ITP-4 Project - Adding Resources to WBS: Mamma's Bakery Expansion
VerifiedAdded on 2022/08/13
|14
|1388
|48
Project
AI Summary
This project report details the process of adding resources to a Work Breakdown Structure (WBS) within the context of the Mamma's Bakery expansion project. The assignment begins with an overview of the project's background and the resources considered, which are categorized into work and material resources. The core of the report focuses on resource allocation, presenting a table that maps resources to specific tasks and subtasks. The report then addresses the issue of resource over allocation, illustrating it with a Gantt chart and explaining the methods used to solve this problem. The solution involves freeing resources from summary tasks to ensure that each resource works for a maximum of 8 hours per day. The report concludes with a summary of the resource needs and the successful resolution of the over allocation problem. The appendix includes the MS Project file used for the analysis.

Running head: PM
Adding Resources to WBS- Part 1
Name of Student
Name of University
Author Note
Adding Resources to WBS- Part 1
Name of Student
Name of University
Author Note
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1
PM
Table of Contents
Background..........................................................................................................................2
Resource Considered...........................................................................................................2
Resource Allocation.............................................................................................................3
Resource Over allocation.....................................................................................................5
Solving Resource Over allocation.......................................................................................9
Conclusion.........................................................................................................................11
Bibliography......................................................................................................................12
Appendix (MS Project File)...............................................................................................13
PM
Table of Contents
Background..........................................................................................................................2
Resource Considered...........................................................................................................2
Resource Allocation.............................................................................................................3
Resource Over allocation.....................................................................................................5
Solving Resource Over allocation.......................................................................................9
Conclusion.........................................................................................................................11
Bibliography......................................................................................................................12
Appendix (MS Project File)...............................................................................................13

