This project report details the implementation of a self-checkout system at GT Smith, focusing on the business case, project phases, and challenges. The project aims to reduce customer waiting times, minimize costs, and improve inventory management by implementing self-checkout machines using RFID technology. The report outlines key deliverables, including machine installation, staff training, and a marketing strategy. It also addresses challenges such as funding issues and technical problems, proposing solutions like outsourcing and expert consultation. The project timeline includes initiation, planning, analysis, execution, monitoring, and close-out phases, with specific durations for each. The report concludes with a project success assessment and a list of references. This assignment provides a comprehensive overview of the project management process from inception to completion.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
PROJECT MANAGEMENT
Self-Checkout system in GT Smith
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Business case
Currently, in GT Smith, users have to stay in long queue to complete their
transactions which increase their waiting time.
Thus, by advancement through self-checkout system, every customer will be able
to create bill of item and goods purchased and pay it.
The development of self-service system by the use of RFID (Radio Frequency
Identification) will enable GT smith to rise its competitive success.
Document Page
Self-Checkout system
Self-checkout/self-service system in supermarkets is increasingly used by many
British supermarkets to reduce their costs and boost service efficiency.
Customers frequently visit in the retail outlets and use self-service machines to
pay bills of their basket without wasting time.
Document Page
Key benefits
Reduce waiting time at the point of checkout
Minimize wages costs
Effective inventory management
Maximize revenue
Improve brand reputation
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Key deliverables
Installation of 2 self-checkout machines in Kottingley because, it is the largest
size supermarket of GT smith while one machinery will be placed at Meanwood,
Ackworth, Outwood, and Pontefract
Trained staff base to teach patrons about machinery usage
A well-structured marketing strategy to maximize patron awareness
Document Page
Work breakdown structure
Document Page
Critical challenges
Lack of enough funds for execution due to sudden death of Bill
Ineffective results of training
Liberal monitoring over workers
Delay supply of Self-checkout machine by contractors
Poor technical functioning
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Actions to overcome challenges
Although sudden accident of Bill brought possibility of financial turbulence, but, through
outsourcing the experienced manager, project manager successfully overcome such
challenging situation.
Moreover, in order to hire new financial manager, more staffing costs is required, still,
proficient knowledge and strict control over monetary usage helps to achieve project goals
successfully.
IT expert has vast knowledge which helps to combat technical functioning issues and
errors in the system.
Document Page
Contd.
As specialist trainers were being hire help to train and educate all the people
excellently.
Project progress report assessment helps in improving control over staff to assure
timely installation of the self-checkout machinery.
In order to overcome possibility of delay supply, supplier has been contacted
before the due date of purchase to get deliveries on time.
Document Page
Project success: Milestone achievment
Task Name Duration Start Finish
Self-checkout system in GT Smith 119 days 1/1/2018 6/14/2018
Business case/Initiation 6 days 1/1/2018 1/8/2018
Planning 15 days 1/8/2018 1/26/2018
Analysis 4 days 1/11/2018 1/16/2018
Execution 85 days 1/17/2018 5/15/2018
Monitoring and controlling 20 days 5/15/2018 6/11/2018
Close-out 3 days 6/12/2018 6/14/2018
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
REFERENCES
McLaughlin, S. B. and Shriner, D. S., 2012. Allocation of resources to defense and repair. Plant
disease. 5. pp.407-431.
Morris, S. and et.al, 2012. Method and system for allocation of resources in a project portfolio.
U.S. Patent 8,214,240.
Petit, Y., 2012. Project portfolios in dynamic environments: Organizing for
uncertainty. International Journal of Project Management. 30(5). pp.539-553.
Document Page
Thank You!
chevron_up_icon
1 out of 12
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]