Comprehensive Project Plan: Repairing Storage Tanks, Western Australia
VerifiedAdded on  2023/06/05
|20
|2571
|195
Report
AI Summary
This report presents a comprehensive project plan for repairing and modifying three petrol storage tanks at a site in Western Australia. The project aims to upgrade the tanks to modern standards and mitigate negative environmental impacts. The plan includes detailed budget estimations, covering project survey and initiation, project planning, execution, and closure, with a total estimated cost of $1,394,380.00. A project schedule spanning 132 days, from September 21, 2018, to March 25, 2019, is outlined using a work breakdown structure and Microsoft Project software. Resource estimations are provided, identifying key personnel, equipment, and materials, along with a Gantt chart illustrating the critical path and stress points. The report also details the assumptions made during planning, such as stable material costs and standard working hours, ensuring a well-structured approach to the tank repair project. Desklib provides access to this and other solved assignments.

Running Head: PROJECT MANAGEMENT
Repairing of Storage Tanks at Western Australia Site
Name of the Student
Name of the University
Repairing of Storage Tanks at Western Australia Site
Name of the Student
Name of the University
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1PROJECT MANAGEMENT
Table of Contents
1.0 Introduction................................................................................................................................2
2.0 Project Budget Estimation.........................................................................................................2
2.1 Overall Budget Estimation....................................................................................................2
2.2 Assumptions..........................................................................................................................7
3.0 Project Schedule........................................................................................................................8
3.1 Schedule.................................................................................................................................8
3.2 Tools and Techniques Used.................................................................................................13
3.3 Comparison of Tools and Methodologies............................................................................14
4.0 Resource Estimation for Project..............................................................................................14
4.1 Resources Required.............................................................................................................14
4.2 Critical Path and Stress Points for Resources......................................................................15
4.3 Tools and Techniques Used.................................................................................................17
5.0 Conclusion...............................................................................................................................17
Bibliography..................................................................................................................................18
Table of Contents
1.0 Introduction................................................................................................................................2
2.0 Project Budget Estimation.........................................................................................................2
2.1 Overall Budget Estimation....................................................................................................2
2.2 Assumptions..........................................................................................................................7
3.0 Project Schedule........................................................................................................................8
3.1 Schedule.................................................................................................................................8
3.2 Tools and Techniques Used.................................................................................................13
3.3 Comparison of Tools and Methodologies............................................................................14
4.0 Resource Estimation for Project..............................................................................................14
4.1 Resources Required.............................................................................................................14
4.2 Critical Path and Stress Points for Resources......................................................................15
4.3 Tools and Techniques Used.................................................................................................17
5.0 Conclusion...............................................................................................................................17
Bibliography..................................................................................................................................18

2PROJECT MANAGEMENT
1.0 Introduction
As per the requirements of the project, the three petrol tanks at the Western Australia site
have to be repaired and modified to reach the modern standards as well as stop affecting the
nearby environment negatively. In order to do this, the organization has proposed a new project
to be executed for the works on the tanks.
In this report, a basic plan for the project including budget, schedule and resources has
been developed with the most accurate estimations.
2.0 Project Budget Estimation
2.1 Overall Budget Estimation
Task Name Duration Cost
Repairing of Storage Tanks at
Western Australia Site
132 days $1,394,380.00
Project Survey and Initiation 22 days $95,600.00
Undertake Survey at the Site 3 days $8,400.00
Inspect Tank 1 2 days $5,600.00
Take Notes on Repair
Requirements
1 day $2,800.00
Inspect Tank 2 2 days $5,600.00
1.0 Introduction
As per the requirements of the project, the three petrol tanks at the Western Australia site
have to be repaired and modified to reach the modern standards as well as stop affecting the
nearby environment negatively. In order to do this, the organization has proposed a new project
to be executed for the works on the tanks.
In this report, a basic plan for the project including budget, schedule and resources has
been developed with the most accurate estimations.
