This report provides a comprehensive analysis of project scope and schedule management in the context of designing a vehicle maintenance facility. The project aims to create a facility for servicing and parking corporate vehicles, including high bay spaces, service bays, offices, and training areas. The report outlines the project's goals and objectives, which center on providing superior service quality, consumer satisfaction, and optimizing space. It includes a detailed project scope statement, a work breakdown structure (WBS) outlining tasks across initiation, planning, execution, and closing phases, and a project schedule with task durations, dependencies, and resource allocation. The report also covers key elements like communication and change management plans, emphasizing the importance of stakeholder involvement and efficient project execution to ensure the successful design and implementation of the vehicle maintenance facility.

Running head: ANALYSIS OF PROJECT SCOPE AND SCHEDULE MANAGEMENT
ANALYSIS OF PROJECT SCOPE AND SCHEDULE MANAGEMENT
Name of student
Name of university
Author’s note:
ANALYSIS OF PROJECT SCOPE AND SCHEDULE MANAGEMENT
Name of student
Name of university
Author’s note:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1ANALYSIS OF PROJECT SCOPE AND SCHEDULE MANAGEMENT
Overview of project:
The purpose of this project is to design a vehicle maintenance facility that provides
maintenance services for corporate vehicles. Along with this, it will also provide parking
facility including paving and building which contains a high bay space. This area needs to be
large enough so that it is capable of parking large vehicles for example pick-up tracks along
with small vehicle for example light vans. Therefore, this area needs to be chosen properly
for effective car parking facility.
Area which is allocated for high bay space will be allocated for servicing vehicles. There will
be four service bays which contains roll-up doors at both ends as well. Along with this space
there will be also an attached office and area allocated for training of employees as well. This
is to ensure that servicing is of high quality and ensure consumer satisfaction as well.
Project goals and objectives:
Goals and objectives are two of the most important aspects that provided strategic direction to
a project and this is what ensures success in a project (Kerzner, 2017). Therefore, it is
important to define project goals and objectives before initiating a project (Whitaker, 2016).
Therefore, in this context, goals and objectives of this project are described in details to
provide a comprehensive idea regarding what this project is trying to achieve and how it will
be achieved through application of proper strategies (Sanghera, 2019).
Goals of this project:
The goal of this project is to design a vehicle maintenance facility which not only ensures
superior service quality but to offer consumer value for money for services that they obtain
from this organization. It is to ensure consumer satisfaction and establish this organization
one of the leading service provider for corporate vehicle maintenance facility as well.
Overview of project:
The purpose of this project is to design a vehicle maintenance facility that provides
maintenance services for corporate vehicles. Along with this, it will also provide parking
facility including paving and building which contains a high bay space. This area needs to be
large enough so that it is capable of parking large vehicles for example pick-up tracks along
with small vehicle for example light vans. Therefore, this area needs to be chosen properly
for effective car parking facility.
Area which is allocated for high bay space will be allocated for servicing vehicles. There will
be four service bays which contains roll-up doors at both ends as well. Along with this space
there will be also an attached office and area allocated for training of employees as well. This
is to ensure that servicing is of high quality and ensure consumer satisfaction as well.
Project goals and objectives:
Goals and objectives are two of the most important aspects that provided strategic direction to
a project and this is what ensures success in a project (Kerzner, 2017). Therefore, it is
important to define project goals and objectives before initiating a project (Whitaker, 2016).
Therefore, in this context, goals and objectives of this project are described in details to
provide a comprehensive idea regarding what this project is trying to achieve and how it will
be achieved through application of proper strategies (Sanghera, 2019).
Goals of this project:
The goal of this project is to design a vehicle maintenance facility which not only ensures
superior service quality but to offer consumer value for money for services that they obtain
from this organization. It is to ensure consumer satisfaction and establish this organization
one of the leading service provider for corporate vehicle maintenance facility as well.

2ANALYSIS OF PROJECT SCOPE AND SCHEDULE MANAGEMENT
Objectives of this project:
Design a vehicle maintenance facility that optimizes spaces for effective service:
In order to ensure service quality, it is important to provide quality service faster so that
consumers get their vehicles serviced quickly and for this large service space will be
allocated for servicing of vehicles as well.
