made before
purchasing the hardware

Improper evaluation of software

requirements
High
IT manager should make the

final assessment after checking

all the reports

32 | P a g e
Document Page
7. Post-Implementation Plan
Activities
Time Cost Resources Allocated
Evaluating the harware and software

requirement
1 day $800
Computers, access to server

and external drives

Updating Dragon NaturallySpeaking

application monthly
2 days $2,400 Computers
Testing the performance quarterly
1 day $1,100 Computers
Evaluating the time taken to respond to the

queries
1 day $2,100 Computers
Taking feedback from customers daily for

evaluating the performance
1 day $1,600
Computers and external

drives

Making changes according to the feedback

received
2 days $6,000
Computers and external

drives

Updating the server monthly
2 days $2,800
Computers and external

drives

Providing new updates to the employees

regarding the changes in the application
3 days $5,800 Computers, and projectors
To execute a project plan it is very important to plan activities that need to perform. MacSpeech

Scribe voice recognition system installation has done in Daintree National Park (Hudson & Laken.

2015, p. 255). To better perform the voice recognition system after installation it is important to

schedule activities. Performance and efficiency of installed hardware, software and server are

dependent on the regular control measures (Martinelli & Milosevic 2016). It also enhanced the

performance of installed voice recognition system. Towards that, customer feedbacks can also be

helpful to improve the performance of voice recognition software (Wang et al. 2018). Developers

can further update the software on the basis of feedbacks so that customer services can be

improved.

33 | P a g e
Document Page
References
Candini, M, Zamagni, E, Nuzzo, A, Ruotolo, F, Iachini, T & Frassinetti, F 2014
, Who is speaking?
Implicit and explicit self and other voice recognition
. Brain and cognition, pp. 112-117.
Daintreerainforestinformation.com 2018,
Daintree National Park’, In
Daintreerainforestinformation.com, <

http://www.daintreerainforestinformation.com/About_Daintree.html >.

Duncan, PJ, Mohammed, DY &
Li, FF 2014, ‘Audio Information Mining–Pragmatic Review,
Outlook, and a Universal Open Architecture
’, Audio Engineering Society Convention, vol. 136,
pp. 201.

Galy, E & Sauceda, MJ 2014, ‘Post-implementation practices of ERP systems and their

relationship to financial performance’
, Information & Management, vol. 51, pp. 310-319.
Hudson, SM & Laken, MA 2015,
Use of a PERT Chart to Improve Efficiency of the
Dissertation
, Nursing education perspectives, pp. 257-258.
Kerzner, H & Kerzner, HR 2017,
Project management: a systems approach to planning,
scheduling, and controlling
, John Wiley & Sons.
Marchewka, JT 2014,
Information technology project management. John Wiley & Sons.
Martinelli, RJ & Milosevic, DZ 2016,
Project management toolbox: tools and techniques for the
practicing project manager
, John Wiley & Sons.
Moyle, BD, McLennan, CLJ, Ruhanen, L & Weiler, B 2014,
Tracking the concept of sustainability
in Australian tourism policy and planning documents
, Journal of Sustainable Tourism, pp. 1037-
1051.

Nas, TF, 2016,
Cost-benefit analysis: Theory and application, Lexington Books.
Pelosi, MJ, Brown, MS, Dirska, H & Assadullah, MM 2014, ‘Efficient Work Team Scheduling:

Using Psychological Models of Knowledge Retention to Improve Code Writing

Efficiency’,
Journal of Systemics, vol. 12, pp. 62-65.
Wang, X, Xu, Y, Hu, H, Liu, M & Li, G 2018,
Feedback-based Metric Learning for Activity
Recognition.
Expert Systems with Applications.
34 | P a g e
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Wu, D 2018, ‘Online position recognition and correction method for sports athletes’, Cognitive
Systems Research
, vol. 52, pp. 174-181.
35 | P a g e
chevron_up_icon
1 out of 35
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]