This project management assignment provides a comprehensive overview of project management techniques. The assignment begins with a detailed planning phase, including optimizing time and resources, determining project duration and cost, identifying the critical path and activities, and outlining resource allocation. A Gantt chart is used to visually represent the project timeline. The second part focuses on tracking and execution, presenting the current status of the project and demonstrating progress with an updated Gantt chart. Variance tables for both time and cost are included to analyze deviations from the initial plan. The assignment covers construction project, detailing tasks, resources, and costs associated with the project. The document utilizes Gantt charts, variance tables, and critical path analysis to illustrate project progress and identify areas for improvement. The report concludes with a bibliography of relevant project management resources.
Document Page
Running head: PROJECT MANAGEMENT
Project management techniques
Name of the Student
Name of the University
Author’s Note
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1
PROJECT MANAGEMENT
Table of Contents
1. Planning.......................................................................................................................................2
1.1 Optimization of time and resources.......................................................................................2
1.2 Duration and cost of the entire project and critical path as well as activities........................2
1.2.1 Duration of the project....................................................................................................2
1.2.2 Cost of the project...........................................................................................................3
1.2.3 Critical path....................................................................................................................3
1.2.4 Critical activities.............................................................................................................4
1.3 Resources and their numbers for this project as per the plan................................................6
1.4 Gantt chart.............................................................................................................................7
2. Tracking and execution................................................................................................................8
2.1 Current status of the project...................................................................................................8
2.2 Gantt chart showing progress................................................................................................8
2.3 Variances tables for time and cost.........................................................................................9
2.3.1 Variance table for time...................................................................................................9
2.3.2 Variance table for cost..................................................................................................11
Bibliography..................................................................................................................................14
Document Page
2
PROJECT MANAGEMENT
1. Planning
1.1 Optimization of time and resources
The procedures through which time and resources are optimized include:
Using mixed strategy: Mixed strategy is utilized by the project for optimizing both time
as well as resources of the project. It is identified that in the plan as well as lock up phase, both
the units are build together thus it assists in optimizing time as well as resources of the project.
Proper tracking: Proper track must be kept on the project so that the entire project can
be completed successfully within the estimated time and budget without creating any challenges.
Proper management: It is quite important to manage both the resources as well as time
of the project so that the entire project can be completed successfully within the estimated time
and budget by optimizing the utilization of resources and time
Training to the workers: The workers are trained so that they are capable of working
efficiently in completing the construction related tasks of the project properly.
1.2 Duration and cost of the entire project and critical path as well as activities
1.2.1 Duration of the project
The entire duration that is required for completing the entire project successfully is
around 156 days. It is estimated that in 156 days both the units are constructed successfully. If
the project managers are not able to complete the project then the project faces number of issues
as well as challenges.
Document Page
3
PROJECT MANAGEMENT
1.2.2 Cost of the project
The entire cost that is estimated for completing the project is around $71,696. The project
must be completed within this budget. If the project managers are unable to complete the project
on this budget then they will face financial crisis.
1.2.3 Critical path
Figure 1: Critical path
(Source: Created by Author)
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4
PROJECT MANAGEMENT
1.2.4 Critical activities
The critical activities of the project include:
Task Name
Construction of units
Plans and Site
Creation of site plan for unit 1
Creation of site plan for unit 2
Council permitance arrangement for unit 2
Preparation of site for unit 2
organizing materials for unit 2
Laying foundations for unit 2
Plumbing for unit 2
Pouring slab for unit 2
To lock up
Erection of frame for unit 2
Roofing for unit 2
Development of brick wall for unit 2
Doors and windows fittings for unit 2
Fit out
Implementation of electrical cables for unit 1
Plumbing for unit 1
Wall plaster for unit 1
Document Page
5
PROJECT MANAGEMENT
Fitting doors for unit 1
Kitchen development for unit 1
Bathroom installation for unit1
Electrical fitting for unit 1
Final fittings of plumbing for unit 1
Paint for unit 1
Approval of council for unit 1
Implementation of electrical cables for unit 2
Plumbing for unit 2
Wall plaster for unit 2
Fitting doors for unit 2
Kitchen development for unit 2
Bathroom installation for unit2
Electrical fitting for unit 2
Final fittings of plumbing for unit 2
Paint for unit 2
Approval of council for unit 2
1.3 Resources and their numbers for this project as per the plan
The resources that are required in the project for completing the project successfully are
as follows:
Resources Number
Document Page
6
PROJECT MANAGEMENT
Draftsperson 10
Electrician 9
Plumber 12
Concreter 10
Carpenter 8
Laborer 25
Painter 12
Supervisor 2
Cabinet Maker 8
Roof Tier 8
Bricklayer 8
Plasterer 12
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
PROJECT MANAGEMENT
1.4 Gantt chart
Figure 2: Gantt chart
(Source: Created by Author)
Document Page
8
PROJECT MANAGEMENT
2. Tracking and execution
2.1 Current status of the project
It is identified that currently the unit 1 is in the “Fit Out” phase and is completing the
activity of plastering walls whereas unit 2 is completed up to “lock up” phase. The technique of
tracking is utilized with the help of the Gantt chart is order to keep track on the project activities.
