This project planning and budgeting assignment focuses on the construction of a bungalow, outlining project goals, objectives, and scope. It includes a detailed work breakdown structure (WBS) and a network diagram illustrating the execution phase. The project schedule, presented with a Gantt chart, outlines tasks, durations, start and finish dates, predecessors, resources, and costs. The project is divided into planning, preparation, execution, and review phases, with specific tasks such as site clearing, foundation laying, wall construction, and finishing touches. The budget is allocated across these tasks, providing a comprehensive financial overview. The project also includes risk management and stakeholder analysis. The assignment concludes with a review and closing phase, including payments, sign-off, and project closure, supported by a comprehensive bibliography.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running Head: PROJECT PLANNING AND BUDGETING
Project Planning and Budgeting
Name of the Student
Name of the University
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1PROJECT PLANNING AND BUDGETING
Project Goals and Objectives
The goal of the project is to construct a bungalow based on certain dimensional
specifications as well as certain parameters of project execution that have been already set.
Accordingly, the objectives of the project are as follows.
To analyze the bungalow specifications to determine whether the project is
feasible
To analyze the project plan specifications to determine whether the project is
feasible
To construct the bungalow based on the construction parameters as well as
predetermined project plan
Project Scope Statement
The scope of the project includes the construction of the bungalow for which,
dimensional and construction specifications have already been provided. Other scope items of
the project include:
Development of bungalow blueprint based on the specifications and parameters is
within the scope of the project.
Determination of resources required to construct the bungalow is within the scope
of the project.
Determination of human resources required for the construction of the bungalow
is within the scope of the project.
Preparation of overall structural design is within the scope of the project.
Document Page
2PROJECT PLANNING AND BUDGETING
Development of the structural framework of the bungalow is within the scope of
the project.
Development of the roof design and framework is within the scope of the project.
Execution of the construction within the predetermined project schedule is within
the scope of the project.
While these are the in scope items, there are also some out of scope items as well that
will be excluded from the project. These are listed as follows.
Construction license for the bungalow is not included within this project.
Procurement and sponsorship plan for the budget is not included within the
project.
Renting plan for the bungalow is not a part of this project.
Work Breakdown Structure (WBS)
The work breakdown structure is developed as follows.
Document Page
3PROJECT PLANNING AND BUDGETING
Figure 1: Work Breakdown Structure of the Project
(Source: Created by Author)
The network diagram of the execution phase of the project is developed as follows.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4PROJECT PLANNING AND BUDGETING
Figure 2: Network Diagram of the Execution Phase of the Project
(Source: Created by Author)
Project Schedule
The project schedule along with the budget is shown as follows.
Task Name Duration Start Finish Predecessors
Resource
Names
Cost
Construction of
Bungalow Project
251 days
Tue
11/6/18
Tue
10/22/19
$274, 800.00
Project
Planning Phase
26 days
Tue
11/6/18
Tue
12/11/18
$0.00
Conduct Team
Meeting
Regarding
1 wk Tue
11/6/18
Mon
11/12/18
$0.00
Document Page
5PROJECT PLANNING AND BUDGETING
Bungalow Project
Prepare
Proposal for the
Proposed Project
1 wk
Tue
11/13/18
Mon
11/19/18
2 $0.00
Develop an
Overall Project
Plan from the