2.0 Project Budget Estimation
2.1 Overall Budget Estimation
Task Name Duration Cost
Repairing of Storage Tanks at
Western Australia Site
132 days $1,394,380.00
Project Survey and Initiation 22 days $95,600.00
Undertake Survey at the Site 3 days $8,400.00
Inspect Tank 1 2 days $5,600.00
Take Notes on Repair
Requirements
1 day $2,800.00
Inspect Tank 2 2 days $5,600.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3PROJECT MANAGEMENT
Take Notes on Repair
Requirements
1 day $2,800.00
Inspect Tank 3 2 days $5,600.00
Take Notes on Repair
Requirements
1 day $2,800.00
Prepare Survey Report 3 days $3,600.00
Submit the Report for Analysis 1 day $1,200.00
Call Board Meeting 1 day $1,600.00
Discuss the Tank Issues 1 day $5,000.00
Discuss Other Issues Related to the
Tanks
1 day $5,000.00
Reach a Suitable Solution 1 day $5,000.00
Agree on a Project for Repair and
Upgrade of the Tanks
1 day $5,000.00
Analyze the Feasibility of the
Project
2 days $10,000.00
Analyze the Constraints of the 2 days $10,000.00
Take Notes on Repair
Requirements
1 day $2,800.00
Inspect Tank 3 2 days $5,600.00
Take Notes on Repair
Requirements
1 day $2,800.00
Prepare Survey Report 3 days $3,600.00
Submit the Report for Analysis 1 day $1,200.00
Call Board Meeting 1 day $1,600.00
Discuss the Tank Issues 1 day $5,000.00
Discuss Other Issues Related to the
Tanks
1 day $5,000.00
Reach a Suitable Solution 1 day $5,000.00
Agree on a Project for Repair and
Upgrade of the Tanks
1 day $5,000.00
Analyze the Feasibility of the
Project
2 days $10,000.00
Analyze the Constraints of the 2 days $10,000.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4PROJECT MANAGEMENT
Project
Prepare Project Proposal 5 days $13,000.00
Submit Proposal 1 day $2,600.00
Receive Approval for Project 0 days $0.00
Project Planning 29 days $47,960.00
Develop a Detailed Project Plan 5 days $8,000.00
Develop Project Charter 2 days $3,200.00
Develop Scope of Project 1 day $1,600.00
Develop the Budget and Schedule
of the Project
2 days $5,200.00
Determine Risks Associated with
the Project
5 days $6,000.00
Develop Risk Management Plan 2 days $2,400.00
Prepare Quality Management Plan 2 days $2,400.00
Release Tender for Project
Contract
2 days $1,600.00
Conduct Bidding Session 1 day $800.00
Project
Prepare Project Proposal 5 days $13,000.00
Submit Proposal 1 day $2,600.00
Receive Approval for Project 0 days $0.00
Project Planning 29 days $47,960.00
Develop a Detailed Project Plan 5 days $8,000.00
Develop Project Charter 2 days $3,200.00
Develop Scope of Project 1 day $1,600.00
Develop the Budget and Schedule
of the Project
2 days $5,200.00
Determine Risks Associated with
the Project
5 days $6,000.00
Develop Risk Management Plan 2 days $2,400.00
Prepare Quality Management Plan 2 days $2,400.00
Release Tender for Project
Contract
2 days $1,600.00
Conduct Bidding Session 1 day $800.00

5PROJECT MANAGEMENT
Select a Contractor for Project
Work
2 days $3,200.00
Discuss the Project with the
Contractor
2 days $7,840.00
Sign Contract 1 day $2,520.00
Hand Over Project Duty to
Contractor
2 days $3,200.00
Provide Approval to Contractor 0 days $0.00
Project Execution 70 days $1,230,820.00
Hire Workers for On Site Work 5 days $4,600.00
Hire Construction Vehicles 2 days $11,600.00
Procure Necessary Resources for
the Project Work
6 days $37,300.00
Proceed for Field Work of Project 1 day $920.00
Repair on Tank 1 30 days $247,600.00
Repair the Steel Patches 5 days $124,600.00
Install Steel Anchors 5 days $24,600.00
Repair Work on Entire Tank 10 days $49,200.00