Ensure quality in servicing:
In order to quality to serving, employee training is of prime importance and this is why it is
essential. Objective of this project is to allow on-site training. Therefore, facility of training
will be provided by allocating space while designing this vehicle maintenance facility.
Reduce time for vehicle registration and process consumer servicing requirements
quickly:
This is an important objective regarding enhancement of consumer satisfaction which is
required for obtaining goal of this project as described in this context. Therefore, space will
be allocated for an attached office so that process of registration is not only faster but it also
requires less time for processing service requirements of consumers as well.
Project scope statement:
In this project, plan for designing a vehicle maintenance facility for providing maintenance
services for corporate vehicles. Along with this, a plan will be also provided regarding how to
provide an effective parking facility that also includes paving and building including a high
bay space. This area will be optimized so that it is capable of parking large vehicles which
include pick-up tracks along with small vehicle for example light vans.
In order to ensure effective implementation for project strategies, a communication plan will
be provided so that it is easier to communicate project requirements and strategies with
Objectives of this project:
Design a vehicle maintenance facility that optimizes spaces for effective service:
In order to ensure service quality, it is important to provide quality service faster so that
consumers get their vehicles serviced quickly and for this large service space will be
allocated for servicing of vehicles as well.
Ensure quality in servicing:
In order to quality to serving, employee training is of prime importance and this is why it is
essential. Objective of this project is to allow on-site training. Therefore, facility of training
will be provided by allocating space while designing this vehicle maintenance facility.
Reduce time for vehicle registration and process consumer servicing requirements
quickly:
This is an important objective regarding enhancement of consumer satisfaction which is
required for obtaining goal of this project as described in this context. Therefore, space will
be allocated for an attached office so that process of registration is not only faster but it also
requires less time for processing service requirements of consumers as well.
Project scope statement:
In this project, plan for designing a vehicle maintenance facility for providing maintenance
services for corporate vehicles. Along with this, a plan will be also provided regarding how to
provide an effective parking facility that also includes paving and building including a high
bay space. This area will be optimized so that it is capable of parking large vehicles which
include pick-up tracks along with small vehicle for example light vans.
In order to ensure effective implementation for project strategies, a communication plan will
be provided so that it is easier to communicate project requirements and strategies with
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3ANALYSIS OF PROJECT SCOPE AND SCHEDULE MANAGEMENT
stakeholders. Along with this, a change management plan will be provided for managing
changes in this project.
However, obtaining licences and approval for this project from required authorities are not
considered in this project scope (Meredith, Mantel Jr & Shafer, 2017). Therefore, this any
necessary approval for this project including acquiring land for this project needs to be
ensured by project authority so that it does not affect implementation of this project. It is an
important requirement for this project and therefore, it needs to be considered as well
(Whitaker, 2016).
Work Breakdown Structure (WBS):
Level WBS Task Name Start Finish
1
1
Design of a vehicle
maintenance facility
Mon 23-03-20 Thu 19-11-20
2 1.1 Initiation phase Mon 23-03-20 Thu 09-04-20
3
1.1.1
obtaining information
regarding project requirements
Mon 23-03-20 Wed 25-03-20
3
1.1.2
analysis project
requirements
Thu 26-03-20 Wed 01-04-20
3
1.1.3
providing scope of the
project
Thu 02-04-20 Mon 06-04-20
3 1.1.4 estimation of project time Tue 07-04-20 Tue 07-04-20
stakeholders. Along with this, a change management plan will be provided for managing
changes in this project.
However, obtaining licences and approval for this project from required authorities are not
considered in this project scope (Meredith, Mantel Jr & Shafer, 2017). Therefore, this any
necessary approval for this project including acquiring land for this project needs to be
ensured by project authority so that it does not affect implementation of this project. It is an
important requirement for this project and therefore, it needs to be considered as well
(Whitaker, 2016).