2
PM
Background
The undertaken project aims in expansion of Mamma’s Bakery. As a part of the initial
project plan, a detailed work break down structure has already been prepared. The next is to
schedule the project and add resources to the task. The report provides an overview of the
resources allocated for each task. The resources are allocated on basis of the task requirement
and the time each resource will be working.
Resource Considered
The resources considered for the chosen project are indicated in the following figure-
PM
Background
The undertaken project aims in expansion of Mamma’s Bakery. As a part of the initial
project plan, a detailed work break down structure has already been prepared. The next is to
schedule the project and add resources to the task. The report provides an overview of the
resources allocated for each task. The resources are allocated on basis of the task requirement
and the time each resource will be working.
Resource Considered
The resources considered for the chosen project are indicated in the following figure-
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3
PM
Figure 1: Illustrating the Resources considered for the Chosen Project
(Source: Generated from MS Project)
In the above figure, the resources are segregated into work and material. The material
column indicates the materials needed for successful execution of the undertaken project. The
other resources are the labors considered for the task. Few of the resources are allocated at 50%
as they will not be working for 8 hours.
Resource Allocation
The resources are allocated to each of the tasks and sub tasks. The following table
represents the resource allocation
Task Name Resource Names
Mammas Bakery Expansion
Momma's Bakery Project
IT System Design Software Engineer
Interview Stakeholders Project Manager [50%]
Identify Project Scope Assistant Project Manager
Create Project Schedule Assistant Project Manager
Stakeholders agree with the project’s
deliverables, resources, and schedule Stakeholders[50%]
Stakeholder signs approval Stakeholders[50%]
Select team members Assistant Resource Manager [50%]
Assign roles Assistant Project Manager ,Resource Manager
Define the current structure of the shop Assistant System Engineer [50%]
Define the target structure of the shop Assistant System Engineer [50%]
Develop hardware list Assistant Technical Expert [50%]
Develop hardware list Assistant Technical Expert [50%]
Divide different requirements into
phases of order to be completed Project Manager [50%]
Research possible solutions for the
requirements System Engineer
Create documentation for entire
system and installation Document Writer[50%]
Review and finalize documentation Project Manager [50%]
System Hardware Network Engineer
PM
Figure 1: Illustrating the Resources considered for the Chosen Project
(Source: Generated from MS Project)
In the above figure, the resources are segregated into work and material. The material
column indicates the materials needed for successful execution of the undertaken project. The
other resources are the labors considered for the task. Few of the resources are allocated at 50%
as they will not be working for 8 hours.
Resource Allocation
The resources are allocated to each of the tasks and sub tasks. The following table
represents the resource allocation
Task Name Resource Names
Mammas Bakery Expansion
Momma's Bakery Project
IT System Design Software Engineer
Interview Stakeholders Project Manager [50%]
Identify Project Scope Assistant Project Manager
Create Project Schedule Assistant Project Manager
Stakeholders agree with the project’s
deliverables, resources, and schedule Stakeholders[50%]
Stakeholder signs approval Stakeholders[50%]
Select team members Assistant Resource Manager [50%]
Assign roles Assistant Project Manager ,Resource Manager
Define the current structure of the shop Assistant System Engineer [50%]
Define the target structure of the shop Assistant System Engineer [50%]
Develop hardware list Assistant Technical Expert [50%]
Develop hardware list Assistant Technical Expert [50%]
Divide different requirements into
phases of order to be completed Project Manager [50%]
Research possible solutions for the
requirements System Engineer
Create documentation for entire
system and installation Document Writer[50%]
Review and finalize documentation Project Manager [50%]
System Hardware Network Engineer
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4
PM
Order two Macbooks Assistant System Engineer [50%]
Oder POS system Assistant System Engineer [50%]
Install hardware based on vendor
instructions Hardware '[1],IT Staff 1,Software [1]
Ensure hardware is being installed in
designated location based on documentation System Engineer
Test hardware to work as specified System Tester
System Software Software Engineer
Purchase Accounting software Accounting Software [1],IT staff 3
Purchase Inventory software Inventory Software [1],IT Staff 2
Install accounting software on the
owner’s MacBook IT Staff 2,Mac Book [1]
Install inventory software on the
owner’s MacBook Labour 2,Assistant Technical Expert [50%]
Install accounting software on the
bookkeeper's MacBook IT Staff 1,Assistant Technical Expert [50%]
System Networking Network Engineer
Obtain network infrastructure Assistant Network Engineer[50%]
Estimate the shop’s Internet usage Assistant Network Engineer[50%]
Order network hardware Assistant Network Engineer[50%],Labour 1
Set up network hardware IT staff 3,Labour 2,Assistant Network Engineer[50%]
Provide Internet
Choose an IPS Assistant Technical Expert [50%]
Sign contract with the chosen IPS Assistant System Engineer [50%]
Cable network Cable Cost [1],Labour 2,Assistant Network Engineer[50%]
Design website
Create a mind map. IT staff 3
Build online ordering function
Add Menu Items Assistant Technical Expert [50%]
Add Contact Information Assistant Software Engineer[50%]
Create visual web designs.
Add Photos Assistant Software Engineer[50%]
Launch Website
Transfer website file to the web host System Engineer
Test website System Tester
Use website analytics to keep track
with the site’s status Assistant Software Engineer[50%]
System Test
Create Test Plan Assistant Software Engineer[50%]
Verify the Website is working as
intended IT Staff 2,System Engineer
Verify the payment system though the
website IT Staff 1,Assistant Software Engineer[50%]
Proceed with Stress testing after
Verification System Engineer ,System Tester
PM
Order two Macbooks Assistant System Engineer [50%]
Oder POS system Assistant System Engineer [50%]
Install hardware based on vendor
instructions Hardware '[1],IT Staff 1,Software [1]
Ensure hardware is being installed in
designated location based on documentation System Engineer
Test hardware to work as specified System Tester
System Software Software Engineer
Purchase Accounting software Accounting Software [1],IT staff 3
Purchase Inventory software Inventory Software [1],IT Staff 2
Install accounting software on the
owner’s MacBook IT Staff 2,Mac Book [1]
Install inventory software on the
owner’s MacBook Labour 2,Assistant Technical Expert [50%]
Install accounting software on the
bookkeeper's MacBook IT Staff 1,Assistant Technical Expert [50%]
System Networking Network Engineer
Obtain network infrastructure Assistant Network Engineer[50%]
Estimate the shop’s Internet usage Assistant Network Engineer[50%]
Order network hardware Assistant Network Engineer[50%],Labour 1
Set up network hardware IT staff 3,Labour 2,Assistant Network Engineer[50%]
Provide Internet
Choose an IPS Assistant Technical Expert [50%]
Sign contract with the chosen IPS Assistant System Engineer [50%]
Cable network Cable Cost [1],Labour 2,Assistant Network Engineer[50%]
Design website
Create a mind map. IT staff 3
Build online ordering function
Add Menu Items Assistant Technical Expert [50%]
Add Contact Information Assistant Software Engineer[50%]
Create visual web designs.
Add Photos Assistant Software Engineer[50%]
Launch Website
Transfer website file to the web host System Engineer
Test website System Tester
Use website analytics to keep track
with the site’s status Assistant Software Engineer[50%]
System Test
Create Test Plan Assistant Software Engineer[50%]
Verify the Website is working as
intended IT Staff 2,System Engineer
Verify the payment system though the
website IT Staff 1,Assistant Software Engineer[50%]
Proceed with Stress testing after
Verification System Engineer ,System Tester