It is identified that mixed strategy is used in both “plan and site” and “lock up phase” in order to
complete the work activities of both the phase properly.
2.2 Gantt chart showing progress
Figure 3: Tracking Gantt chart
(Source: Created by Author)
Document Page
9
PROJECT MANAGEMENT
2.3 Variances tables for time and cost
2.3.1 Variance table for time
Task Name Duration Start Finish
Construction of units 156 days
Thu
10/12/17
Thu 5/17/18
Plans and Site 23 days
Thu
10/12/17
Mon 11/13/17
Creation of site plan for unit 1 3 days
Thu
10/12/17
Mon 10/16/17
Creation of site plan for unit 2 3 days
Tue
10/17/17
Thu 10/19/17
Council permitance arrangement
for unit 1
4 days
Fri
10/20/17
Wed 10/25/17
Council permitance arrangement
for unit 2
4 days
Fri
10/20/17
Wed 10/25/17
Preparation of site for unit 1 2 days
Thu
10/26/17
Fri 10/27/17
Preparation of site for unit 2 2 days
Thu
10/26/17
Fri 10/27/17
Organizing materials for unit 1 4 days
Mon
10/30/17
Thu 11/2/17
organizing materials for unit 2 4 days Mon Thu 11/2/17
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10
PROJECT MANAGEMENT
10/30/17
Laying foundations for unit 1 3 days Fri 11/3/17 Tue 11/7/17
Laying foundations for unit 2 3 days Fri 11/3/17 Tue 11/7/17
Plumbing for unit 1 2 days
Wed
11/8/17
Thu 11/9/17
Plumbing for unit 2 2 days
Wed
11/8/17
Thu 11/9/17
Pouring slab for unit 1 2 days
Fri
11/10/17
Mon 11/13/17
Pouring slab for unit 2 2 days
Fri
11/10/17
Mon 11/13/17
To lock up 15 days
Tue
11/14/17
Mon 12/4/17
Erection of frame for unit 1 3 days
Tue
11/14/17
Thu 11/16/17
Erection of frame for unit 2 3 days
Tue
11/14/17
Thu 11/16/17
Roofing for unit 1 4 days
Fri
11/17/17
Wed 11/22/17
Roofing for unit 2 4 days
Fri
11/17/17
Wed 11/22/17
Document Page
11
PROJECT MANAGEMENT
Development of brick wall for unit
1
5 days
Thu
11/23/17
Wed 11/29/17
Development of brick wall for unit
2
5 days
Thu
11/23/17
Wed 11/29/17
Doors and windows fitting for unit
1
3 days
Thu
11/30/17
Mon 12/4/17
Doors and windows fittings for unit
2
3 days
Thu
11/30/17
Mon 12/4/17
Fit out 118 days
Tue
12/5/17
Thu 5/17/18
Implementation of electrical cables
for unit 1
10 days Tue 12/5/17 Mon 12/18/17
Plumbing for unit 1 12 days
Tue
12/19/17
Wed 1/3/18
Wall plaster for unit 1 13 days Thu 1/4/18 Mon 1/22/18
Fitting doors for unit 1 14 days Tue 1/23/18 Fri 2/9/18
Kitchen development for unit 1 15 days
Mon
2/12/18
Fri 3/2/18
Bathroom installation for unit1 12 days Mon 3/5/18 Tue 3/20/18
Electrical fitting for unit 1 11 days
Wed
3/21/18
Wed 4/4/18
Final fittings of plumbing for unit 1 10 days Thu 4/5/18 Wed 4/18/18