Work Breakdown Structure (WBS):
Level WBS Task Name Start Finish
1
1
Design of a vehicle
maintenance facility
Mon 23-03-20 Thu 19-11-20
2 1.1 Initiation phase Mon 23-03-20 Thu 09-04-20
3
1.1.1
obtaining information
regarding project requirements
Mon 23-03-20 Wed 25-03-20
3
1.1.2
analysis project
requirements
Thu 26-03-20 Wed 01-04-20
3
1.1.3
providing scope of the
project
Thu 02-04-20 Mon 06-04-20
3 1.1.4 estimation of project time Tue 07-04-20 Tue 07-04-20
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4ANALYSIS OF PROJECT SCOPE AND SCHEDULE MANAGEMENT
3
1.1.5
estimation of project
budget
Thu 02-04-20 Mon 06-04-20
3
1.1.6
obtaining land for the
project
Tue 07-04-20 Thu 09-04-20
3
1.1.7
Milestone 1: initiation
phase complete
Thu 09-04-20 Thu 09-04-20
4
1.2
Planning phase and design
of prototype
Fri 10-04-20 Mon 06-07-20
5 1.2.1 Project plan design Fri 10-04-20 Tue 21-04-20
5 1.2.2 Resource plan Wed 22-04-20 Fri 24-04-20
5 1.2.3 Financial plan Mon 27-04-20 Tue 28-04-20
5 1.2.4 Quality plan Wed 29-04-20 Fri 08-05-20
5 1.2.5 Risk management plan Mon 11-05-20 Tue 12-05-20
5 1.2.6 Acceptance plan Wed 13-05-20 Thu 14-05-20
5 1.2.7 Communication plan Fri 15-05-20 Fri 15-05-20
5
1.2.8
Procurement of
construction materials
Mon 18-05-20 Wed 27-05-20
5 1.2.9 designing prototype Thu 28-05-20 Mon 29-06-20
5 1.2.10 analysing prototype Tue 30-06-20 Mon 06-07-20
5 1.2.11 Milestone 2: Completion Mon 06-07-20 Mon 06-07-20
3
1.1.5
estimation of project
budget
Thu 02-04-20 Mon 06-04-20
3
1.1.6
obtaining land for the
project
Tue 07-04-20 Thu 09-04-20
3
1.1.7
Milestone 1: initiation
phase complete
Thu 09-04-20 Thu 09-04-20
4
1.2
Planning phase and design
of prototype
Fri 10-04-20 Mon 06-07-20
5 1.2.1 Project plan design Fri 10-04-20 Tue 21-04-20
5 1.2.2 Resource plan Wed 22-04-20 Fri 24-04-20
5 1.2.3 Financial plan Mon 27-04-20 Tue 28-04-20
5 1.2.4 Quality plan Wed 29-04-20 Fri 08-05-20
5 1.2.5 Risk management plan Mon 11-05-20 Tue 12-05-20
5 1.2.6 Acceptance plan Wed 13-05-20 Thu 14-05-20
5 1.2.7 Communication plan Fri 15-05-20 Fri 15-05-20
5
1.2.8
Procurement of
construction materials
Mon 18-05-20 Wed 27-05-20
5 1.2.9 designing prototype Thu 28-05-20 Mon 29-06-20
5 1.2.10 analysing prototype Tue 30-06-20 Mon 06-07-20
5 1.2.11 Milestone 2: Completion Mon 06-07-20 Mon 06-07-20

5ANALYSIS OF PROJECT SCOPE AND SCHEDULE MANAGEMENT
of planning phase
1.3 Execution phase Tue 07-07-20 Fri 13-11-20
1.3.1 preparing lot for building Tue 07-07-20 Wed 29-07-20
1.3.2 foundation layout Thu 30-07-20 Tue 18-08-20
1.3.3 completing house framing Wed 19-08-20 Thu 10-09-20
1.3.4 roof building Fri 11-09-20 Wed 30-09-20
1.3.5
Siding, wiring, and
plumbing
Thu 01-10-20 Fri 23-10-20
1.3.6 System integration review Mon 26-10-20 Mon 26-10-20
1.3.7 Interior finishing Tue 27-10-20 Fri 13-11-20
1.3.8
Milestone 3: Completion
of execution phase
Fri 13-11-20 Fri 13-11-20
1.4 Closing phase Mon 16-11-20 Thu 19-11-20
1.4.1 Post project review Mon 16-11-20 Tue 17-11-20
1.4.2 Stakeholder sign off Wed 18-11-20 Wed 18-11-20
1.4.3 Post go-live support Thu 19-11-20 Thu 19-11-20
1.4.4
Milestone 4: Completion
of closure phase