Select a Contractor for Project
Work
2 days $3,200.00
Discuss the Project with the
Contractor
2 days $7,840.00
Sign Contract 1 day $2,520.00
Hand Over Project Duty to
Contractor
2 days $3,200.00
Provide Approval to Contractor 0 days $0.00
Project Execution 70 days $1,230,820.00
Hire Workers for On Site Work 5 days $4,600.00
Hire Construction Vehicles 2 days $11,600.00
Procure Necessary Resources for
the Project Work
6 days $37,300.00
Proceed for Field Work of Project 1 day $920.00
Repair on Tank 1 30 days $247,600.00
Repair the Steel Patches 5 days $124,600.00
Install Steel Anchors 5 days $24,600.00
Repair Work on Entire Tank 10 days $49,200.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6PROJECT MANAGEMENT
Including Top
Cleaning of the Tank 5 days $24,600.00
Repaint of the Tank 5 days $24,600.00
Repair on Tank 2 39 days $413,680.00
Repair the Steel Patches 5 days $205,600.00
Install Steel Anchors 7 days $42,840.00
Repair Work on Entire Tank
Including Top
13 days $79,560.00
Cleaning of the Tank 7 days $42,840.00
Repaint of the Tank 7 days $42,840.00
Repair on Tank 3 56 days $515,120.00
Repair the Steel Patches 6 days $189,120.00
Install Steel Anchors 10 days $65,200.00
Replacement of Main Supply
Valve
5 days $32,600.00
Repair Work on Entire Tank
Including Top
15 days $97,800.00
Including Top
Cleaning of the Tank 5 days $24,600.00
Repaint of the Tank 5 days $24,600.00
Repair on Tank 2 39 days $413,680.00
Repair the Steel Patches 5 days $205,600.00
Install Steel Anchors 7 days $42,840.00
Repair Work on Entire Tank
Including Top
13 days $79,560.00
Cleaning of the Tank 7 days $42,840.00
Repaint of the Tank 7 days $42,840.00
Repair on Tank 3 56 days $515,120.00
Repair the Steel Patches 6 days $189,120.00
Install Steel Anchors 10 days $65,200.00
Replacement of Main Supply
Valve
5 days $32,600.00
Repair Work on Entire Tank
Including Top
15 days $97,800.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT MANAGEMENT
Cleaning of the Tank 10 days $65,200.00
Repaint of the Tank 10 days $65,200.00
Project Hand Over 0 days $0.00
Project Closing 11 days $20,000.00
Review of Project Work 4 days $11,200.00
Finish Payments to Contractor and
Workers
2 days $2,800.00
Documentation of Project 5 days $6,000.00
Stakeholder Sign Off and Closing 0 days $0.00
2.2 Assumptions
The assumptions that have been made while developing this schedule are as follows.
 The determined costs for the materials are final and will not exceed the budget.
 The usages for the salaries of the stakeholders are based on 8 working hours per
day except Saturday and Sunday.
 The stakeholders do not need to perform overtime during the entire course of the
project.
 The determined duration of the project is accurate.
Cleaning of the Tank 10 days $65,200.00
Repaint of the Tank 10 days $65,200.00
Project Hand Over 0 days $0.00
Project Closing 11 days $20,000.00
Review of Project Work 4 days $11,200.00
Finish Payments to Contractor and
Workers
2 days $2,800.00
Documentation of Project 5 days $6,000.00
Stakeholder Sign Off and Closing 0 days $0.00
2.2 Assumptions
The assumptions that have been made while developing this schedule are as follows.
 The determined costs for the materials are final and will not exceed the budget.
 The usages for the salaries of the stakeholders are based on 8 working hours per
day except Saturday and Sunday.
 The stakeholders do not need to perform overtime during the entire course of the
project.
 The determined duration of the project is accurate.

