PM592 Week 5: Earned Value Analysis and Variance Calculation

Verified

Added on  2023/06/10

|7
|636
|293
Homework Assignment
AI Summary
This assignment provides a detailed analysis of Earned Value Management (EVM) techniques, specifically focusing on the calculation and interpretation of cost and schedule variances. The solution includes the calculation of Planned Value (PV), Earned Value (EV), Actual Cost (AC), Schedule Variance (SV), Cost Variance (CV), Schedule Performance Index (SPI), and Cost Performance Index (CPI) for two project scenarios. The first scenario (5.1) presents a project with four activities, calculating the EVM metrics and providing an interpretation of the results. The second scenario (5.2) extends the analysis to four different projects (A, B, C, and D), comparing their performance based on EVM metrics. The assignment includes a summary of the calculations, identifies project problems (delays, over budget), and offers recommendations for improvement, such as utilizing more resources, employing effective schedule planners, and applying project management principles for change and control management. The overall goal is to demonstrate an understanding of EVM's role in project monitoring and control, highlighting how it helps in identifying and addressing project deviations.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
EARNED VALUE
ANALYSIS
Name of the Student:
Student ID:
Name of the University:
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
CALCULATION OF COST AND
SCHEDULE VARIANCES
Calculation of planned and earned values, actual cost, and cost &
schedule variances
Schedule Performance Index and Cost Performance Index would also
be analyzed
Outcomes,
For 5.1 BAC = $810,000, PV = $445,000, EV = $421,200, AC =
$395,000, SV = EV – PV = -$23,800, CV = EV – AC = $26,200, SPI =
EV / PV = 0.95, CPI = EV / AC = 1.07
For 5.2 Project
A
Project
B
Project C Project
D
Project
BAC $250,000 $190,000 $250,000 $500,000 $1,190,00
0
PV $117,500 $95,000 $300,000 $335,000 $876,000
EV $125,000 $123,500 $250,000 $275,000 $773,500
AC $165,000 $150,000 $200,000 $350,000 $865,000.0
0
SV $7,500 $28,500 -$50,000 -$60,000 -
$74,000.00
CV -$40,000 -$26,500 $50,000 -$75,000 -
Document Page
SUMMARY AND REVIEW OF
CALCULATION OF 5.1
Calculation of 5.1 was based on the expected and actual cost of
the project activities (A, B, C, and D)
Expected budget for activity A was $150,000, activity B was
$100,000, activity C was $110,000, and activity D was $450,000
Total BAC for the project was $810,000
The SV, CV, SPI, and CPI has been calculated with the help of
calculating the PV, EV, and AC
SV value has been negative for the project and CV value for the
project is positive
The negative value has shown that project is behind schedule and
the positive value has shown that the project is cost effective
Document Page
PROBLEMS AND RECOMMENDATIONS
OF PROJECT OF 5.1
The problems of project was the delay in execution of the project
activities
The delay in project can result in forming the issues for the project
execution
The delay of the project can be sorted out by using more
resources
The project is ahead in terms of cost and hence, the extra saved
resources can be utilized for gaining the time lapsed
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
SUMMARY AND REVIEW OF
CALCULATION OF 5.2
Calculation of 5.2 was based on the expected and actual cost of
the project activities (A, B, C, and D)
Expected budget for activity A was $250,000, activity B was
$190,000, activity C was $250,000, and activity D was $500,000
Total BAC for the project was $1,910,000
The SV, CV, SPI, and CPI has been calculated with the help of
calculating the PV, EV, and AC
SV value has been negative for the project and CV value for the
project is also negative
The negative value has shown that project is behind schedule and
the negative value has shown that the project is over budget
Document Page
PROBLEMS AND RECOMMENDATIONS
OF PROJECT OF 5.2
The activities of the project had been both delayed and over budgeted
The project activities had been lagging in terms of expected work
completion
The exhaustion of the resources is another major factor that had
resulted in negative cost variance for the project
The utilization of the effective schedule planner would help in
overcoming the delay
Practically project can be completed in the estimated time duration
with minimum cost variation from the calculated value by using
project management principles of change management and control
management process
Document Page
chevron_up_icon
1 out of 7
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]