Thu 19-11-20 Thu 19-11-20
of planning phase
1.3 Execution phase Tue 07-07-20 Fri 13-11-20
1.3.1 preparing lot for building Tue 07-07-20 Wed 29-07-20
1.3.2 foundation layout Thu 30-07-20 Tue 18-08-20
1.3.3 completing house framing Wed 19-08-20 Thu 10-09-20
1.3.4 roof building Fri 11-09-20 Wed 30-09-20
1.3.5
Siding, wiring, and
plumbing
Thu 01-10-20 Fri 23-10-20
1.3.6 System integration review Mon 26-10-20 Mon 26-10-20
1.3.7 Interior finishing Tue 27-10-20 Fri 13-11-20
1.3.8
Milestone 3: Completion
of execution phase
Fri 13-11-20 Fri 13-11-20
1.4 Closing phase Mon 16-11-20 Thu 19-11-20
1.4.1 Post project review Mon 16-11-20 Tue 17-11-20
1.4.2 Stakeholder sign off Wed 18-11-20 Wed 18-11-20
1.4.3 Post go-live support Thu 19-11-20 Thu 19-11-20
1.4.4
Milestone 4: Completion
of closure phase
Thu 19-11-20 Thu 19-11-20
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6ANALYSIS OF PROJECT SCOPE AND SCHEDULE MANAGEMENT
Project schedule:
Task
Mode
WBS Task Name
Duratio
n
Start Finish Predecessors Resource Names
Auto
Scheduled
1
design of a new
warehouse
system
174
days
Mon
23-
03-20
Thu
19-11-
20
Auto
Scheduled
1.1
Initiation
phase
14 days
Mon
23-
03-20
Thu
09-04-
20
Auto
Scheduled
1.1.1
obtaining
information
regarding project
requirements
3 days
Mon
23-
03-20
Wed
25-03-
20
project manager
Auto
Scheduled
1.1.2
analysis
project
requirements
5 days
Thu
26-
03-20
Wed
01-04-
20
3 project manager
Auto
Scheduled
1.1.3
providing
scope of the
project
3 days
Thu
02-
04-20
Mon
06-04-
20
4 project manager
Auto
Scheduled
1.1.4
estimation of
project time
1 day
Tue
07-
04-20
Tue
07-04-
20
5 project manager
Auto 1.1.5 estimation of 3 days Thu Mon 4 project manager
Project schedule:
Task
Mode
WBS Task Name
Duratio
n
Start Finish Predecessors Resource Names
Auto
Scheduled
1
design of a new
warehouse
system
174
days
Mon
23-
03-20
Thu
19-11-
20
Auto
Scheduled
1.1
Initiation
phase
14 days
Mon
23-
03-20
Thu
09-04-
20
Auto
Scheduled
1.1.1
obtaining
information
regarding project
requirements
3 days
Mon
23-
03-20
Wed
25-03-
20
project manager
Auto
Scheduled
1.1.2
analysis
project
requirements
5 days
Thu
26-
03-20
Wed
01-04-
20
3 project manager
Auto
Scheduled
1.1.3
providing
scope of the
project
3 days
Thu
02-
04-20
Mon
06-04-
20
4 project manager
Auto
Scheduled
1.1.4
estimation of
project time
1 day
Tue
07-
04-20
Tue
07-04-
20
5 project manager
Auto 1.1.5 estimation of 3 days Thu Mon 4 project manager
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7ANALYSIS OF PROJECT SCOPE AND SCHEDULE MANAGEMENT
Scheduled project budget
02-
04-20
06-04-
20
Auto
Scheduled
1.1.6
obtaining
land for the
project
3 days
Tue
07-
04-20
Thu
09-04-
20
7 project manager
Auto
Scheduled
1.1.7
Milestone 1:
initiation phase
complete
0 days
Thu
09-
04-20
Thu
09-04-
20
8
Auto
Scheduled
1.2
Planning
phase and
design of
prototype
62 days
Fri
10-
04-20
Mon
06-07-
20
Auto
Scheduled
1.2.1
Project plan
design
8 days
Fri
10-
04-20
Tue
21-04-
20
9 project manager
Auto
Scheduled
1.2.2
Resource
plan
3 days
Wed
22-
04-20
Fri 24-
04-20
11 project manager
Auto
Scheduled
1.2.3
Financial
plan
2 days
Mon
27-
04-20
Tue
28-04-
20
12 project manager
Auto
Scheduled