8PROJECT MANAGEMENT
3.0 Project Schedule
3.1 Schedule
Task Name Duration Start Finish
Repairing of Storage Tanks at
Western Australia Site
132 days Fri 21-09-18 Mon 25-03-19
Project Survey and Initiation 22 days Fri 21-09-18 Mon 22-10-18
Undertake Survey at the Site 3 days Fri 21-09-18 Tue 25-09-18
Inspect Tank 1 2 days Wed 26-09-18 Thu 27-09-18
Take Notes on Repair
Requirements
1 day Fri 28-09-18 Fri 28-09-18
Inspect Tank 2 2 days Wed 26-09-18 Thu 27-09-18
Take Notes on Repair
Requirements
1 day Fri 28-09-18 Fri 28-09-18
Inspect Tank 3 2 days Wed 26-09-18 Thu 27-09-18
Take Notes on Repair
Requirements
1 day Fri 28-09-18 Fri 28-09-18
Prepare Survey Report 3 days Mon 01-10-18 Wed 03-10-18
Submit the Report for Analysis 1 day Thu 04-10-18 Thu 04-10-18
3.0 Project Schedule
3.1 Schedule
Task Name Duration Start Finish
Repairing of Storage Tanks at
Western Australia Site
132 days Fri 21-09-18 Mon 25-03-19
Project Survey and Initiation 22 days Fri 21-09-18 Mon 22-10-18
Undertake Survey at the Site 3 days Fri 21-09-18 Tue 25-09-18
Inspect Tank 1 2 days Wed 26-09-18 Thu 27-09-18
Take Notes on Repair
Requirements
1 day Fri 28-09-18 Fri 28-09-18
Inspect Tank 2 2 days Wed 26-09-18 Thu 27-09-18
Take Notes on Repair
Requirements
1 day Fri 28-09-18 Fri 28-09-18
Inspect Tank 3 2 days Wed 26-09-18 Thu 27-09-18
Take Notes on Repair
Requirements
1 day Fri 28-09-18 Fri 28-09-18
Prepare Survey Report 3 days Mon 01-10-18 Wed 03-10-18
Submit the Report for Analysis 1 day Thu 04-10-18 Thu 04-10-18
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9PROJECT MANAGEMENT
Call Board Meeting 1 day Fri 05-10-18 Fri 05-10-18
Discuss the Tank Issues 1 day Mon 08-10-18 Mon 08-10-18
Discuss Other Issues Related to
the Tanks
1 day Mon 08-10-18 Mon 08-10-18
Reach a Suitable Solution 1 day Mon 08-10-18 Mon 08-10-18
Agree on a Project for Repair
and Upgrade of the Tanks
1 day Mon 08-10-18 Mon 08-10-18
Analyze the Feasibility of the
Project
2 days Tue 09-10-18 Wed 10-10-18
Analyze the Constraints of the
Project
2 days Thu 11-10-18 Fri 12-10-18
Prepare Project Proposal 5 days Mon 15-10-18 Fri 19-10-18
Submit Proposal 1 day Mon 22-10-18 Mon 22-10-18
KEY MILESTONE 1: Receive
Approval for Project
0 days Mon 22-10-18 Mon 22-10-18
Project Planning 29 days Tue 23-10-18 Fri 30-11-18
Develop a Detailed Project Plan 5 days Tue 23-10-18 Mon 29-10-18
Call Board Meeting 1 day Fri 05-10-18 Fri 05-10-18
Discuss the Tank Issues 1 day Mon 08-10-18 Mon 08-10-18
Discuss Other Issues Related to
the Tanks
1 day Mon 08-10-18 Mon 08-10-18
Reach a Suitable Solution 1 day Mon 08-10-18 Mon 08-10-18
Agree on a Project for Repair
and Upgrade of the Tanks
1 day Mon 08-10-18 Mon 08-10-18
Analyze the Feasibility of the
Project
2 days Tue 09-10-18 Wed 10-10-18
Analyze the Constraints of the
Project
2 days Thu 11-10-18 Fri 12-10-18
Prepare Project Proposal 5 days Mon 15-10-18 Fri 19-10-18
Submit Proposal 1 day Mon 22-10-18 Mon 22-10-18
KEY MILESTONE 1: Receive
Approval for Project
0 days Mon 22-10-18 Mon 22-10-18
Project Planning 29 days Tue 23-10-18 Fri 30-11-18
Develop a Detailed Project Plan 5 days Tue 23-10-18 Mon 29-10-18
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10PROJECT MANAGEMENT
