Project Management: Security in Major International Competition

Verified

Added on  2022/08/13

|4
|709
|42
Project
AI Summary
This project focuses on the application of project management principles to ensure security in major international sporting events. It begins with a detailed Work Breakdown Structure (WBS) that outlines the project's phases, including initiation, planning, execution, and closing. The WBS breaks down the project into manageable tasks with durations, start and finish dates, and predecessors, providing a clear roadmap for the project's lifecycle. The project objectives include providing security to venues, transit systems, increasing the number of recruits, and training them to specific security standards. The project involves requirement analysis, event review, team meetings, venue and security requirement reviews, abstract plan creation, and approval from the governing body. The planning phase includes project charter development, scope definition, objective and goal setting, budget and risk assessments, and a complete project plan. Execution involves recruiting and training security personnel, including weapons and firearms training, evaluation, and full-time hiring. The closing phase includes review, deployment orders, project documentation, and sign-off. The project provides a comprehensive approach to managing security in large-scale sporting events, ensuring the safety of players, staff, and spectators. The project concludes with a bibliography of relevant project management resources.
Document Page
Running Head: PROJECT MANAGEMENT
Security in Major International Sporting Competition
Name of the Student
Name of the University
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1PROJECT MANAGEMENT
Work Breakdown Structure
Very often, due to the complex or long nature of a project, it is required to break it down
to simpler work packages for the convenience of planning, scheduling, budgeting or even for the
team members who will work in the project. For example, if a contractor is told to build just a
house, it will be difficult for him to undertake but if he told to develop the design of the house as
per certain specifications, plan for the construction as per design and then proceed to
construction of the house, it will be much more easier for him to understand and execute the
project. This role of breaking down the project for the purpose of working on separate work
packages that can be scheduled and budgeted individually is fulfilled by the work breakdown
structure, which is developed, considering the given case study, as shown in the following table.
WBS Task Name Duration Start Finish Predecessor
s
0 Security in International Sporting Event 162 days Mon 01-06-20 Tue 12-01-21
1 Project Initiation 22 days Mon 01-06-20 Tue 30-06-20
1.1 Requirement Analysis 4 days Mon 01-06-20 Thu 04-06-20
1.2 Review the Nature of the Event 4 days Fri 05-06-20 Wed 10-06-20 2
1.3 Team Meeting Regarding Security 3 days Thu 11-06-20 Mon 15-06-20 3
1.4 Review List of Venues for the Sporting Event 4 days Tue 16-06-20 Fri 19-06-20 4
1.5 Review Security Requirements 2 days Mon 22-06-20 Tue 23-06-20 5
1.6 Create an Abstract Plan for the Security 5 days Wed 24-06-20 Tue 30-06-20 6
1.7 Get Approval from the Governing Body 0 days Tue 30-06-20 Tue 30-06-20 7
2 Project Planning 20 days Wed 01-07-20 Tue 28-07-20
2.1 Project Charter Development 5 days Wed 01-07-20 Tue 07-07-20 8
2.2 Defining Scope of the Project 2 days Wed 08-07-20 Thu 09-07-20 10
2.3 Defining Objectives and Goals of the Project 2 days Fri 10-07-20 Mon 13-07-20 11
Document Page
2PROJECT MANAGEMENT
2.4 Assessment of Overall Budget of the Project 3 days Tue 14-07-20 Thu 16-07-20 12
2.5 Assessment of Possible Risks in the Project 3 days Fri 17-07-20 Tue 21-07-20 13
2.6 Development of Complete Project Plan 5 days Wed 22-07-20 Tue 28-07-20 14
3 Project Execution 95 days Wed 29-07-20 Tue 08-12-20
3.1 Recruitment of Trainees for the Security Services 15 days Wed 29-07-20 Tue 18-08-20 15
3.2 Training of the Recruits as per Security Standards and
Guidelines 45 days Wed 19-08-20 Tue 20-10-20 17
3.3 Training with Weapons and Firearms 15 days Wed 21-10-20 Tue 10-11-20 18
3.4 Evaluation 10 days Wed 11-11-20 Tue 24-11-20 19
3.5 Hire Full Time 10 days Wed 25-11-20 Tue 08-12-20 20
4 Project Closing 25 days Wed 09-12-20 Tue 12-01-21
4.1 Review the Training Process 5 days Wed 09-12-20 Tue 15-12-20 21
4.2 Send Out Deployment Orders for the Newly Trained
Security Personnel 10 days Wed 16-12-20 Tue 29-12-20 23
4.3 Documentation of the Project 10 days Wed 30-12-20 Tue 12-01-21 24
4.4 Sign Off and Closing 0 days Tue 12-01-21 Tue 12-01-21 25
Project Objectives
The main objectives of the project are as follows.
To provide security to the sporting event venues for the players, staff and
spectators
To provide security and assistance in the nearby roadways and other transit
systems
To increase the number of recruits in the security ranks in the city
To train the new recruits in security as per specifications
To allocate the newly trained recruits in various venues of the sports event
Document Page
3PROJECT MANAGEMENT
Bibliography
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach.
Routledge.
Heagney, J. (2016). Fundamentals of project management. Amacom.
Kerzner, H. (2017). Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Meredith, J. R., Mantel Jr, S. J., & Shafer, S. M. (2017). Project management: a managerial
approach. John Wiley & Sons.