1.2.4 Quality plan 8 days Wed
29-
Fri 08- 13 project manager
Scheduled project budget
02-
04-20
06-04-
20
Auto
Scheduled
1.1.6
obtaining
land for the
project
3 days
Tue
07-
04-20
Thu
09-04-
20
7 project manager
Auto
Scheduled
1.1.7
Milestone 1:
initiation phase
complete
0 days
Thu
09-
04-20
Thu
09-04-
20
8
Auto
Scheduled
1.2
Planning
phase and
design of
prototype
62 days
Fri
10-
04-20
Mon
06-07-
20
Auto
Scheduled
1.2.1
Project plan
design
8 days
Fri
10-
04-20
Tue
21-04-
20
9 project manager
Auto
Scheduled
1.2.2
Resource
plan
3 days
Wed
22-
04-20
Fri 24-
04-20
11 project manager
Auto
Scheduled
1.2.3
Financial
plan
2 days
Mon
27-
04-20
Tue
28-04-
20
12 project manager
Auto
Scheduled
1.2.4 Quality plan 8 days Wed
29-
Fri 08- 13 project manager

8ANALYSIS OF PROJECT SCOPE AND SCHEDULE MANAGEMENT
04-20 05-20
Auto
Scheduled
1.2.5
Risk
management
plan
2 days
Mon
11-
05-20
Tue
12-05-
20
14 project manager
Auto
Scheduled
1.2.6
Acceptance
plan
2 days
Wed
13-
05-20
Thu
14-05-
20
15 project manager
Auto
Scheduled
1.2.7
Communicati
on plan
1 day
Fri
15-
05-20
Fri 15-
05-20
16 project manager
Auto
Scheduled
1.2.8
Procurement
of construction
materials
8 days
Mon
18-
05-20
Wed
27-05-
20
17
project manager,
procurement
manager
Auto
Scheduled
1.2.9
designing
prototype
23 days
Thu
28-
05-20
Mon
29-06-
20
18 architecture
Auto
Scheduled
1.2.10
analysing
prototype
5 days
Tue
30-
06-20
Mon
06-07-
20
19 architecture
Auto
Scheduled
1.2.11
Milestone 2:
Completion of
planning phase
0 days
Mon
06-
07-20
Mon
06-07-
20
20
04-20 05-20
Auto
Scheduled
1.2.5
Risk
management
plan
2 days
Mon
11-
05-20
Tue
12-05-
20
14 project manager
Auto
Scheduled
1.2.6
Acceptance
plan
2 days
Wed
13-
05-20
Thu
14-05-
20
15 project manager
Auto
Scheduled
1.2.7
Communicati
on plan
1 day
Fri
15-
05-20
Fri 15-
05-20
16 project manager
Auto
Scheduled
1.2.8
Procurement
of construction
materials
8 days
Mon
18-
05-20
Wed
27-05-
20
17
project manager,
procurement
manager
Auto
Scheduled
1.2.9
designing
prototype
23 days
Thu
28-
05-20
Mon
29-06-
20
18 architecture
Auto
Scheduled
1.2.10
analysing
prototype
5 days
Tue
30-
06-20
Mon
06-07-
20
19 architecture
Auto
Scheduled
1.2.11
Milestone 2:
Completion of
planning phase
0 days
Mon
06-
07-20
Mon
06-07-
20
20
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9ANALYSIS OF PROJECT SCOPE AND SCHEDULE MANAGEMENT
Auto
Scheduled
1.3
Execution
phase
94 days
Tue
07-
07-20
Fri 13-
11-20
Auto
Scheduled
1.3.1
preparing lot
for building
17 days
Tue
07-
07-20
Wed
29-07-
20
20 construction team
Auto
Scheduled
1.3.2
foundation
layout
14 days
Thu
30-
07-20
Tue
18-08-
20
23 construction team
Auto
Scheduled
1.3.3
completing
house framing
17 days
Wed
19-
08-20
Thu
10-09-
20
24 construction team
Auto
Scheduled
1.3.4 roof building 14 days
Fri
11-
09-20
Wed
30-09-
20
25 construction team
Auto
Scheduled
1.3.5
Siding,
wiring, and
plumbing
17 days
Thu
01-
10-20
Fri 23-
10-20
26 construction team
Auto
Scheduled
1.3.6
System
integration
review
1 day
Mon
26-
10-20
Mon
26-10-
20
27
construction
engineer
Auto
Scheduled
1.3.7 Interior
finishing
14 days Tue
27-
Fri 13- 28 interior designer
Auto
Scheduled
1.3
Execution
phase
