Project Management: Event Planning and Execution Project

Verified

Added on  2022/08/13

|4
|382
|15
Project
AI Summary
This project management assignment focuses on event planning, utilizing a work breakdown structure (WBS) to organize tasks, durations, and dependencies. The assignment outlines the planning, execution, and post-event review phases of an event, including creating an event team, negotiating with participants, planning activities, obtaining approvals, marketing, and managing resources. A detailed WBS is provided, breaking down the project into manageable tasks with specified durations, start and finish dates, and predecessors. The assignment also includes a network chart and a bibliography, demonstrating the application of project management principles and providing supporting references. This resource, available on Desklib, offers students a comprehensive example of project planning and execution, particularly in the context of event management.
Document Page
Running head: PROJECT MANAGEMENT
PROJECT MANAGEMENT
Name of the Student
Name of the University
Author Note
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1PROJECT MANAGEMENT
Work breakdown structure
Task Name Duration Start Finish Predecessors
Plan the
event/budget/procurement 69 days Fri 2/28/20 Wed 6/3/20
Create an events team and
participants 12 days Fri 2/28/20 Mon 3/16/20
From an executive team 3 days Fri 2/28/20 Tue 3/3/20
call musician/volunteers 3 days Wed 3/4/20 Fri 3/6/20 3
negotiate terms and
conditions with all
participants
6 days Mon 3/9/20 Mon 3/16/20
plan cost estimation 3 days Mon 3/9/20 Wed 3/11/20 4
create a security team 3 days Thu 3/12/20 Mon 3/16/20 6
Plan activities 36 days Tue 3/17/20 Tue 5/5/20
draft a program 4 days Tue 3/17/20 Fri 3/20/20 7
book venue 4 days Mon 3/23/20 Thu 3/26/20 9
obtain approval from the
council 6 days Fri 3/27/20 Fri 4/3/20 10
get the budget and grants 4 days Mon 4/6/20 Thu 4/9/20 11
advertise music festival 4 days Fri 4/10/20 Wed 4/15/20 12
print flyers 3 days Thu 4/16/20 Mon 4/20/20 13
distribute flyers 4 days Tue 4/21/20 Fri 4/24/20 14
create digital advert for
social media 4 days Mon 4/27/20 Thu 4/30/20 15
get sponsor 3 days Fri 5/1/20 Tue 5/5/20
sell ticket 3 days Fri 5/1/20 Tue 5/5/20 16
preparation for event day 21 days Wed 5/6/20 Wed 6/3/20
set up to equipment 5 days Wed 5/6/20 Tue 5/12/20 18
decorate venue 5 days Wed 5/13/20 Tue 5/19/20 20
Document Page
2PROJECT MANAGEMENT
set up food/drinks section 4 days Wed 5/20/20 Mon 5/25/20 21
Actual event day 3 days Tue 5/26/20 Thu 5/28/20
run the event 3 days Tue 5/26/20 Thu 5/28/20 22
Part event activity 4 days Fri 5/29/20 Wed 6/3/20
post event review 4 days Fri 5/29/20 Wed 6/3/20 24
Network chart
Document Page
3PROJECT MANAGEMENT
Bibliography
Ashtiani, B.N., Jiang, Q., Tayah, M., Welcker, B.L., Patton, T.G., Panvalkar, S.S. and Chan,
W.K.T., Microsoft Technology Licensing LLC, 2017. Controlling resource allocation with
automated consumption against a work breakdown structure. U.S. Patent 9,720,737.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach.
Routledge.
Lock, D., 2017. The essentials of project management. Routledge.