Hafod Eryri Project: Gantt Chart, WBS, and Budget Analysis

Verified

Added on  2022/09/07

|13
|989
|17
Project
AI Summary
This project management assignment analyzes the Hafod Eryri project, covering various aspects of project planning and execution. It begins with the calculation of weighted expected time durations for different activities and uses this data to create a Gantt chart and a Work Breakdown Structure (WBS). The assignment then reflects dependencies between tasks and assigns resources, materials, and facilities. A critical path analysis is performed, and methods for resolving resource overload are presented. The assignment also includes a detailed budget breakdown, including total costs and a cash flow analysis. The document incorporates figures illustrating the Gantt chart, WBS, dependencies, resource allocation, critical path, resource leveling, and cash flow. A bibliography of relevant project management literature is also included.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: PROJECT MANAGEMENT
Project management
Name of the Student
Name of the University
Author’s Note
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1
PROJECT MANAGEMENT
Table of Contents
1. Gantt chart and WBS as per weighted expected time duration..................................................2
1.1 Calculation of time................................................................................................................2
1.2 Gantt chart.............................................................................................................................3
1.3 WBS.......................................................................................................................................4
2. Reflecting dependencies..............................................................................................................5
3. Assigning resources, materials and facilities...............................................................................6
4. Critical path.................................................................................................................................7
5. Resolving resource overload........................................................................................................8
6. Budget..........................................................................................................................................8
6.1 Total budget...........................................................................................................................8
6.2 Cashflow..............................................................................................................................11
Bibliography..................................................................................................................................12
Document Page
2
PROJECT MANAGEMENT
1. Gantt chart and WBS as per weighted expected time duration
1.1 Calculation of time
Activity
Optimist
ic
Pessimisti
c
Most
likely
Weighted expected time
duration
Steel framework design 13 19 16 17.5
Detail design 20 30 25 27.5
Material procurement 9 12 9.75 11.1
Steel fabrication 18 28 22 25.3
Sub-assembly batching for
shipment 14 17 13 15.8
Road transport to railhead 2 8 5 6.5
Rail transport to site 2.5 5 3.75 4.4
Steel structure erection 3 7 6 6.2
Structural steel snagging 1 6 2 4.5
Framework inspection 2 2 2 2
Steel roof design 10 18 14 16.0
Detail design 22 27 24.5 25.8
Test section procurement 5.4 11.4 8.4 9.9
Test section build 4 6 5 5.5
Roof testing 1 3 2 2.5
Roof design updates 6 8 7 7.5
Material procurement 7.5 12.75 8.55 11.2
Roof section fabrication 18 20 19 19.5
Sub-assembly batching for
shipment 7 16 9 13.3
Road transport to railhead 3 6 4.5 5.3
Rail transport to site 4 8 6 7
Roof build 5 10 7 8.7
Roof structure snagging 1 4 2 3.2
Framework inspection 1 4 2.5 3.3
Document Page
3
PROJECT MANAGEMENT
1.2 Gantt chart
Figure 1: Gantt chart
(Source: Created by Author)
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4
PROJECT MANAGEMENT
1.3 WBS
0
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
2.11
2.12
2.13
2.14
Hafod Eryri Project
£ 935,410.80 8,302.4 hours
Building structure
£ 282,388.00 3,320.8 hours
Steel framework design
£ 31,780.00 420 hours
Detail design
£ 36,960.00 660 hours
Material procurement
£ 103,296.00 0 hours
Steel fabrication
£ 48,576.00 1,214.4 hours
Sub-assembly batching
for shipment
£ 10,112.00 252.8 hours
Road transport to
railhead
£ 17,660.00 104 hours
Rail transport to site
£ 9,500.00 0 hours
Steel structure erection
£ 19,344.00 545.6 hours
Structural steel snagging
£ 3,960.00 108 hours
Framework inspection
£ 1,200.00 16 hours
Roof structure
£ 653,022.80 4,981.6 hours
Steel roof design
£ 45,696.00 640 hours
Detail design
£ 69,350.40 1,238.4 hours
Test section procurement
£ 15,463.60 79.2 hours
Test section build