Develop Project Charter 2 days Tue 30-10-18 Wed 31-10-18
Develop Scope of Project 1 day Thu 01-11-18 Thu 01-11-18
Develop the Budget and
Schedule of the Project
2 days Fri 02-11-18 Mon 05-11-18
Determine Risks Associated
with the Project
5 days Tue 06-11-18 Mon 12-11-18
Develop Risk Management Plan 2 days Tue 13-11-18 Wed 14-11-18
Prepare Quality Management
Plan
2 days Thu 15-11-18 Fri 16-11-18
Release Tender for Project
Contract
2 days Mon 19-11-18 Tue 20-11-18
Conduct Bidding Session 1 day Wed 21-11-18 Wed 21-11-18
Select a Contractor for Project
Work
2 days Thu 22-11-18 Fri 23-11-18
Discuss the Project with the
Contractor
2 days Mon 26-11-18 Tue 27-11-18
Sign Contract 1 day Wed 28-11-18 Wed 28-11-18
Develop Project Charter 2 days Tue 30-10-18 Wed 31-10-18
Develop Scope of Project 1 day Thu 01-11-18 Thu 01-11-18
Develop the Budget and
Schedule of the Project
2 days Fri 02-11-18 Mon 05-11-18
Determine Risks Associated
with the Project
5 days Tue 06-11-18 Mon 12-11-18
Develop Risk Management Plan 2 days Tue 13-11-18 Wed 14-11-18
Prepare Quality Management
Plan
2 days Thu 15-11-18 Fri 16-11-18
Release Tender for Project
Contract
2 days Mon 19-11-18 Tue 20-11-18
Conduct Bidding Session 1 day Wed 21-11-18 Wed 21-11-18
Select a Contractor for Project
Work
2 days Thu 22-11-18 Fri 23-11-18
Discuss the Project with the
Contractor
2 days Mon 26-11-18 Tue 27-11-18
Sign Contract 1 day Wed 28-11-18 Wed 28-11-18

11PROJECT MANAGEMENT
Hand Over Project Duty to
Contractor
2 days Thu 29-11-18 Fri 30-11-18
KEY MILESTONE 2: Provide
Approval to Contractor
0 days Fri 30-11-18 Fri 30-11-18
Project Execution 70 days Mon 03-12-18 Fri 08-03-19
Hire Workers for On Site Work 5 days Mon 03-12-18 Fri 07-12-18
Hire Construction Vehicles 2 days Mon 10-12-18 Tue 11-12-18
Procure Necessary Resources
for the Project Work
6 days Wed 12-12-18 Wed 19-12-18
Proceed for Field Work of
Project
1 day Thu 20-12-18 Thu 20-12-18
Repair on Tank 1 30 days Fri 21-12-18 Thu 31-01-19
Repair the Steel Patches 5 days Fri 21-12-18 Thu 27-12-18
Install Steel Anchors 5 days Fri 28-12-18 Thu 03-01-19
Repair Work on Entire Tank
Including Top
10 days Fri 04-01-19 Thu 17-01-19
Cleaning of the Tank 5 days Fri 18-01-19 Thu 24-01-19
Repaint of the Tank 5 days Fri 25-01-19 Thu 31-01-19
Hand Over Project Duty to
Contractor
2 days Thu 29-11-18 Fri 30-11-18
KEY MILESTONE 2: Provide
Approval to Contractor
0 days Fri 30-11-18 Fri 30-11-18
Project Execution 70 days Mon 03-12-18 Fri 08-03-19
Hire Workers for On Site Work 5 days Mon 03-12-18 Fri 07-12-18
Hire Construction Vehicles 2 days Mon 10-12-18 Tue 11-12-18
Procure Necessary Resources
for the Project Work
6 days Wed 12-12-18 Wed 19-12-18
Proceed for Field Work of
Project
1 day Thu 20-12-18 Thu 20-12-18
Repair on Tank 1 30 days Fri 21-12-18 Thu 31-01-19
Repair the Steel Patches 5 days Fri 21-12-18 Thu 27-12-18
Install Steel Anchors 5 days Fri 28-12-18 Thu 03-01-19
Repair Work on Entire Tank
Including Top
10 days Fri 04-01-19 Thu 17-01-19
Cleaning of the Tank 5 days Fri 18-01-19 Thu 24-01-19
Repaint of the Tank 5 days Fri 25-01-19 Thu 31-01-19
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 20
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.