94 days
Tue
07-
07-20
Fri 13-
11-20
Auto
Scheduled
1.3.1
preparing lot
for building
17 days
Tue
07-
07-20
Wed
29-07-
20
20 construction team
Auto
Scheduled
1.3.2
foundation
layout
14 days
Thu
30-
07-20
Tue
18-08-
20
23 construction team
Auto
Scheduled
1.3.3
completing
house framing
17 days
Wed
19-
08-20
Thu
10-09-
20
24 construction team
Auto
Scheduled
1.3.4 roof building 14 days
Fri
11-
09-20
Wed
30-09-
20
25 construction team
Auto
Scheduled
1.3.5
Siding,
wiring, and
plumbing
17 days
Thu
01-
10-20
Fri 23-
10-20
26 construction team
Auto
Scheduled
1.3.6
System
integration
review
1 day
Mon
26-
10-20
Mon
26-10-
20
27
construction
engineer
Auto
Scheduled
1.3.7 Interior
finishing
14 days Tue
27-
Fri 13- 28 interior designer
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10ANALYSIS OF PROJECT SCOPE AND SCHEDULE MANAGEMENT
10-20 11-20
Auto
Scheduled
1.3.8
Milestone 3:
Completion of
execution phase
0 days
Fri
13-
11-20
Fri 13-
11-20
29
Auto
Scheduled
1.4 Closing phase 4 days
Mon
16-
11-20
Thu
19-11-
20
Auto
Scheduled
1.4.1
Post project
review
2 days
Mon
16-
11-20
Tue
17-11-
20
30 project manager
Auto
Scheduled
1.4.2
Stakeholder
sign off
1 day
Wed
18-
11-20
Wed
18-11-
20
32 project manager
Auto
Scheduled
1.4.3
Post go-live
support
1 day
Thu
19-
11-20
Thu
19-11-
20
33 project manager
Auto
Scheduled
1.4.4
Milestone 4:
Completion of
closure phase
0 days
Thu
19-
11-20
Thu
19-11-
20
34
10-20 11-20
Auto
Scheduled
1.3.8
Milestone 3:
Completion of
execution phase
0 days
Fri
13-
11-20
Fri 13-
11-20
29
Auto
Scheduled
1.4 Closing phase 4 days
Mon
16-
11-20
Thu
19-11-
20
Auto
Scheduled
1.4.1
Post project
review
2 days
Mon
16-
11-20
Tue
17-11-
20
30 project manager
Auto
Scheduled
1.4.2
Stakeholder
sign off
1 day
Wed
18-
11-20
Wed
18-11-
20
32 project manager
Auto
Scheduled
1.4.3
Post go-live
support
1 day
Thu
19-
11-20
Thu
19-11-
20
33 project manager
Auto
Scheduled
1.4.4
Milestone 4:
Completion of
closure phase
0 days
Thu
19-
11-20
Thu
19-11-
20
34

11ANALYSIS OF PROJECT SCOPE AND SCHEDULE MANAGEMENT
References:
Kerzner, H. (2017). Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Meredith, J. R., Mantel Jr, S. J., & Shafer, S. M. (2017). Project management: a managerial
approach. John Wiley & Sons.
Sanghera, P. (2019). Project Scope Management. In CAPM® in Depth (pp. 135-171). Apress,
Berkeley, CA.
Whitaker, S. (2016). Scope Management. In Pass the PMP® Exam (pp. 91-131). Apress,
Berkeley, CA.
Whitaker, S. (2016). Scope Management. In Pass the PMP® Exam (pp. 91-131). Apress,
Berkeley, CA.
References:
Kerzner, H. (2017). Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Meredith, J. R., Mantel Jr, S. J., & Shafer, S. M. (2017). Project management: a managerial
approach. John Wiley & Sons.
Sanghera, P. (2019). Project Scope Management. In CAPM® in Depth (pp. 135-171). Apress,
Berkeley, CA.
Whitaker, S. (2016). Scope Management. In Pass the PMP® Exam (pp. 91-131). Apress,
Berkeley, CA.
Whitaker, S. (2016). Scope Management. In Pass the PMP® Exam (pp. 91-131). Apress,
Berkeley, CA.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 12
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.