£ 3,520.00 88 hours
Roof testing
£ 2,900.00 60 hours
Roof design updates
£ 7,260.00 120 hours
Material procurement
£ 209,396.80 89.6 hours
Roof section fabrication
£ 62,400.00 1,560 hours
Sub-assembly batching
for shipment
£ 12,768.00 319.2 hours
Road transport to
railhead
£ 16,892.00 84.8 hours
Rail transport to site
£ 10,180.00 112 hours
Roof build
£ 17,400.00 487.2 hours
Roof structure snagging
£ 2,816.00 76.8 hours
Framework inspection
£ 176,980.00 26.4 hours
Figure 2: Work breakdown structure
(Source: Created by Author)
Document Page
5
PROJECT MANAGEMENT
2. Reflecting dependencies
Figure 3: Reflecting dependencies
(Source: Created by Author)
Document Page
6
PROJECT MANAGEMENT
3. Assigning resources, materials and facilities
Figure 4: Assigning resources, materials and facilities
(Source: Created by Author)
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
PROJECT MANAGEMENT
4. Critical path
Figure 5: Critical path
(Source: Created by Author)
Document Page
8
PROJECT MANAGEMENT
5. Resolving resource overload
Figure 6: Resource levelling
(Source: Created by Author)
6. Budget
6.1 Total budget
WBS Task Name Duration Start Finish Predecessors Cost
0 Hafod Eryri
Project 175.3 days
Mon
23-10-
06
Mon
25-06-
07
£ 935,410.80
1 Building
structure 68 days
Mon
23-10-
06
Wed
24-01-
07
£ 282,388.00
1.1 Steel
framework design 17.5 days Mon 23-
10-06
Wed 15-
11-06 £ 31,780.00
1.2 Detail design 27.5 days Wed 15- Fri 22- 2 £ 36,960.00
Document Page
9
PROJECT MANAGEMENT
11-06 12-06
1.3 Material
procurement 11.1 days Wed 15-
11-06
Thu 30-
11-06 2 £ 103,296.00
1.4 Steel
fabrication 25.3 days Thu 30-
11-06
Thu 04-
01-07 4 £ 48,576.00
1.5
Sub-assembly
batching for
shipment
15.8 days Thu 30-
11-06
Fri 22-
12-06 4 £ 10,112.00
1.6 Road transport
to railhead 6.5 days Fri 22-
12-06
Mon 01-
01-07 6 £ 17,660.00
1.7 Rail transport to
site 4.4 days Mon 01-
01-07
Mon 08-
01-07 7 £ 9,500.00
1.8 Steel structure
erection 6.2 days Mon 08-
01-07
Tue 16-
01-07 8 £ 19,344.00
1.9 Structural steel
snagging 4.5 days Tue 16-
01-07
Mon 22-
01-07 9 £ 3,960.00
1.10 Framework
inspection 2 days Tue 23-
01-07
Wed 24-
01-07 10 £ 1,200.00
2 Roof structure 107.3 days Thu 25-
01-07
Mon
25-06-
07
£ 653,022.80
2.1 Steel roof
design 16 days Thu 25-
01-07
Thu 15-
02-07 11 £ 45,696.00
2.2 Detail design 25.8 days Thu 25-
01-07
Thu 01-
03-07 11 £ 69,350.40
2.3 Test section
procurement 9.9 days Thu 01-
03-07
Thu 15-
03-07 14 £ 15,463.60
2.4 Test section
build 5.5 days Thu 01-
03-07
Fri 09-
03-07 14 £ 3,520.00
2.5 Roof testing 2.5 days Thu 01- Tue 06- 14 £ 2,900.00
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10
PROJECT MANAGEMENT
03-07 03-07
2.6 Roof design
updates 7.5 days Tue 06-
03-07
Thu 15-
03-07 17 £ 7,260.00
2.7 Material
procurement 11.2 days Thu 15-
03-07
Fri 30-
03-07 18 £ 209,396.80
2.8 Roof section
fabrication 19.5 days Mon 02-
04-07
Fri 27-
04-07 19 £ 62,400.00
2.9
Sub-assembly
batching for
shipment
13.3 days Fri 27-
04-07
Wed 16-
05-07 20 £ 12,768.00
2.10 Road transport
to railhead 5.3 days Wed 16-
05-07
Thu 24-
05-07 21 £ 16,892.00
2.11 Rail transport
to site 7 days Thu 24-
05-07
Mon 04-
06-07 22 £ 10,180.00
2.12 Roof build 8.7 days Mon 04-
06-07
Thu 14-
06-07 23 £ 17,400.00
2.13 Roof structure
snagging 3.2 days Thu 14-
06-07
Tue 19-
06-07 24 £ 2,816.00
2.14 Framework
inspection 3.3 days Wed 20-
06-07
Mon 25-
06-07 25 £ 176,980.00
Document Page
11
PROJECT MANAGEMENT
6.2 Cashflow
October
2006
November
2006
December
2006
January
2007
February
2007
March
2007
April
2007
May 2007 June 2007
£ 0.00
£ 100,000.00
£ 200,000.00
£ 300,000.00
£ 400,000.00
£ 500,000.00
£ 600,000.00
£ 700,000.00
£ 800,000.00
£ 900,000.00
£ 1,000,000.00
Cash Flow
Cumulative Cost
Figure 7: Cash Flow
(Source: Created by Author)
Document Page
12
PROJECT MANAGEMENT
Bibliography
Badewi, A., 2016. The impact of project management (PM) and benefits management (BM)
practices on project success: Towards developing a project benefits governance
framework. International Journal of Project Management, 34(4), pp.761-778.
De Carvalho, M.M., Patah, L.A. and de Souza Bido, D., 2015. Project management and its
effects on project success: Cross-country and cross-industry comparisons. International Journal
of Project Management, 33(7), pp.1509-1522.
Hornstein, H.A., 2015. The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2), pp.291-
298.
Joslin, R. and Müller, R., 2015. Relationships between a project management methodology and
project success in different project governance contexts. International Journal of Project
Management, 33(6), pp.1377-1392.
Papke-Shields, K.E. and Boyer-Wright, K.M., 2017. Strategic planning characteristics applied to
project management. International Journal of Project Management, 35(2), pp.169-179.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), pp.278-290.
chevron_up_icon
1 out of 13
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]