5
PM
Verify database is connected Assistant System Engineer [50%],Assistant Software
Engineer[50%]
Verify Accounting system is
connected Assistant System Engineer [50%],System Engineer
Verify inventory system is connected Assistant System Engineer [50%]
Proceed with Stress testing after
Verification IT staff 3,System Tester
Project Management Project Manager [50%]
Conduct stakeholder workshop Assistant Project Manager ,Stakeholders[50%]
All hands weekly in-house meeting
once a week Project Manager [50%]
Bi-weekly conference calls with the
customer Assistant Project Manager
System Transition System Engineer
Monitor system Assistant System Engineer [50%],Assistant Technical
Expert [50%]
Provide system support System Engineer
Training
Train users on IT system Trainer ,Training Modules [1]
Train users on website Trainer
Finish project Project Manager [50%]
Review contract Project Manager [50%]
Stakeholders sign off for project close Stakeholders[50%]
Hand over final documentation Assistant Project Manager
Conduct performance review Project Manager [50%]
Table 1: Showing Resource Allocation
Resource Over allocation
The table 1 illustrates the allocation of resources to specific task. However, the allocation
of the resources in that manner has resulted in over allocation of certain resources that are needed
to be solved.
PM
Verify database is connected Assistant System Engineer [50%],Assistant Software
Engineer[50%]
Verify Accounting system is
connected Assistant System Engineer [50%],System Engineer
Verify inventory system is connected Assistant System Engineer [50%]
Proceed with Stress testing after
Verification IT staff 3,System Tester
Project Management Project Manager [50%]
Conduct stakeholder workshop Assistant Project Manager ,Stakeholders[50%]
All hands weekly in-house meeting
once a week Project Manager [50%]
Bi-weekly conference calls with the
customer Assistant Project Manager
System Transition System Engineer
Monitor system Assistant System Engineer [50%],Assistant Technical
Expert [50%]
Provide system support System Engineer
Training
Train users on IT system Trainer ,Training Modules [1]
Train users on website Trainer
Finish project Project Manager [50%]
Review contract Project Manager [50%]
Stakeholders sign off for project close Stakeholders[50%]
Hand over final documentation Assistant Project Manager
Conduct performance review Project Manager [50%]
Table 1: Showing Resource Allocation
Resource Over allocation
The table 1 illustrates the allocation of resources to specific task. However, the allocation
of the resources in that manner has resulted in over allocation of certain resources that are needed
to be solved.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6
PM
PM
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7
PM
Figure 2: Showing the Resource Graph and over allocated Resources
The following Gantt chart provides an idea of the resource over allocation observed-
PM
Figure 2: Showing the Resource Graph and over allocated Resources
The following Gantt chart provides an idea of the resource over allocation observed-

8
PM
PM
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9
PM
Figure 3: Illustrating the Resource over allocation
Solving Resource Over allocation
The problem of resource over allocation is needed to be solved to ensure every resource
works for 8 hours a day. The resource over allocation is occurring in the schedule mainly
because few resources are allocated to the summary tasks. Therefore, the resources are to be
freed from the summary task. Since each of the individual tasks are allocated with a particular
resource, the resources from the summary task can be freed to solve the problem of resource over
allocation-
PM
Figure 3: Illustrating the Resource over allocation
Solving Resource Over allocation
The problem of resource over allocation is needed to be solved to ensure every resource
works for 8 hours a day. The resource over allocation is occurring in the schedule mainly
because few resources are allocated to the summary tasks. Therefore, the resources are to be
freed from the summary task. Since each of the individual tasks are allocated with a particular
resource, the resources from the summary task can be freed to solve the problem of resource over
allocation-
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10
PM
PM

11
PM
Figure 4: Illustrating that solving of resource over allocation
The problem of resource over allocation is solved by freeing the resources that are
assigned to the summary task. Allocation of the resources to summary task is not mandatory in
this project since specific resources are allocated for each of the individual task.
Conclusion
The report provides an overview of the resource needs of the Mamma’s Bakery project.
On basis of the WBS developed, the resources are assigned to each of the task. The report
provides an evidence of the resource allocation and solving the problem of resource over
allocation to ensure that each resource works for a maximum of 8 hours per day.
PM
Figure 4: Illustrating that solving of resource over allocation
The problem of resource over allocation is solved by freeing the resources that are
assigned to the summary task. Allocation of the resources to summary task is not mandatory in
this project since specific resources are allocated for each of the individual task.
Conclusion
The report provides an overview of the resource needs of the Mamma’s Bakery project.
On basis of the WBS developed, the resources are assigned to each of the task. The report
provides an evidence of the resource allocation and solving the problem of resource over
allocation to ensure that each resource works for a maximum of 8 hours per day.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 14
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.