Proposal
0.5 wks
Tue
11/20/18
Thu
11/22/18
3 $0.00
Conduct
Detailed Review
Meeting
Regarding the
Project Plan
1 wk
Thu
11/22/18
Thu
11/29/18
4 $0.00
Determine
Whether the
Project is Feasible
in Terms of
Economy and
Scope
0.5 wks
Thu
11/29/18
Mon
12/3/18
5 $0.00
Document Page
6PROJECT PLANNING AND BUDGETING
Finalize the
Project
1 wk
Tue
12/4/18
Mon
12/10/18
6 $0.00
Receive Green
Light to Go Ahead
1 day
Tue
12/11/18
Tue
12/11/18
7 $0.00
Project
Preparation and
Initiation Phase
35 days
Wed
12/12/18
Tue
1/29/19
$0.00
Determine
Project Scope and
Objectives
0.5 wks
Wed
12/12/18
Fri
12/14/18
8 $0.00
Determine
Assumptions and
Constraints
0.5 wks
Fri
12/14/18
Tue
12/18/18
10 $0.00
Prepare an
Accurate Budget
for the Project
0.5 wks
Wed
12/19/18
Fri
12/21/18
11 $0.00
Prepare a
Feasible Schedule
for the Project
0.5 wks
Fri
12/21/18
Tue
12/25/18
12 $0.00
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7PROJECT PLANNING AND BUDGETING
Prepare a List
of Resources
Required
1 wk
Wed
12/26/18
Tue 1/1/19 13 $0.00
Prepare a List
of Stakeholders
and Other Human
Resource
Requirements for
the Project
0.5 wks
Wed
1/2/19
Fri 1/4/19 14 $0.00
Complete the
Project Charter
0.5 wks Fri 1/4/19 Tue 1/8/19 15 $0.00
Prepare Risk
Matrix for
Identification of
the Major Risks
0.5 wks
Wed
1/9/19
Fri
1/11/19
16 $0.00
Prepare Risk
Management Plan
1.5 wks
Fri
1/11/19
Tue
1/22/19
17 $0.00
Proceed to the
Construction of
the Bungalow
1 wk
Wed
1/23/19
Tue
1/29/19
18 $0.00
Document Page
8PROJECT PLANNING AND BUDGETING
Project
Execution Phase
170 days
Wed
1/30/19
Tue
9/24/19
$274, 800.00
Clear Ground 2 wks
Wed
1/30/19
Tue
2/12/19
19
Laborer 1,
Laborer 2,
Laborer 3,
Laborer 4,
Laborer 5,
Laborer 6
$14, 400.00
Lay
Foundations
3 wks
Wed
2/13/19
Tue 3/5/19 21
Laborer 1,
Laborer 2,
Laborer 3,
Laborer 4,
Tradesman 1,
Tradesman 2
$25, 200.00
Build Dwarf
Walls
2 wks
Wed
3/6/19
Tue
3/19/19
22
Laborer 1,
Laborer 2,
Tradesman 1,
Tradesman 2,
Tradesman 3,
Tradesman 4
$19, 200.00
Oversite
Concrete
1 wk Wed
3/6/19
Tue
3/12/19
22 Laborer 1,
Laborer 2,
$4, 800.00
Document Page
9PROJECT PLANNING AND BUDGETING
Laborer 3,
Laborer 4
Floor Joists 2 wks
Wed
3/20/19
Tue 4/2/19 23, 24
Tradesman 3,
Tradesman 4
$7, 200.00
Main Walls 5 wks
Wed
4/3/19
Tue 5/7/19 25
Laborer 5,
Laborer 6,
Tradesman 1,
Tradesman 2,
Tradesman 3,
Tradesman 4
$48, 000.00
Door and
Window Frames
3 wks
Wed
4/3/19
Tue
4/23/19
25
Tradesman 1,
Tradesman 2
$10, 800.00
Ceiling Joists 2 wks
Wed
5/8/19
Tue
5/21/19
26, 27
Tradesman 3,
Tradesman 4
$7, 200.00
Roof Timbers 6 wks
Wed
5/8/19
Tue
6/18/19
26, 27
Tradesman 1,
Tradesman 2
$21, 600.00
Tiles 2 wks Wed
6/19/19
Tue 7/2/19 28, 29 Laborer 1,
Laborer 2,
Tradesman 1,
Tradesman 2,
$15, 600.00
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10PROJECT PLANNING AND BUDGETING
Tradesman 3
Floorboards 3 wks
Wed
6/19/19
Tue 7/9/19 28, 29
Tradesman 1,
Tradesman 2
$10, 800.00
Ceiling Boards 2 wks
Wed
7/10/19
Tue
7/23/19
30, 31
Tradesman 3,
Tradesman 4
$7, 200.00
Skirtings 1 wk
Wed
7/10/19
Tue
7/16/19
30, 31
Tradesman 1,
Tradesman 3
$3, 600.00
Glazing 2 wks
Wed
7/24/19
Tue 8/6/19 32, 33
Tradesman 2,
Tradesman 4
$7, 200.00
Plastering 2 wks
Wed
8/7/19
Tue
8/20/19
34
Laborer 2,
Tradesman 2,
Tradesman 3,
Tradesman 4
$13, 200.00
Electrics 3 wks
Wed
8/7/19
Tue
8/27/19
34
Tradesman 1,
Tradesman 4
$10, 800.00
Plubming and
Heating
4 wks
Wed
8/7/19
Tue 9/3/19 34
Laborer 3,
Tradesman 2,
Tradesman 3,
Tradesman 4
$26, 400.00
Painting 3 wks Wed Tue 35, 36, 37 Tradesman 1, $21, 600.00
Document Page
11PROJECT PLANNING AND BUDGETING
9/4/19 9/24/19
Tradesman 2,
Tradesman 3,
Tradesman 4
Project Review
and Closing
Phase
20 days
Wed
9/25/19
Tue
10/22/19
$0.00
Conduct
Review and
Appraisal of the
Project
2 wks
Wed
9/25/19
Tue
10/8/19
38 $0.00
Make All the
Payments and
Wages
1 wk
Wed
10/9/19
Tue
10/15/19
40 $0.00
Sign Off 0.9 wks
Wed
10/16/19
Tue
10/22/19
41 $0.00
Close the
Project
0.1 wks
Tue
10/22/19
Tue
10/22/19
42 $0.00
chevron_up_icon
1 out of 12
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]